Post on 23-Feb-2018
7/24/2019 Ampliacin de Oficinas Purina
1/15
Id Modo de
tarea
Nombre de tarea Duracin Comienzo Fin
1 AMPLIACION Y REMODELACIN DE OFICINAS - PURINA 17.5 das 01/03/16 08:00 a.m. 22/03/16 05:00 p2 Inicio 0 das 01/03/16 08:00 a.m. 01/03/16 08:00 a.
3 TRABAJOS PROVISIONALES 4 das 01/03/16 08:00 a.m. 04/03/16 05:00 p
4 CERCO PROVISIONAL CON PANELES DE MADERA H = 2.45 1 da 02/03/16 08:00 a.m. 02/03/16 05:00 p
5 TRANSPORTE DE MATERIALES , MOVILIZACION DE EQUIPOS Y
HERRAMIENTAS A OBRAS
1 da 02/03/16 08:00 a.m. 02/03/16 05:00
p.m.6 PROTECCIN DE ZONA DE TRABAJO 1 da 01/03/16 08:00 a.m. 01/03/16 05:00 p
7 LIMPIEZA MANUAL DEL TERRENO 1 da 03/03/16 08:00 a.m. 03/03/16 05:00 p
8 TRAZO Y REPLANTEO DURANTE TODA LA OBRA 1 da 04/03/16 08:00 a.m. 04/03/16 05:00 p
9 DEMOLICIONES 2.5 das 05/03/16 08:00 a.m. 08/03/16 05:00 p
10 DEMOLICION DE ALBAILERIA Y OTROS 2.5 das 05/03/16 08:00 a.m. 08/03/16 05:00 p
11 DEMOLICION DE TABIQUE DE DRYWALL D:13CM 1 da 07/03/16 08:00 a.m. 07/03/16 05:00 p
12 DEMOLICION DE TABIQUE DE DRYWALL D:10CM 1 da 07/03/16 08:00 a.m. 07/03/16 05:00 p
13 DEMOLICION DE PISO PORCELANATO EXISTENTE 2 das 07/03/16 08:00 a.m. 08/03/16 05:00 p14 DEMOLICION DE SARDINEL DE CONCRETO EXISTENTE 1 da 05/03/16 08:00 a.m. 07/03/16 12:00 p
15 RETIRO DE PISO EXISTENTE Y ESCARIFICADO DE SUPERFICIE PARARECIBIR NUEVO ENCHAPE PORCELANATO
2 das 07/03/16 08:00 a.m. 08/03/16 05:00
p.m.
16 DESMONTAJES 0.5 das 05/03/16 08:00 a.m. 05/03/16 12:00 p
17 DESMONTAJE DE TOMACORRIENTES 2 horas 05/03/16 08:00 a.m. 05/03/16 10:00 a.
18 DESMONTAJES DE ARTEFACTOS DE ALUMBRADO 2 horas 05/03/16 10:00 a.m. 05/03/16 12:00 p
19 DESMONTAJES DE PUERTAS DE VIDRIO 2 horas 05/03/16 08:00 a.m. 05/03/16 10:00 a.
20 DESMONTAJES BALDOSAS 2 horas 05/03/16 08:00 a.m. 05/03/16 10:00 a.
21 DESMONTAJES DE VENTANAS DE VIDRIO 2 horas 05/03/16 08:00 a.m. 05/03/16 10:00 a.
22 DESMONTAJE DE PISO ALFOMBRADO 2 horas 05/03/16 10:00 a.m. 05/03/16 12:00 p
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tarea inactiva
Hito inactivo
Resumen inactivo
Tarea manual
solo duracin
Informe de resumen manual
Resumen manual
solo el comienzo
solo fin
Tareas externas
Hito externo
Fecha lmite
Tareas crticas
Divisin crtica
Progreso
Progreso manual
Pgina 1
Proyecto: Ampliacin de oficina
Fecha: 23/02/16 06:01 p.m.
7/24/2019 Ampliacin de Oficinas Purina
2/15
Id Modo de
tarea
Nombre de tarea Duracin Comienzo Fin
23 MOVIMIENTOS DE TIERRAS 3 das 05/03/16 08:00 a.m. 09/03/16 12:00 p
24 RELLENO CON MATERIAL DE AFIRMADO EN ESTACIONAMIENTO 1 da 08/03/16 01:00 p.m. 09/03/16 12:00 p
25 NIVELACIN, RIEGO Y APISONADO, MANUAL 1 da 05/03/16 08:00 a.m. 07/03/16 12:00 p
26 ACARREO MANUAL DE MATERIAL 1 da 07/03/16 01:00 p.m. 08/03/16 12:00 p
27 ESTRUCTURAS 5 das 07/03/16 01:00 p.m. 12/03/16 12:00 p
28 CONCRETO SIMPLE 5 das 07/03/16 01:00 p.m. 12/03/16 12:00 p29 FALSO PISO 4" CON MEZCLA 1:8 C:H , ACABADO PULIDO PARA
EXTERIORES1 da 07/03/16 01:00 p.m. 08/03/16 12:00
p.m.
