ACARICRONOGRAMA DE AVANCE DE OBRAOBRA: PLAZUELA Y PARQUE INFANTIL ACARIUBICACIN: NUEVO ACARI - ACARI - CARAVELI - AREQUIPAENTIDAD: MUNICIPALIDAD DISTRITAL DE ACARIPLAZO: 60 DIAS CALENDARIOFECHA:JULIO 2009PLAZO DE EJECUCION 90 DIAS CALENDARIOITEMDESCRIPCIONSECTOR 1SECTOR 2SECTOR 3OBRASCERCOPRIMERASEGUNDAUnidadMetradoPrecioParcial%30 DIAS%60 DIAS%EXTERIORESPERIMETRICOETAPAETAPA00.00.00INSFRAESTRUCTURA DEPORTIVA9308.380.200.2000.01.00OBRAS PRELIMINARES01.00.00TRABAJOS PRELIMINARES0.000.0001.00.01POZA PARA AGUA (2X1.5X1)M31.5083.65125.48100%01.00.02CONSTRUCCION DE CAMPAMENTO DE OBRAM31.5083.65125.48GLB1.00767.18767.18100%0.000.0001.03.00TRAZO, NIVELES Y REPLANTEO PRELIMINAR CON VALLAS AISLADASGLB1.00767.18767.18M2726.150.15108.92100%01.03.01LIMPIEZA DE TERRENO MANUALM2726.150.15108.92M2726.151.431,038.3960%40%0.000.0001.04.00CARTEL DE OBRA (1.20 X 2.40M)M2726.151.431,038.39GLB1.00724.47724.47100%GLB1.00724.47724.470.000.0002.00.00MOVIMIENTO DE TIERRAS02.02.00EXCAVACIONES PARA CIMIENTOS Y ZAPATAS EN TERRENO PEDREGOSOM335.548.42299.25100%0.000.0002.02.01DEMOLICION Y CORTE SUPERFICIAL LATERAL CON MAQUINARIAM335.548.42299.25M347.2525.251,193.06100%02.03.00ELIMINACION DE DESMONTE PROV. DEL MOV. EN TERRENO PEDREGOSOM347.2525.251,193.06M338.2695.073,637.38100%0.000.00M338.2695.073,637.3803.00.00CONCRETO CICLOPEO0.000.0003.02.00CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRAM313.82112.761,558.34100%03.05.00AFIRMADOM313.82112.761,558.34M2325.165.421,762.37100%0.000.0003.06.00FALSO PISO DE 4" DE CONCRETO 1:10M2325.165.421,762.37M251.0520.901,066.95100%03.08.00ENCOFRADO Y DESENCOFRADO NORMALM251.0520.901,066.95M212.6826.04330.19100%0.000.00M212.6826.04330.1904.00.00CONCRETO ARMADO0.000.0004.00.01MURO CERCO DE PERGOLA DE CONCRETO ARMADO f!c=175KG/CM204.00.02CONCRETO EN MUROS CERCO PERGOLA REFORZADO F'C= 140 KG/CM2M316.36155.102,537.44100%0.000.0004.00.03ENCOFRADO Y DESENCOF. MUROS DE 0.25 A 1.30 MTM316.36155.102,537.44M298.1719.021,867.19100%04.00.04ACERO EN MUROS REFORZADO GRADO 60M298.1719.021,867.19KG231.874.721,094.43100%0.000.00KG231.874.721,094.4304.01.00ZAPATAS04.01.01CONCRETO PARA ZAPATAS F'C=210 KG/CM21048.57M34.00189.82759.28100%0.500.5004.01.02ACERO PARA ZAPATAS GRADO 60M34.00189.82759.2810,356.95KG53.044.78253.53100%0.00KG53.044.78253.531,035.7004.02.00COLUMNAS0.000.0004.02.01CONCRETO EN COLUMNAS F'C=210 KG/CM2M31.25270.12337.65100%04.02.02ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNASM31.25270.12337.65M220.0023.16463.20100%0.00%04.02.03ACERO GRADO 60 EN COLUMNASM220.0023.16463.20KG350.004.511,578.50100%KG350.004.511,578.5004.05.00MURO PARA MEDIDOR04.05.02MURO DE SOGA LADRILLO KING-KONG CON CEMENTO-CAL-ARENAM22.2556.83127.87100%M22.2556.83127.8704.07.00GRADAS EN PERGOLA04.07.01CONCRETO EN ESCALERAS F'C=175 KG/CM2M31.50260.77391.16100%04.07.02ACERO GRADO 60 EN ESCALERASM31.50260.77391.16KG95.004.72448.40100%04.07.03ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERASKG95.004.72448.40M24.0035.47141.88100%M24.0035.47141.8805.00.00PISOS Y PAVIMENTOS05.01.00CONTRAPISO DE 48 MM. EN PERGOLAM251.0512.24624.85100%05.02.00VEREDA DE CONCRETO DE 4"M251.0512.24624.85M2274.1136.239,931.0170%30%05.03.00CAMA