    Getting There and Enjoying the Trip:

    Using Roadmaps to Turn EA into Results

    David Baker

    Chief Architect

    Diamond Management & Technology Consultants

    [email protected]

    October 24, 2007

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    2/28

    Page 1

    EA typically delivers a future state that is impossible to reach in a

    single step

    Current

    State

    Future

    State?

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    3/28

    Page 2

    The trouble is you cannot predict the economic climate that far in

    advance

    Some organizations immediately start implementing the future state

    Usually results in questions being asked 6 to 12 months later

    Why are we doing this?

    How much longer will it take?

    When can I expect to get my new capabilities?

    Need to do SOME economic planning

    Impossible to take the time to determine the exact number(and type) of resources at the time of the EA plan

    But SOME planning is absolutely necessary BEFORE

    mobilizing the troops

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    4/28

    Page 3

    Your EA plan MUST record your planning assumptions

    Business priorities at the time of the plan

    High level cost assumptions for the transformation

    High level benefit assumptions for the transformation

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    5/28

    Page 4

    What goes into a roadmap?

    Business Capabilities

    I need the ability to.

    Business Operations

    by doing.

    BusinessCapabilitiesRequiring IT

    Support

    When eachcapability is

    delivered

    1H06 2H06 1H07 2H07Theme1

    Capability 01

    Capability 12

    Capability 04Theme2

    Capability 07Capability 09

    Capability 02Theme3

    Capability 03

    Capability 05

    Capability 08

    Technical Solution

    ...with

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    6/28

    Page 5

    Resulting in clear answers to questions held by key stakeholders

    Have we done this before?

    How do we get it done?

    How do I make sure its done

    correctly?

    Whats possible?

    Businesswants to know

    ITManagers

    want to know

    Whats possible?

    When do I get it?

    How much does it cost / save?

    What are the business risks?

    TechnicalStaff

    wants to know

    What do I build?

    What do I build it with?

    When do I build it?

    EA Roadmap

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    7/28Page 6

    Your EA Roadmap is NOT a project plan!

    A Roadmap is a time phased set of activities but at the

    Program/Initiative level NOT a project level

    You are planning the necessary transitions for a multi-year effort

    NOT planning the implementation The Roadmap defines key objectives, and a high-level, prioritized

    approach to reach those objectives

    Roadmaps have enough detail to test the business justification but

    NOT detailed sourcing or budgeting detail

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    8/28Page 7

    EA Roadmaps are created as part of the Strategy and Planning

    cycle

    BusinessStrategicPlanning

    IT StrategicPlanning

    ReleasePlanning(PortfolioMgmt)

    ProjectExecution(SDLC)

    BusinessOperations

    Use enterprise and business unitdirection and goals to drive IT plans

    Develop projects that

    support businessesannual and strategic

    plans

    Prioritize the allocation of

    IT resources to achieve

    business strategy, in

    alignment with enterprise

    architecture

    Run thebusiness

    Portfolio 1Blueprints

    Portfolio 2Blueprints

    Portfolio 3Blueprints

    EnterpriseBlueprints

    Filter

    Project

    Project

    Project

    Project

    Project

    Multi-Year Plans(Roadmaps)

    Budget Cycle(Project Plans)

    Project Cycle Continuous

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    9/28Page 8

    The Roadmapping process

    CurrentState

    (strategy, process,technology)

    FutureState

    (strategy, process,technology)

    Identify Gaps

    IdentifyThemes &Initiatives

    BusinessPrioritization

    Mitigate Risk

    SequenceInitiatives

    BusinessJustification

    Lay OutRoadmap

    Input

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    10/28Page 9

    Identify the gaps between the current and future states

    Identify the new and modified business capabilities

    Consider changes to organization, processes, information and the

    underlying technology

    Rationalize your portfolio of applications

    Retire some applications

    Rehabilitate some applications

    Replace some applications

    Eliminate some applications

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    11/28Page 10

    Bundle the changes into business themes and initiatives

    Initiative Description Capabilities Addressed

    Support

    Service Model

    Analytics

    Enhance program through

    improved strategies and data

    analytics

    Ability to leverage any external data to perform member

    identification and predictive modeling

    Ability to leverage utilization and outcome metrics at the

    provider level to improve network management and

    help shape the networkAbility to access treatment utilization and efficacy and

    deliver feedback to providers

    Improve Financial

    Reporting and

    Analytics

    Improve financial tracking and

    analytics for products and

    enable ROI calculations

    Ability to provide aggregate and individual information

    regarding utilization and ROI

    Ability to track and predict medical costs and to

    properly allocate the contribution margin of products

    Support New

    Products /

    Segments

    Create and support new

    products to serve individual

    and newly identified markets

    Ability to meet currently identified market opportunities

    through new product offerings

    Ability to market to and service members with no plan

    sponsors

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    12/28Page 11

    Use the prioritized capabilities to determine priority order ofthe initiatives

    There are many ways to prioritize the list of capabilities

    Prioritize them directly in a business workshop (hard)