30 ENCOFR. Y DESENC.NORMAL 1 da 08/03/16 01:00 p.m. 09/03/16 12:00 p
31 SARDINEL DE CONCRETO H:37CM 1 da 09/03/16 01:00 p.m. 10/03/16 12:00 p
32 RAMPA DE CONCRETO , ACABADO PULIDO BRUADO 2 das 10/03/16 01:00 p.m. 12/03/16 12:00 p
33 TABIQUERIA LIGERA (DRYWALL) 3 das 11/03/16 08:00 a.m. 15/03/16 12:00 p
34 TABIQUE SIMPLE C/ PLACA STD. DOS CARAS e=0,17 M 1 da 11/03/16 08:00 a.m. 11/03/16 05:00 p
35 TABIQUE SIMPLE C/ PLACA STD. DOS CARAS e=0,12 M 1 da 11/03/16 08:00 a.m. 11/03/16 05:00 p36 DINTELES CON SISTEMA DRYWALL STD. GYPLAC 1/2" e= 0,15 m 1 da 12/03/16 08:00 a.m. 14/03/16 12:00 p
37 DINTELES CON SUPERBOARD 8MM e= 0,15 m 2 das 12/03/16 08:00 a.m. 15/03/16 12:00 p
38 FALSO CIELO RASO (DRYWALL) 2 das 15/03/16 01:00 p.m. 17/03/16 12:00 p
39 CIELO RASO CON BALDOSAS ACUSTICAS OLIMPICUS OWA 2 das 15/03/16 01:00 p.m. 17/03/16 12:00p.m.
40 ESTRUCTURA DE SISTEMA DE DRYWALL 1 da 17/03/16 01:00 p.m. 18/03/16 12:00 p
41 ESTRUCTURA SIMPLE CON VIGUETAS PERFIL 90 PESADO, PARA NUEVO ENRECEPCION
1 da 17/03/16 01:00 p.m. 18/03/16 12:00
p.m.
42 ESTRUCTURA METALICA DE 4"X2" PARA NUEVO TECHO EN RECEPCION 1 da 17/03/16 01:00 p.m. 18/03/16 12:00p.m.
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tarea inactiva
Hito inactivo
Resumen inactivo
Tarea manual
solo duracin
Informe de resumen manual
Resumen manual
solo el comienzo
solo fin
Tareas externas
Hito externo
Fecha lmite
Tareas crticas
Divisin crtica
Progreso
Progreso manual
Pgina 2
Proyecto: Ampliacin de oficina
Fecha: 23/02/16 06:01 p.m.
7/24/2019 Ampliacin de Oficinas Purina
3/15
Id Modo de
tarea
Nombre de tarea Duracin Comienzo Fin
43 PISOS Y PAVIMENTOS 2 das 09/03/16 08:00 a.m. 10/03/16 05:00 p
44 PORCELANATO EN PISO. SILVER PULIDO 0.60X0.60 2 das 09/03/16 08:00 a.m. 10/03/16 05:00 p
45 CONTRAZOCALO 2 das 11/03/16 08:00 a.m. 14/03/16 12:00 p
46 PORCELANATO SILVER PULIDO 0.60X0.10 2 das 11/03/16 08:00 a.m. 14/03/16 12:00 p
47 CUBIERTAS 3 das 18/03/16 01:00 p.m. 22/03/16 05:00 p
48 CUBIERTA MANTO ASFALTICO EN NUEVO TECHO DE RECEPCION 1 da 18/03/16 01:00 p.m. 19/03/16 12:00 p49 CUBIERTA SUPERIOR CON SUPERBOARD DE 12MM 1 da 21/03/16 08:00 a.m. 21/03/16 05:00 p
50 CUBIERTA POLICARBONATO MAKROLON BAYER, CON MARCO DEALUMINIO DE 4"X1 1/2", CON SELLO SIKAFLEX Y PERNOS DE FIJACION
1 da 22/03/16 08:00 a.m. 22/03/16 05:00
p.m.