Y PROTECCION CON ARENA EN ZANAS DE JUEGOS RECREATIVOSM2274.1136.239,931.01M2154.009.031,390.62100%M2154.009.031,390.6206.00.00REVOQUES ENLUCIDOS Y MOLDURAS06.01.01TARRAJEO EN SUPERFICIE DE VIGAS Y COLUMNAS Y BANCAS CON CEMENTO-ARENAM2166.4112.062,006.90100%06.02.00REVESTIMIENTO DE SARDINEL DE CONCRETO RENDIMIENTO = 45 ML/DIAM2166.4112.062,006.90M259.205.251,360.80100%M259.205.251,360.8007.00.00CARPINTERIA DE MADERA07.01.00PERGOLA DE MADERA SEGUN DISEOGLB1.009,214.709,214.7050%50%GLB1.009,214.709,214.7008.00.00CARPINTERIA METALICA08.01.00PAPELERA DE FIERRO LAMINADOUND6.00250.001,500.00100%08.02.00RUEDA GIRATORIAUND6.00250.001,500.00UND1.003,500.003,500.00100%08.03.00BANCAS DE FIERRO Y MADERAUND1.003,500.003,500.00UND16.00400.006,400.00100%08.04.00COLUMPIO PARA CUATRO PERSONASUND16.00400.006,400.00UND1.001,700.001,700.00100%08.05.00JUEGO MULTIPLEUND1.001,700.001,700.00UND1.004,300.004,300.00100%08.06.00CASTILLOUND1.004,300.004,300.00UND1.001,550.001,550.00100%08.07.00BALANZAUND1.001,550.001,550.00UND1.001,900.001,900.00100%08.08.00BARRAS PARALELASUND1.001,900.001,900.00UND1.00650.00650.00100%08.09.00PASAMANOSUND1.00650.00650.00UND1.00450.00450.00100%08.10.00POSTE PEDESTAL PARA CONTROLUND1.00450.00450.00UND82.0065.985,410.36100%08.11.00CADENA PROTECTORA DE JARDIN E=1"UND82.0065.985,410.36M172.005.80997.60100%M172.005.80997.6009.00.00INSTALACIONES ELECTRICAS09.01.00SALIDA PARA CENTROS DE LUZPTO8.0077.75622.00100%09.01.01SALIDA PARA LUMINARIASPTO8.0077.75622.00PTO24.0029.21701.04100%09.01.02TUBERIAS PVC SAP (ELECTRICAS) D=1"PTO24.0029.21701.04M116.008.851,026.6070%30%09.01.03CABLE ELECTRICO NYY 3 X 4 MM2.M116.008.851,026.60M140.003.68515.20100%09.02.00TABLERO ELECTRICO DE CONTROL AUTOMATICO PARA LA EB.M140.003.68515.20UND1.00352.00352.00100%09.03.00POSTES FAROLUND1.00352.00352.00UND8.00218.991,751.9250%50%09.04.00POZO-CONEXION A TIERRA EN SISTEMA C/ALUMB,TOMACORRUND8.00218.991,751.92UND1.00516.27516.27100%UND1.00516.27516.2709.05.00INSTALACIONES SANITARIAS09.09.00INSTALACIONES DE AGUA FRIA09.09.01SALIDA DE AGUA FRIA09.09.02SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2"PTO2.0054.09108.18100%PTO2.0054.09108.1809.09.03REDES DE DICTRIBUCION09.09.04RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAPM26.009.56248.56100%M26.009.56248.5609.09.05LLAVES Y VALVULAS09.09.06VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE 1/2"UND1.0062.6562.65100%UND1.0062.6562.6509.09.07ADITAMENTOS VARIOS09.09.08LLAVE DE RIEGO CON GRIFO DE 1/2"PZA2.0029.8259.64100%PZA2.0029.8259.6410.00.00PINTURA10.01.00PINTURA EN INETRIORES Y EXTERIORES A LA CAL 2 MANOSM281.814.89400.05100%10.02.00PINTURA DE CONTRAZOCALO C/ESMALTE ECONOMICOM281.814.89400.05M75.752.37179.53100%M75.752.37179.5311.00.00ARBOLIZACION11.01.00FICUSUND6.0034.11204.66100%11.02.00SEMBRIO DE GRASSUND6.0034.11204.66M2164.4628.584,700.27100%11.03.00SEMBRIO DE FLORESM2164.4628.584,700.27UND10.0028.42284.20100%UND10.0028.42284.2012.00.00FLETE12.01.00MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA, MATERIALES Y HERRAMIENTASGLB1.002,000.002,000.0060%40%100.00%50.00%50.00%89,232.1044,616.0544,616.0513,384.816,692.416,692.41102,616.9151,308.4651,308.46