Cronograma de Inversiones y Avance Fisico

10
AMPLIACION Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABNLE Y DESAGUE DE L CRONOGRAMA DE INVERSI ALTERNATIVA 01 ITEM Descripción PERIODO DE ESTUDIOS Und. Cant. Medida 90 DIAS MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 A SISTEMA DE AGUA POTABLE A1 REDES Y CONEXIONES DOMICILIARIAS GLB 1 10,495,473.53 262,386.84 262,386.84 262,386.84 262,386.84 524,773.68 524,773.68 A2 PLANTA DE TRATAMIENTO AGUA POTABLE PTAP GLB 1.00 2,889,234.33 72,230.86 72,230.86 72,230.86 72,230.86 144,461.72 144,461.72 A3 LINEA DE CONDUCCION Y LINEA DE ADUCCION GLB 1.00 5,949,860.45 148,746.51 148,746.51 148,746.51 148,746.51 297,493.02 297,493.02 A4 RESERVORIO PUMAHUANCA V=1230 M3 GLB 1.00 1,121,674.14 28,041.85 28,041.85 56,083.71 56,083.71 A5 RESERVORIO MARISCAL CASTILLA V=775 M3 GLB 1.00 676,366.65 16,909.17 16,909.17 33,818.33 33,818.33 B SISTEMA DE DESAGUE Y PLANTA DE TRATAMIENTO B1 REDES DE COLECTORES Y PRETRAMIENTO GLB 1.00 15,703,973.49 392,599.34 392,599.34 392,599.34 392,599.34 785,198.67 785,198.67 B2 ESTACION DE BOMBEO CHARCAHUAYLLA GLB 1.00 600,487.69 15,012.19 15,012.19 15,012.19 15,012.19 30,024.38 30,024.38 B3 LINEA DE IMPULSION GLB 1.00 523,888.76 13,097.22 13,097.22 26,194.44 26,194.44 B4 PLANTA DE TRATAMIENTO PTAR GLB 1.00 11,225,088.45 280,627.21 280,627.21 561,254.42 561,254.42 B5 PUENTE PASARELA PLANTA DE TRATAMIENTO GLB 1.00 752,985.03 37,649.25 37,649.25 COSTO DIRECTO TOTAL 49,939,032.51 - 890,975.73 890,975.74 ### ### ### ### GASTOS GENRALES 15% 7,490,854.88 133,646.36 133,646.36 184,447.68 184,447.68 374,542.74 374,542.74 UTILIDAD 10% 4,993,903.25 89,097.57 89,097.57 122,965.12 122,965.12 249,695.16 249,695.16 SUB TOTAL 62,423,790.64 ### ### ### ### ### ### IGV (18%) 11,236,282.31 200,469.54 200,469.54 276,671.52 276,671.52 561,814.12 561,814.12 TOTAL PRESUPUESTO DE OBRA 73,660,072.95 ### ### ### ### ### ### GASTOS DE SUPERVISION DE OBRA 6% 4,419,604.38 78,851.35 78,851.35 108,824.13 108,824.13 220,980.22 220,980.22 ELABORACION EXPEDIENTE TECNICO 1.5% 1,104,901.09 1,104,901.09 GASTOS ADMINISTRATIVOS 0.25% 184,150.18 3,285.47 3,285.47 4,534.34 4,534.34 9,207.51 9,207.51 Costo de la Inversión

description

ASA

Transcript of Cronograma de Inversiones y Avance Fisico

Page 1: Cronograma de Inversiones y Avance Fisico

AMPLIACION Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABNLE Y DESAGUE DE LA CIUDAD DE URUBAMBA - PROVINCIA DE URUBMABA - CUSCO

CRONOGRAMA DE INVERSIONALTERNATIVA 01

ITEM DescripciónPERIODO DE ESTUDIOS

PERIODO DE EJECUCION DE OBRA 18 MESES

Und. Cant. 540 DIAS CALENDARIOS

Medida 90 DIAS MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9

A SISTEMA DE AGUA POTABLE

A1 REDES Y CONEXIONES DOMICILIARIAS GLB 1 10,495,473.53 262,386.84 262,386.84 262,386.84 262,386.84 524,773.68 524,773.68 524,773.68 524,773.68 1,049,547.35