51 CARPINTERIA METALICA 1 da 16/03/16 08:00 a.m. 16/03/16 05:00 p
52 BARANDA METALICA EN HALL DE INGRESO CON PASAMANOS DE 2" 1 da 16/03/16 08:00 a.m. 16/03/16 05:00 p
53 CARPINTERIA DE MADERA 1 da 18/03/16 01:00 p.m. 19/03/16 12:00 p
54 MOBILIARIO 1 da 18/03/16 01:00 p.m. 19/03/16 12:00 p
55 MUEBLE DE CREDENZA INFERIOR, MELAMINE DE 18MM , INCLUYETIRADORES DE ACERO INOX, BRAZO HIDRAULICOS Y VISAGRAS TIPOCANGREJO
1 da 18/03/16 01:00 p.m. 19/03/16 12:00p.m.
56 MUEBLE DE CREDENZA SUPERIOR, MELAMINE DE 18MM , INCLUYETIRADORES DE ACERO INOX, BRAZO HIDRAULICOS Y VISAGRAS TIPOCANGREJO
1 da 18/03/16 01:00 p.m. 19/03/16 12:00
p.m.
57 ESCRITORIOS, MELAMINE DE 18MM , INCLUYE TIRADORES DE ACEROINOX, PASACABLES Y SEPARADORES METALICOS
1 da 18/03/16 01:00 p.m. 19/03/16 12:00
p.m.
58 VIDRIOS, CRISTALES Y SIMILARES 3 das 12/03/16 08:00 a.m. 16/03/16 12:00 p
59 VIDRIO TEMPLADO 10MM CLS COLOR INCOLORO, CON MARCO DEALUMINIO.
1 da 14/03/16 01:00 p.m. 15/03/16 12:00
p.m.
60 COLOCACION DE LAMINAS POLARIZADAS 1 da 15/03/16 01:00 p.m. 16/03/16 12:00 p
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tarea inactivaHito inactivo
Resumen inactivo
Tarea manual
solo duracin
Informe de resumen manual
Resumen manual
solo el comienzosolo fin
Tareas externas
Hito externo
Fecha lmite
Tareas crticas
Divisin crtica
ProgresoProgreso manual
Pgina 3
Proyecto: Ampliacin de oficina
Fecha: 23/02/16 06:01 p.m.
7/24/2019 Ampliacin de Oficinas Purina
4/15
Id Modo de
tarea
Nombre de tarea Duracin Comienzo Fin
61 FRENO HIDRAULICO SEVAX 80 KG 1 da 14/03/16 01:00 p.m. 15/03/16 12:00 p
62 CERRADURA DE ACERO INOXIDABLE 1 da 15/03/16 01:00 p.m. 16/03/16 12:00 p
63 BANDEJA DE ACERO INOX PARA VENTANILLAS 1 da 12/03/16 08:00 a.m. 14/03/16 12:00 p
64 PINTURA 3 das 15/03/16 01:00 p.m. 18/03/16 12:00 p
65 MUROS INTERIORES AMERICAN COLOR 2 MANOS + EMPASTADO 3 das 15/03/16 01:00 p.m. 18/03/16 12:00 p
66 INSTALACIONES ELECTRICAS 4 das 17/03/16 01:00 p.m. 22/03/16 05:00 p67 SALIDA PARA LUMINARIAS 1 da 17/03/16 01:00 p.m. 18/03/16 12:00 p
68 SALIDA DE TECHO C/TUB. SEL (3/4) CABLE TW12 1 da 17/03/16 01:00 p.m. 18/03/16 12:00 p
69 SALIDA PARA TOMACORRIENTES 2.5 das 18/03/16 01:00 p.m. 22/03/16 12:00 p
70 SALIDA P/ TOMAC. BIP. COMERCIAL SIMPLE TUB. SEL 3/4 2 horas 21/03/16 01:00 p.m. 21/03/16 03:00 p
71 SALIDA P/ TOMAC. BIP. SIMPLE TUB. ESTABILIZADO 4 horas 21/03/16 01:00 p.m. 21/03/16 05:00 p
72 SALIDA P/ TELEFONO Y DATA 4 horas 21/03/16 01:00 p.m. 21/03/16 05:00 p
73 PLACAS MODELO UNIVERSAL BTICINO MODELO PVC 4 horas 21/03/16 08:00 a.m. 21/03/16 12:00 p
74 ENTUBADO Y CABLEADO 1 da 18/03/16 01:00 p.m. 19/03/16 12:00 p75 RESANE EN MUROS POR PICADO DE NUEVAS TUBERIAS 4 horas 22/03/16 08:00 a.m. 22/03/16 12:00 p
76 SALIDA PARA INTERRUPTORES 3 das 18/03/16 01:00 p.m. 22/03/16 05:00 p
77 SALIDA P/ INTERRUPTOR. SIMPLE TUB. SEL 3/4 1 da 21/03/16 08:00 a.m. 21/03/16 05:00 p
78 ENTUBADO Y CABLEADO 1 da 18/03/16 01:00 p.m. 19/03/16 12:00 p
79 PLACAS MODELO UNIVERSAL BTICINO MODELO PVC 1 da 22/03/16 08:00 a.m. 22/03/16 05:00 p
80 SALIDA DE PASE 1 da 21/03/16 08:00 a.m. 21/03/16 05:00 p
81 CAJAS DE PASE GALVANIZADA 100X100 1 da 21/03/16 08:00 a.m. 21/03/16 05:00 p
82 ARTEFACTOS 1 da 17/03/16 01:00 p.m. 18/03/16 12:00 p
83 INSTALACION DE LUMINARIAS 1 da 17/03/16 01:00 p.m. 18/03/16 12:00 p
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tarea inactivaHito inactivo
Resumen inactivo
Tarea manual
solo duracin
Informe de resumen manual
Resumen manual
solo el comienzosolo fin
Tareas externas
Hito externo
Fecha lmite
Tareas crticas
Divisin crtica
ProgresoProgreso manual
Pgina 4
Proyecto: Ampliacin de oficina
Fecha: 23/02/16 06:01 p.m.
