ITEM JUNTA DE DILATACIÓN Y CONSTRUCCIÓN MUROS CANALUNIDAD ML
CONCEPTOEQUIPO RENDIMIENTO VALOR UNITARIO DESPERDICIO UNIDAD VALORFORMALETA 0.1 9350 0 ML $ 935.00 PISTOLA CALAFATEO 0.01 25000 UND $ 250.00 PISTOLA DE CALOR 0.005 200000 UND $ 1,000.00 MATERIALES CANTIDAD VALOR UNITARIO DESPERDICIO UNIDAD VALORCINTA A 15 O SIMILAR 1 18792 0 ML $ 18,792.00 VOLKEM 116 100 67.8 CM3 $ 6,780.00 TRANSPORTE CANTIDAD VALOR UNITARIO VALOR
MANO DE OBRA JORNAL-PRESTACIONAL RENDIMIENTO CANTIDAD PRESTACIONEVALOROFICIAL 68504 28 1 71.26% $ 2,446.57 AYUDANTE 43957 28 1 71.26% $ 1,569.89 COSTO DIRECTO $ 31,773.46
![Page 2: APU CINTA CANAL.xlsx](https://reader036.fdocuments.co/reader036/viewer/2022082820/55cf91d5550346f57b911f30/html5/thumbnails/2.jpg)
ITEM JUNTA DE DILATACIÓN Y CONSTRUCCIÓN MUROS CANAL PLACAUNIDAD ML
CONCEPTOEQUIPO RENDIMIENTO VALOR UNITARIO DESPERDICIO UNIDAD VALORPISTOLA CALAFATEO 0.01 25000 UND $ 250.00 PISTOLA DE CALOR 0.005 200000 UND $ 1,000.00 MATERIALES CANTIDAD VALOR UNITARIO DESPERDICIO UNIDAD VALORCINTA P 18 O SIMILIAR 1 31900 0 ML $ 31,900.00 VOLKEM 116 100 67.8 CM3 $ 6,780.00 TRANSPORTE CANTIDAD VALOR UNITARIO VALOR
MANO DE OBRA JORNAL-PRESTACIONAL RENDIMIENTO CANTIDAD PRESTACIONEVALOROFICIAL 68504 35 1 71.26% $ 1,957.26 AYUDANTE 43957 35 1 71.26% $ 1,255.91 COSTO DIRECTO $ 43,143.17