A2 PLANTA DE TRATAMIENTO AGUA POTABLE PTAP GLB 1.00 2,889,234.33 72,230.86 72,230.86 72,230.86 72,230.86 144,461.72 144,461.72 144,461.72 144,461.72 288,923.43

A3 LINEA DE CONDUCCION Y LINEA DE ADUCCION GLB 1.00 5,949,860.45 148,746.51 148,746.51 148,746.51 148,746.51 297,493.02 297,493.02 297,493.02 297,493.02 594,986.05

A4 RESERVORIO PUMAHUANCA V=1230 M3 GLB 1.00 1,121,674.14 28,041.85 28,041.85 56,083.71 56,083.71 56,083.71 56,083.71 112,167.41

A5 RESERVORIO MARISCAL CASTILLA V=775 M3 GLB 1.00 676,366.65 16,909.17 16,909.17 33,818.33 33,818.33 33,818.33 33,818.33 67,636.67

B SISTEMA DE DESAGUE Y PLANTA DE TRATAMIENTO

B1 REDES DE COLECTORES Y PRETRAMIENTO GLB 1.00 15,703,973.49 392,599.34 392,599.34 392,599.34 392,599.34 785,198.67 785,198.67 785,198.67 785,198.67 1,570,397.35

B2 ESTACION DE BOMBEO CHARCAHUAYLLA GLB 1.00 600,487.69 15,012.19 15,012.19 15,012.19 15,012.19 30,024.38 30,024.38 30,024.38 30,024.38 60,048.77

B3 LINEA DE IMPULSION GLB 1.00 523,888.76 13,097.22 13,097.22 26,194.44 26,194.44 26,194.44 26,194.44 52,388.88

B4 PLANTA DE TRATAMIENTO PTAR GLB 1.00 11,225,088.45 280,627.21 280,627.21 561,254.42 561,254.42 561,254.42 561,254.42 1,122,508.85

B5 PUENTE PASARELA PLANTA DE TRATAMIENTO GLB 1.00 752,985.03 37,649.25 37,649.25 37,649.25 37,649.25 75,298.50

COSTO DIRECTO TOTAL 49,939,032.51 - 890,975.73 890,975.74 1,229,651.19 1,229,651.19 2,496,951.63 2,496,951.63 2,496,951.63 2,496,951.63 4,993,903.25

GASTOS GENRALES 15% 7,490,854.88 133,646.36 133,646.36 184,447.68 184,447.68 374,542.74 374,542.74 374,542.74 374,542.74 749,085.49

UTILIDAD 10% 4,993,903.25 89,097.57 89,097.57 122,965.12 122,965.12 249,695.16 249,695.16 249,695.16 249,695.16 499,390.33

SUB TOTAL 62,423,790.64 1,113,719.66 1,113,719.67 1,537,063.98 1,537,063.98 3,121,189.53 3,121,189.53 3,121,189.53 3,121,189.53 6,242,379.07

IGV (18%) 11,236,282.31 200,469.54 200,469.54 276,671.52 276,671.52 561,814.12 561,814.12 561,814.12 561,814.12 1,123,628.23

TOTAL PRESUPUESTO DE OBRA 73,660,072.95 1,314,189.20 1,314,189.21 1,813,735.50 1,813,735.50 3,683,003.65 3,683,003.65 3,683,003.65 3,683,003.65 7,366,007.30

GASTOS DE SUPERVISION DE OBRA 6% 4,419,604.38 78,851.35 78,851.35 108,824.13 108,824.13 220,980.22 220,980.22 220,980.22 220,980.22 441,960.44

ELABORACION EXPEDIENTE TECNICO 1.5% 1,104,901.09 1,104,901.09

GASTOS ADMINISTRATIVOS 0.25% 184,150.18 3,285.47 3,285.47 4,534.34 4,534.34 9,207.51 9,207.51 9,207.51 9,207.51 18,415.02

Costo de la Inversión

L47
usuario:
Page 2: Cronograma de Inversiones y Avance Fisico

TOTAL INVERSION PRESUPUESTARIA 79,368,728.60 1,104,901.08 1,396,326.02 1,396,326.04 1,927,093.97 1,927,093.97 3,913,191.38 3,913,191.38 3,913,191.38 3,913,191.38 7,826,382.75

AMPLIACION Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABNLE Y DESAGUE DE LA CIUDAD DE URUBAMBA - PROVINCIA DE URUBMABA - CUSCO