7/24/2019 Ampliacin de Oficinas Purina
5/15
Id Modo de
tarea
Nombre de tarea Duracin Comienzo Fin
84 INSTALACION DE LUMINARIAS EMPOTRADAS- EXISTENTES 1 da 17/03/16 01:00 p.m. 18/03/16 12:00 p
85 VARIOS, LIMPIEZA, JARDINERIA 1 da 18/03/16 01:00 p.m. 19/03/16 12:00 p
86 LIMPIEZA FINAL DE OBRA 1 da 18/03/16 01:00 p.m. 19/03/16 12:00 p
87 ELIMINACION DE DESMONTE, VOLQUETES DE 20M3, D 10KM 1 da 18/03/16 01:00 p.m. 19/03/16 12:00 p
88 SSMA. 1 da 01/03/16 08:00 a.m. 01/03/16 05:00 p
89 EXAMENES MEDICOS PRE-OCUPACIONAL 1 da 01/03/16 08:00 a.m. 01/03/16 05:00 p
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tarea inactivaHito inactivo
Resumen inactivo
Tarea manual
solo duracin
Informe de resumen manual
Resumen manual
solo el comienzosolo fin
Tareas externas
Hito externo
Fecha lmite
Tareas crticas
Divisin crtica
ProgresoProgreso manual
Pgina 5
Proyecto: Ampliacin de oficina
Fecha: 23/02/16 06:01 p.m.
7/24/2019 Ampliacin de Oficinas Purina
6/15
01/03
12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12
lun 29/02 mi 02/03 vie 04/03 dom 06/03 mar 08/03 ue 10/03 sb 12/03 lun 14/03 mi 16/03 vie
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tarea inactivaHito inactivo
Resumen inactivo
Tarea manual
solo duracin
Informe de resumen manual
Resumen manual
solo el comienzosolo fin
Tareas externas
Hito externo
Fecha lmite
Tareas crticas
Divisin crtica
ProgresoProgreso manual
Pgina 6
Proyecto: Ampliacin de oficina
Fecha: 23/02/16 06:01 p.m.
7/24/2019 Ampliacin de Oficinas Purina
7/15
12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12
lun 29/02 mi 02/03 vie 04/03 dom 06/03 mar 08/03 ue 10/03 sb 12/03 lun 14/03 mi 16/03 vie
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tarea inactivaHito inactivo
Resumen inactivo
Tarea manual
solo duracin
Informe de resumen manual
Resumen manual
solo el comienzosolo fin
Tareas externas
Hito externo
Fecha lmite
Tareas crticas
Divisin crtica
ProgresoProgreso manual
Pgina 7
Proyecto: Ampliacin de oficina
Fecha: 23/02/16 06:01 p.m.
7/24/2019 Ampliacin de Oficinas Purina
8/15
12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12
lun 29/02 mi 02/03 vie 04/03 dom 06/03 mar 08/03 ue 10/03 sb 12/03 lun 14/03 mi 16/03 vie
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tarea inactivaHito inactivo
Resumen inactivo
Tarea manual
solo duracin
Informe de resumen manual
Resumen manual
solo el comienzosolo fin
Tareas externas
Hito externo
Fecha lmite
Tareas crticas
Divisin crtica
ProgresoProgreso manual
Pgina 8
Proyecto: Ampliacin de oficina
Fecha: 23/02/16 06:01 p.m.