    Map them to the prioritized business goals (easy)

    Use weights, Harvey balls, Assign each initiative the average priority of its associated

    capabilities (or weight them, or . . . )

    Initiative Priority Capability Priority

    Support Service Model Analytics M Capability 1 HCapability 2 M

    Capability 3 L

    Improve Financial Reporting and Analytics H Capability 4 H

    Capability 5 H

    Support New Products / Segments M Capability 6 H

    Capability 7 L

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    13/28Page 12

    Create business justifications for each initiative

    Element Description ExampleProblem statement Defines the reason for the project idea

    to exist in the first place

    Cannot provide customers withreal-time information

    Project Goals What is the project trying to accomplish;

    must address the problem

    Enhance operating costs by real-time handling of claims information

    Market opportunity What is the total size (people,revenues) of the potential market for

    this project?

    $3M claims processed per year

    Value proposition For each target group, what is the

    value?

    Provide Call Reps with real timeinformation

    Capital costs Upfront investment $10M in systemsOperating Costs Ongoing investment $1.5M annually in labor, data

    analysis, maintenance

    Benefits Increased revenues, decreased costs Reduce customer turnover

    Risks / Mitigants Will conditions change to fundamentally

    change the need for this project?

    Data in other projects will be

    negatively impacted

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    14/28Page 13

    Use scorecards to show traceability amongst EA elements

    INITIATIVE DESCRIPTION

    Enhance medical management programs through improvedstrategies and data analytics

    CAPABILITIES ADDRESSED Ability to leverage all client and any available external

    experience information to perform member identification andpredictive modeling

    Ability to leverage utilization, outcome, and satisfaction metricsat the provider level to improve network management and helpshape the network

    Ability to analyze the results of integration and CareManagement programs to validate medical offsets, help directprogram improvements, and develop new programs

    Ability to assess treatment utilization and efficacy and deliverfeedback to providers

    BENEFITS DESCRIPTION

    Sales: Client has been rejected for bids in the past because ofan inability to leverage data from external carriers and on allservices available to a member

    Medical Costs: Improved ability to identify members andapproach them with treatment options tailored to their needs andeligibility will increase the use of highly effective, low costservices and will increase medical offset. Incorporating data, inparticular, can have benefits from being be the first experience inthe benefit path and may become aware of high risk membersbefore they are known elsewhere in the company (e.g.,substance abuse pregnant woman). The benefits might notaccrue, but they will accrue to the company as a whole in termsof medical cost reductions

    AFFECTED IT COMPONENTS Enterprise Data Warehouse Financial Books of Record

    Compliance Systems Provider Portal

    DEPENDENCIES/CONSTRAINTS Project XYZ for integration of member data and enhanced

    individualization (2Q06)

    BUSINESS PRIORITY High

    Duration

    1-3 months

    3-6 months

    6-9 months

    9-12 months

    12 months +

    Cost Range

    $0 - $250,000

    $250,000 - $499,000

    $500,000 - $999,000

    $1,000,000 - $4,999,000

    $5,000,000 - $10,000,000

    RANGE FOR BENEFIT, DURATION & COST

    Benefit Range

    $0 - $499,000

    $500,000 - $1,999,000

    $2,000,000 - $4,999,000

    $5,000,000 - $7,999,000

    $8,000,000 +

    1

    4

    5

    7

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    15/28Page 14

    A word about costs and benefits

    There is no need to do a rigorous cost/benefit analysis at this point in

    the lifecycle

    A roadmap is NOT a budget

    The subsequent portfolio management phase will drive thedetail to a budget level (mobilize resources and costs)

    The costs and benefits estimated during the roadmap phase are an

    additional tool for determining the overall multi-year sequence

    Do just enough estimation Have business subject matter experts estimate the benefit

    ranges

    Have architects use engineering estimation techniques to

    develop cost ranges

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    16/28Page 15

    Consult your architecture models to understand and mitigaterisks

    Consult your EA plan to understand the type of architecture risks

    involved

    New technology - risky

    System replacements complex and costly Lack of skilled resources risky

    Foundational technologies - impact the schedule

    Compliance requirements schedule pressure

    Sequence the architecture changes into slices

    Account for technology dependencies

    Account for architecture risks

    Eat the elephant one bite at a time!