CRONOGRAMA DE AVANCE FISICO

ALTERNATIVA 01

ITEM DescripciónPERIODO DE ESTUDIOS

PERIODO DE EJECUCION DE OBRA 18 MESES

Und. Cant. 540 DIAS CALENDARIOS

Medida 90 DIAS MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9

A SISTEMA DE AGUA POTABLE

A1 REDES Y CONEXIONES DOMICILIARIAS GLB 1.00 10,495,473.53 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00%

A2 PLANTA DE TRATAMIENTO AGUA POTABLE PTAP GLB 1.00 2,889,234.33 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00%

A3 LINEA DE CONDUCCION Y LINEA DE ADUCCION GLB 1.00 5,949,860.45 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00%

A4 RESERVORIO PUMAHUANCA V=1230 M3 GLB 1.00 1,121,674.14 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00%

A5 RESERVORIO MARISCAL CASTILLA V=775 M3 GLB 1.00 676,366.65 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00%

B SISTEMA DE DESAGUE Y PLANTA DE TRATAMIENTO

B1 REDES DE COLECTORES Y PRETRAMIENTO GLB 1.00 15,703,973.49 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00%

B2 ESTACION DE BOMBEO CHARCAHUAYLLA GLB 1.00 600,487.69 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00%

B3 LINEA DE IMPULSION GLB 1.00 523,888.76 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00%

B4 PLANTA DE TRATAMIENTO PTAR GLB 1.00 11,225,088.45 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00%

B5 PUENTE PASARELA PLANTA DE TRATAMIENTO GLB 1.00 752,985.03 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00%

COSTO DIRECTO TOTAL 49,939,032.51 -

GASTOS GENRALES 15% 7,490,854.88 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00%

UTILIDAD 10% 4,993,903.25 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00%

SUB TOTAL 62,423,790.64 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00%

IGV (18%) 11,236,282.31 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00%

TOTAL PRESUPUESTO DE OBRA 73,660,072.95 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00%

GASTOS DE SUPERVISION DE OBRA 6% 4,419,604.38 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00%

ELABORACION EXPEDIENTE TECNICO 1.5% 1,104,901.09 100.00%

Costo de la Inversión

Page 3: Cronograma de Inversiones y Avance Fisico

GASTOS ADMINISTRATIVOS 0.25% 184,150.18 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00%

TOTAL INVERSION PRESUPUESTARIA 79,368,728.60 0.01 0.01 0.03 0.03 0.05 0.05 0.05 0.05 0.10

Page 4: Cronograma de Inversiones y Avance Fisico

AMPLIACION Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABNLE Y DESAGUE DE LA CIUDAD DE URUBAMBA - PROVINCIA DE URUBMABA - CUSCO

CRONOGRAMA DE INVERSIONALTERNATIVA 01

PERIODO DE EJECUCION DE OBRA 18 MESESLIQUIDACION DE OBRA

540 DIAS CALENDARIOS

MES 10 MES 11 MES 12 MES 13 MES 14 MES 15 MES 16 MES 17 MES 18 60 DIAS

1,049,547.35 1,049,547.35 1,049,547.35 787,160.51 787,160.51 1,049,547.35 524,773.68

288,923.43 288,923.43 288,923.43 216,692.57 216,692.57 288,923.43 144,461.72

594,986.05 594,986.05 594,986.05 446,239.53 446,239.53 594,986.05 297,493.02

112,167.41 112,167.41 112,167.41 84,125.56 84,125.56 112,167.41 56,083.71 28,041.85 28,041.85

67,636.67 67,636.67 67,636.67 50,727.50 50,727.50 67,636.67 33,818.33 16,909.17 16,909.17

1,570,397.35 1,570,397.35 1,570,397.35 1,177,798.01 1,177,798.01 1,570,397.35 785,198.67

60,048.77 60,048.77 60,048.77 45,036.58 45,036.58 60,048.77 30,024.38

52,388.88 52,388.88 52,388.88 39,291.66 39,291.66 52,388.88 26,194.44 13097.219 13097.219

1,122,508.85 1,122,508.85 1,122,508.85 841,881.63 841,881.63 1,122,508.85 561,254.42 280627.21125 280627.21125

75,298.50 75,298.50 75,298.50 56,473.88 56,473.88 75,298.50 37,649.25 37,649.25 37,649.25