7/24/2019 Ampliacin de Oficinas Purina
9/15
12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12
lun 29/02 mi 02/03 vie 04/03 dom 06/03 mar 08/03 ue 10/03 sb 12/03 lun 14/03 mi 16/03 vie
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tarea inactiva
Hito inactivo
Resumen inactivo
Tarea manual
solo duracin
Informe de resumen manual
Resumen manual
solo el comienzo
solo fin
Tareas externas
Hito externo
Fecha lmite
Tareas crticas
Divisin crtica
Progreso
Progreso manual
Pgina 9
Proyecto: Ampliacin de oficina
Fecha: 23/02/16 06:01 p.m.
7/24/2019 Ampliacin de Oficinas Purina
10/15
12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12
lun 29/02 mi 02/03 vie 04/03 dom 06/03 mar 08/03 ue 10/03 sb 12/03 lun 14/03 mi 16/03 vie
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tarea inactiva
Hito inactivo
Resumen inactivo
Tarea manual
solo duracin
Informe de resumen manual
Resumen manual
solo el comienzo
solo fin
Tareas externas
Hito externo
Fecha lmite
Tareas crticas
Divisin crtica
Progreso
Progreso manual
Pgina 10
Proyecto: Ampliacin de oficina
Fecha: 23/02/16 06:01 p.m.
7/24/2019 Ampliacin de Oficinas Purina
11/15
12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12
vie 18/03 dom 20/03 mar 22/03 ue 24/03 sb 26/03 lun 28/03 mi 30/03 vie 01/04 dom 03/04 ma
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tarea inactiva
Hito inactivo
Resumen inactivo
Tarea manual
solo duracin
Informe de resumen manual
Resumen manual
solo el comienzo
solo fin
Tareas externas
Hito externo
Fecha lmite
Tareas crticas
Divisin crtica
Progreso
Progreso manual
Pgina 11
Proyecto: Ampliacin de oficina
Fecha: 23/02/16 06:01 p.m.
7/24/2019 Ampliacin de Oficinas Purina
12/15
12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12
vie 18/03 dom 20/03 mar 22/03 ue 24/03 sb 26/03 lun 28/03 mi 30/03 vie 01/04 dom 03/04 ma
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tarea inactiva
Hito inactivo
Resumen inactivo
Tarea manual
solo duracin
Informe de resumen manual
Resumen manual
solo el comienzo
solo fin
Tareas externas
Hito externo
Fecha lmite
Tareas crticas
Divisin crtica
Progreso
Progreso manual
Pgina 12
Proyecto: Ampliacin de oficina
Fecha: 23/02/16 06:01 p.m.
7/24/2019 Ampliacin de Oficinas Purina
13/15
12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12
vie 18/03 dom 20/03 mar 22/03 ue 24/03 sb 26/03 lun 28/03 mi 30/03 vie 01/04 dom 03/04 ma
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tarea inactiva
Hito inactivo
Resumen inactivo
Tarea manual
solo duracin
Informe de resumen manual
Resumen manual
solo el comienzo
solo fin
Tareas externas
Hito externo
Fecha lmite
Tareas crticas
Divisin crtica
Progreso
Progreso manual
Pgina 13
Proyecto: Ampliacin de oficina
Fecha: 23/02/16 06:01 p.m.
7/24/2019 Ampliacin de Oficinas Purina
14/15
12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12
vie 18/03 dom 20/03 mar 22/03 ue 24/03 sb 26/03 lun 28/03 mi 30/03 vie 01/04 dom 03/04 ma
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tarea inactiva
Hito inactivo
Resumen inactivo
Tarea manual
solo duracin
Informe de resumen manual
Resumen manual
solo el comienzo
solo fin
Tareas externas
Hito externo
Fecha lmite
Tareas crticas
Divisin crtica
Progreso
Progreso manual
Pgina 14
Proyecto: Ampliacin de oficina
Fecha: 23/02/16 06:01 p.m.
7/24/2019 Ampliacin de Oficinas Purina
15/15
12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12
vie 18/03 dom 20/03 mar 22/03 ue 24/03 sb 26/03 lun 28/03 mi 30/03 vie 01/04 dom 03/04 ma
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tarea inactiva
Hito inactivo
Resumen inactivo
Tarea manual
solo duracin
Informe de resumen manual
Resumen manual
solo el comienzo
solo fin
Tareas externas
Hito externo
Fecha lmite
Tareas crticas
Divisin crtica
Progreso
Progreso manual
Pgina 15
Proyecto: Ampliacin de oficina
Fecha: 23/02/16 06:01 p.m.