TRAMO: TRAMO: LLERA - CD. VICTORIA
FECHA DE TERMINO PROGRAMADA (CON CONVENIO): 31 DE JUNIO DE 2014
RESIDENTE DE OBRA: ING. SERVANDO JORGE COVIAN CANALES
AVANCE AL: 4 DE JULIO DE 2014
CONTRATO: 2014-28-CB-A-052-W-00-2014
CARRETERA : CD. VALLES- CD. VICTORIA
SUBTRAMO: KM. 176+200, KM. 176+500 Y KM. 177+100
CONTRATISTA: ARRENDADORA DE MAQUINARIA DEL MANTE, S.A DE C.V.
FECHA DE INICIO PROGRAMADA: 1 DE MAYO DE 2014
RESIDENCIA GENERAL DE CONSERVACION DE CARRETERAS
obras 2014
$-
$500,000.00
$1,000,000.00
$1,500,000.00
$2,000,000.00
$2,500,000.00
MAYOJUNIO
JULIOAGOSTO
$117,468.72
$617,580.22
$1,570,880.22
$2,151,562.44
$- $-
$-
$988,440.25
$- $-
$- $-
AVANCE
PROGRAMADO AVANCE
CENTRO SCT TAMAULIPAS
RESIDENCIA GENERAL DE CONSERVACION DE CARRETERAS
MES CALENDARIO EJERCIDO
ANTICIPO 748,743.73$
MAYO 136,263.72$ -$
JUNIO 580,129.34$ -$
JULIO 1,105,828.00$ -$
AGOSTO 673,591.38$ -$
0 -$ -$
0 -$ -$
- -$ -$
- -$ -$
- -$ -$
- -$ -$
- -$ -$
- -$ -$
2,495,812.43$
748,743.73$
AVANCE PROGRAMADO AVANCE FÍSICO ATRASO O ADELANTO
28.70% 45.94% +17.24%
AVANCE PONDERADO
EJERCIDO ACUMULADO
CENTRO SCT TAMAULIPAS
AVANCE FINANCIERO CON IVA
RESIDENTE DE OBRA: ING. SERVANDO JORGE COVIAN CANALES
AVANCE AL: 4 DE JULIO DE 2014
CONTRATO: 2014-28-CB-A-052-W-00-2014
RESIDENCIA GENERAL DE CONSERVACION DE CARRETERAS
PROBLEMATICA:
CENTRO SCT TAMAULIPAS
RESIDENTE DE OBRA: ING. SERVANDO JORGE COVIAN CANALES
AVANCE AL: 4 DE JULIO DE 2014
CONTRATO: 2014-28-CB-A-052-W-00-2014
RESIDENCIA GENERAL DE CONSERVACION DE CARRETERAS
ALCANTARILLA DOBLE DE 1.22 M DEL KM 176+200-177+200
CONCRETO EN ALCANTARILLAS DEL KM 176+200-177+200
ALCANTARILLA DOBLE DE 1.22 M DEL KM 176+200-177+200
ALCANTARILLAS DEL KM 176+200-177+200
CENTRO SCT TAMAULIPAS