4,993,903.25 4,993,903.25 4,993,903.25 3,745,427.44 3,745,427.44 4,993,903.25 2,496,951.63 376324.7015 376324.7015

749,085.49 749,085.49 749,085.49 561,814.12 561,814.12 749,085.49 374,542.74 56,448.71 56,448.71

499,390.33 499,390.33 499,390.33 374,542.74 374,542.74 499,390.33 249,695.16 37,632.47 37,632.47

6,242,379.07 6,242,379.07 6,242,379.07 4,681,784.30 4,681,784.30 6,242,379.07 3,121,189.53 470,405.88 470,405.88

1,123,628.23 1,123,628.23 1,123,628.23 842,721.17 842,721.17 1,123,628.23 561,814.12 84,673.06 84,673.06

7,366,007.30 7,366,007.30 7,366,007.30 5,524,505.47 5,524,505.47 7,366,007.30 3,683,003.65 555,078.93 555,078.93

441,960.44 441,960.44 441,960.44 331,470.33 331,470.33 441,960.44 220,980.22 33,304.74 33,304.74

18,415.02 18,415.02 18,415.02 13,811.26 13,811.26 18,415.02 9,207.51 1,387.70 1,387.70

Page 5: Cronograma de Inversiones y Avance Fisico

7,826,382.75 7,826,382.75 7,826,382.75 5,869,787.06 5,869,787.06 7,826,382.75 3,913,191.38 589,771.37 589,771.37

AMPLIACION Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABNLE Y DESAGUE DE LA CIUDAD DE URUBAMBA - PROVINCIA DE URUBMABA - CUSCO

CRONOGRAMA DE AVANCE FISICO

ALTERNATIVA 01

PERIODO DE EJECUCION DE OBRA 18 MESESLIQUIDACION DE OBRA

540 DIAS CALENDARIOS

MES 10 MES 11 MES 12 MES 13 MES 14 MES 15 MES 16 MES 17 MES 18 60 DIAS

10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00%

10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00%

10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00%

10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00%

10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00%

10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

Page 6: Cronograma de Inversiones y Avance Fisico

10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

0.10 0.10 0.10 0.08 0.08 0.08 0.08 0.01 0.01 1.00

Page 7: Cronograma de Inversiones y Avance Fisico

AMPLIACION Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE Y DESAGUE DE LA CIUDAD DE URUBAMBA - PROVINCIA DE URUBMABA - CUSCO

CRONOGRAMA DE INVERSIONALTERNATIVA 01

ITEM DescripciónPERIODO DE ESTUDIOS

PERIODO DE EJECUCION DE OBRA 18 MESESLIQUIDACION DE OBRA

Und. Cant. 540 DIAS CALENDARIOS

Medida 90 DIAS MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12 MES 13 MES 14 MES 15 MES 16 MES 17 MES 18 60 DIAS

A SISTEMA DE AGUA POTABLE

A1 REDES Y CONEXIONES DOMICILIARIAS GLB 1 10,495,473.53 262,386.84 262,386.84 262,386.84 262,386.84 524,773.68 524,773.68 524,773.68 524,773.68 1,049,547.35 1,049,547.35 1,049,547.35 1,049,547.35 787,160.51 787,160.51 1,049,547.35 524,773.68

A2 PLANTA DE TRATAMIENTO AGUA POTABLE PTAP GLB 1.00 2,889,234.33 72,230.86 72,230.86 72,230.86 72,230.86 144,461.72 144,461.72 144,461.72 144,461.72 288,923.43 288,923.43 288,923.43 288,923.43 216,692.57 216,692.57 288,923.43 144,461.72

A3 LINEA DE CONDUCCION Y LINEA DE ADUCCION GLB 1.00 5,949,860.45 148,746.51 148,746.51 148,746.51 148,746.51 297,493.02 297,493.02 297,493.02 297,493.02 594,986.05 594,986.05 594,986.05 594,986.05 446,239.53 446,239.53 594,986.05 297,493.02

A4 RESERVORIO PUMAHUANCA V=1230 M3 GLB 1.00 1,121,674.14 28,041.85 28,041.85 56,083.71 56,083.71 56,083.71 56,083.71 112,167.41 112,167.41 112,167.41 112,167.41 84,125.56 84,125.56 112,167.41 56,083.71 28,041.85 28,041.85