    Consult your EA plan to understand the type of architecture risks

    involved

    New technology - risky

    System replacements complex and costly Lack of skilled resources risky

    Foundational technologies - impact the schedule

    Compliance requirements schedule pressure

    Sequence the architecture changes into slices

    Account for technology dependencies

    Account for architecture risks

    Eat the elephant one bite at a time!

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    17/28Page 16

    Use your work to sequence the initiatives

    SequencedInitiatives

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    18/28Page 17

    You can also use any number of cash based indicators to adjust

    the sequence (or to rule out individual initiatives)

    NPV

    IRR

    Payback /Breakeven

    PeakFunding

    ROI

    Definition Pros Cons Net Present Value Discounted sum of all cash flows

    for the project Invest where NPV > 0

    Measure of valuecreation should lead to

    good (best) investmentdecisions

    Difficulty / uncertainty inchoosing discount rate

    Does not account foramount of investmentrequired

    Internal Rate of Return Discount rate that produces an

    NPV of zero

    Invest where IRR is greater thanan established hurdle rate

    Easily scaleable byinvestment size

    Can lead to badinvestment decisions

    use with care!

    Point in time where cumulative netcash flow = 0

    Amount of time required to recoupthe original investment from aproject

    Under uncertain flight toquality stock marketconditions, Payback canbecome the indicator

    Can often lead to badinvestment decisions

    The maximum negative cumulativenet cash flow over the lifetime ofthe project

    Represents the total amount ofmoney required to be put into theproject

    Appropriate to itsobjective

    the nature of thefunding is a whole otherissue...

    Return on Investment

    The total returns of the projectdivided by the total cash outflow

    Allows for easy

    comparison acrossprojects

    Does not take into

    account the amount ofcapital needed

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    19/28Page 18

    Initiatives can also be sequenced into stages based on business

    need and dependency to deliver incremental capability

    Costs of achieving capabilities

    CostIllustrative

    Stage 2

    Stage 3

    Stage 4

    Portfolio Management Strategy

    1Stay in

    business

    Non-optional level of investment Address regulatory

    environment, align with currentprojects, keep current onsoftware releases, etc.

    2Build

    foundation

    Enable initial capabilities Establish foundation for

    realizing additional capabilitiesin stages 3 and 4

    3 Improveeffectiveness

    Delivers additional capabilitiesin response to pain points

    Dependent on stage 2

    4Improve

    efficiency

    Delivers efficiency focusing onmigrating capabilities to newstrategic platforms

    Dependent on stage 2

    Capability

    Stage 1

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    20/28Page 19

    Lay out the roadmap

    Interim Solution

    Reporting Tool Re-architecture

    Core View

    End-to-End Workflow

    Electronic Receipt/ Submission and Data Validation

    End-to-End Solution

    Analytics Tools Re-architecture1

    2

    3

    4

    5

    6

    7

    8 Training Tools Re-architecture

    9 External Constituent Integration

    System Foundation & InformationManagement

    High Quality Data Capture & InformationExchange

    Dynamic Processing & Workflow

    Advanced Analysis & Reporting

    Multi-Channel Access

    IT Portfolio Management & StrategicEnterprise Architecture

    Integrated Organization & Communication

    2006 2007 2008 2009

    Theme 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q

    1

    2

    4

    5

    3 6

    7

    8

    9

    Milestones

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    21/28Page 20

    Another example

    SF&IM

    HQDC&

    InfoEx.

    DynPr

    oc

    &WF

    AA&R

    MCA

    ITPM&

    SEA

    IntOrg&

    Comm

    2006 2007 2008 2009

    THEME / INITITIVE 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q

    Define High-Level Process Flows Define Data Architecture Strategy Create Book of Record Implement Interim Solution Select Vendor Package Implement Enhanced Tool Retire Acquisition and Data Collection Apps

    Develop Business Information Model Define Process Flows Define Integration Strategy Implement Electronic Receipt & Submission Provide Automated Data Validation

    Optimized Business Process (OBP) Select Technology Tools Implement WF & BR Process Improvements

    Define Process Flows Define DW/DM Architecture Strategy Implement DW/DM Structures & Feeds Develop New Reports Select Data Analytics Tool Implement Data Analytics Tool Retire and Re-architect Reporting/Analytics