A5 RESERVORIO MARISCAL CASTILLA V=775 M3 GLB 1.00 676,366.65 16,909.17 16,909.17 33,818.33 33,818.33 33,818.33 33,818.33 67,636.67 67,636.67 67,636.67 67,636.67 50,727.50 50,727.50 67,636.67 33,818.33 16,909.17 16,909.17

B SISTEMA DE DESAGUE Y PLANTA DE TRATAMIENTO

B1 REDES DE COLECTORES Y PRETRAMIENTO GLB 1.00 15,703,973.49 392,599.34 392,599.34 392,599.34 392,599.34 785,198.67 785,198.67 785,198.67 785,198.67 1,570,397.35 1,570,397.35 1,570,397.35 1,570,397.35 1,177,798.01 1,177,798.01 1,570,397.35 785,198.67

B2 ESTACION DE BOMBEO CHARCAHUAYLLA GLB 1.00 600,487.69 15,012.19 15,012.19 15,012.19 15,012.19 30,024.38 30,024.38 30,024.38 30,024.38 60,048.77 60,048.77 60,048.77 60,048.77 45,036.58 45,036.58 60,048.77 30,024.38

B3 LINEA DE IMPULSION GLB 1.00 523,888.76 13,097.22 13,097.22 26,194.44 26,194.44 26,194.44 26,194.44 52,388.88 52,388.88 52,388.88 52,388.88 39,291.66 39,291.66 52,388.88 26,194.44 13097.219 13097.219

B4 PLANTA DE TRATAMIENTO PTAR GLB 1.00 11,327,077.75 283,176.94 283,176.94 566,353.89 566,353.89 566,353.89 566,353.89 1,132,707.78 1,132,707.78 1,132,707.78 1,132,707.78 849,530.83 849,530.83 1,132,707.78 566,353.89 283176.94375 283176.94375

B5 PUENTE PASARELA PLANTA DE TRATAMIENTO GLB 1.00 752,985.03 37,649.25 37,649.25 37,649.25 37,649.25 75,298.50 75,298.50 75,298.50 75,298.50 56,473.88 56,473.88 75,298.50 37,649.25 37,649.25 37,649.25

COSTO DIRECTO TOTAL 50,041,021.81 - 890,975.73 890,975.74 1,232,200.92 1,232,200.92 2,502,051.09 2,502,051.09 2,502,051.09 2,502,051.09 5,004,102.18 5,004,102.18 5,004,102.18 5,004,102.18 3,753,076.64 3,753,076.64 5,004,102.18 2,502,051.09 378874.434 378874.434

GASTOS GENRALES 15% 7,506,153.27 133,646.36 133,646.36 184,830.14 184,830.14 375,307.66 375,307.66 375,307.66 375,307.66 750,615.33 750,615.33 750,615.33 750,615.33 562,961.50 562,961.50 750,615.33 375,307.66 56,831.17 56,831.17

UTILIDAD 10% 5,004,102.18 89,097.57 89,097.57 123,220.09 123,220.09 250,205.11 250,205.11 250,205.11 250,205.11 500,410.22 500,410.22 500,410.22 500,410.22 375,307.66 375,307.66 500,410.22 250,205.11 37,887.44 37,887.44

SUB TOTAL 62,551,277.26 1,113,719.66 1,113,719.67 1,540,251.15 1,540,251.15 3,127,563.86 3,127,563.86 3,127,563.86 3,127,563.86 6,255,127.73 6,255,127.73 6,255,127.73 6,255,127.73 4,691,345.80 4,691,345.80 6,255,127.73 3,127,563.86 473,593.04 473,593.04

IGV (18%) 11,259,229.91 200,469.54 200,469.54 277,245.21 277,245.21 562,961.50 562,961.50 562,961.50 562,961.50 1,125,922.99 1,125,922.99 1,125,922.99 1,125,922.99 844,442.24 844,442.24 1,125,922.99 562,961.50 85,246.75 85,246.75

TOTAL PRESUPUESTO DE OBRA 73,810,507.16 1,314,189.20 1,314,189.21 1,817,496.36 1,817,496.36 3,690,525.36 3,690,525.36 3,690,525.36 3,690,525.36 7,381,050.72 7,381,050.72 7,381,050.72 7,381,050.72 5,535,788.04 5,535,788.04 7,381,050.72 3,690,525.36 558,839.79 558,839.79