    Define Process Flows Select Technology Tool Design & Implement Core Safety View Define Integration Strategy Integrate External Systems Retire Doc Mgmt Systems & Integrated Sys

    Define & Deploy Communication Strategy Establish Process Improvement Governance Create Acquisition Assessment Framework Institute Regulations Pipeline Management Select & Implement Training Tools

    Program Management Office Institute IT Investment Management Enhance SEA Competency Develop Arch. GPs, Governance, & Processes

    Develop Strategic Architecture Blueprints

    Retire: System 5, System 7

    Retire: System 9, System 10,System 11

    Re-architect: System 12,System 13

    Re-architect: System 14,System 15, 16

    Retire: System 18, 19, 20, 21

    Retire: System 22, 23

    Maintain: SRM Portal

    Re-architect / Retire: System 8

    Re-architect: Training systems

    Retire: System 4

    Retire: Fsystem 1, System 2,System 3

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    22/28Page 21

    One more example

    Support Service Model Analytics Leverage all Aetna and external experience data

    Leverage utilization, outcome, and satisfaction metrics

    Analyze the results of Behavioral Health integration

    Assess treatment utilization and efficacy

    Support Enhanced Service Model Identify high risk, highly actionable Members

    Monitor progress and track the adherence

    Provide constituent-targeted service experience

    Financial Reporting & Analytics Provide aggregate and individual information

    Track and predict Behavioral Health medical costs

    Enhance Provider Web Experience Provide constituent-targeted service experience

    Enhance Member Web Experience Provide constituent-targeted service experience

    Enhance Plan Sponsor Experience Provide constituent-targeted service experience Provide a single bill (i.e. including all products)

    Operational Improvements Deliver flexible and customized products and services

    Provide constituent-targeted service experience Administer BH products in a cost effective manner

    Perform cost effective pricing for targeted business

    New Products / Segments Meet currently identified market opportunities

    Market to and service Individuals

    Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

    2006 2007 2008

    A1457

    B23

    10

    C69

    D10

    E10

    F1012

    G8

    101415

    H1113

    ID Theme / Initiative

    $3,856 $3,214 $3,983 $4,129 $2,864 $2,349 $1,696 $1,121 $880 $389 $0 $0$24,518TOTAL COSTS ($000)

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    23/28Page 22

    Remember, the level of detail is commensurate with the lifecycle

    stage

    Portfolio 1Blueprints

    Portfolio 2Blueprints

    Portfolio 3Blueprints

    EnterpriseBlueprints

    BusinessStrategicPlanning

    IT StrategicPlanning

    Roadmap createdhere

    Sequenced list ofinitiatives

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    24/28Page 23

    Remember, the level of detail is commensurate with the lifecycle

    stage

    Portfolio 1Blueprints

    Portfolio 2Blueprints

    Portfolio 3Blueprints

    EnterpriseBlueprints

    Filter

    Project

    Project

    Project

    Project

    Project

    BusinessStrategicPlanning

    IT StrategicPlanning

    ReleasePlanning(PortfolioMgmt)

    Roadmap createdhere

    Sequenced list ofinitiatives

    Filter and refine intoProjects

    Apply resource andfinancial constraints

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    25/28

    Page 24

    Remember, the level of detail is commensurate with the lifecycle

    stage

    Portfolio 1Blueprints

    Portfolio 2Blueprints

    Portfolio 3Blueprints

    EnterpriseBlueprints

    Filter

    Project

    Project

    Project

    Project

    Project

    BusinessStrategicPlanning

    IT StrategicPlanning

    ReleasePlanning(PortfolioMgmt)

    ProjectExecution(SDLC)

    BusinessOperations

    Roadmap createdhere

    Sequenced list ofinitiatives

    Filter and refine intoProjects

    Apply resource andfinancial constraints

    Use prioritizedinitiatives andcapabilities togovern project

    execution

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    26/28

    Page 25

    A few considerations for service orientation

    The move to services means that the business capabilities will be

    mapped to services, not systems or applications

    Services will be retired, rehabilitated, rearchitected or removed

    Roadmaps may have to become more granularto address theimpact to services

    Service-level roadmaps will be especially important during

    governance of implementation projects

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    27/28

    Page 26

    Recap: What is a roadmap?

    Prioritized business capabilities

    Prioritized initiatives

    Initiative scorecards

    Cost and benefit estimates, estimated duration

    Risk mitigation strategies

    Sequence architecture time slices

    Sequenced initiatives

    Input to portfolio management

  • 8/2/2019 BakerRoadmapping-12269811883-phpapp03

    28/28

    Thank You