GASTOS DE SUPERVISION DE OBRA 6% 4,428,630.43 78,851.35 78,851.35 109,049.78 109,049.78 221,431.52 221,431.52 221,431.52 221,431.52 442,863.04 442,863.04 442,863.04 442,863.04 332,147.28 332,147.28 442,863.04 221,431.52 33,530.39 33,530.39

ELABORACION EXPEDIENTE TECNICO 1.5% 1,107,157.61 1,107,157.61

GASTOS ADMINISTRATIVOS 0.25% 184,526.27 3,285.47 3,285.47 4,543.74 4,543.74 9,226.31 9,226.31 9,226.31 9,226.31 18,452.63 18,452.63 18,452.63 18,452.63 13,839.47 13,839.47 18,452.63 9,226.31 1,397.10 1,397.10

TOTAL INVERSION PRESUPUESTARIA 79,530,821.46 1,107,157.60 1,396,326.02 1,396,326.04 1,931,089.88 1,931,089.88 3,921,183.19 3,921,183.19 3,921,183.19 3,921,183.19 7,842,366.39 7,842,366.39 7,842,366.39 7,842,366.39 5,881,774.79 5,881,774.79 7,842,366.39 3,921,183.19 593,767.28 593,767.28

Costo de la Inversión

L47
usuario:
Page 8: Cronograma de Inversiones y Avance Fisico

AMPLIACION Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE Y DESAGUE DE LA CIUDAD DE URUBAMBA - PROVINCIA DE URUBMABA - CUSCO

DIAGRAMA DE GANTT CON AVANCE PORCENTUALALTERNATIVA 01

ITEM DescripciónPERIODO DE ESTUDIOS

PERIODO DE EJECUCION DE OBRA 18 MESESLIQUIDACION DE OBRA

Und. Cant. 540 DIAS CALENDARIOS

Medida 90 DIAS MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12 MES 13 MES 14 MES 15 MES 16 MES 17 MES 18 60 DIAS

A SISTEMA DE AGUA POTABLE

A1 REDES Y CONEXIONES DOMICILIARIAS GLB 1.00 10,495,473.53 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00% 10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00%

A2 PLANTA DE TRATAMIENTO AGUA POTABLE PTAP GLB 1.00 2,889,234.33 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00% 10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00%

A3 LINEA DE CONDUCCION Y LINEA DE ADUCCION GLB 1.00 5,949,860.45 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00% 10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00%

A4 RESERVORIO PUMAHUANCA V=1230 M3 GLB 1.00 1,121,674.14 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00% 10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

A5 RESERVORIO MARISCAL CASTILLA V=775 M3 GLB 1.00 676,366.65 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00% 10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

B SISTEMA DE DESAGUE Y PLANTA DE TRATAMIENTO

B1 REDES DE COLECTORES Y PRETRAMIENTO GLB 1.00 15,703,973.49 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00% 10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00%

B2 ESTACION DE BOMBEO CHARCAHUAYLLA GLB 1.00 600,487.69 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00% 10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00%

B3 LINEA DE IMPULSION GLB 1.00 523,888.76 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00% 10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

B4 PLANTA DE TRATAMIENTO PTAR GLB 1.00 11,327,077.75 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00% 10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

B5 PUENTE PASARELA PLANTA DE TRATAMIENTO GLB 1.00 752,985.03 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00% 10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

COSTO DIRECTO TOTAL 50,041,021.81 -

GASTOS GENRALES 15% 7,506,153.27 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00% 10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

UTILIDAD 10% 5,004,102.18 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00% 10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

SUB TOTAL 62,551,277.26 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00% 10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

IGV (18%) 11,259,229.91 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00% 10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

TOTAL PRESUPUESTO DE OBRA 73,810,507.16 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00% 10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

GASTOS DE SUPERVISION DE OBRA 6% 4,428,630.43 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00% 10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

ELABORACION EXPEDIENTE TECNICO 1.5% 1,107,157.61 100.00%

GASTOS ADMINISTRATIVOS 0.25% 184,526.27 2.50% 2.50% 2.50% 2.50% 5.00% 5.00% 5.00% 5.00% 10.00% 10.00% 10.00% 10.00% 7.50% 7.50% 10.00% 5.00% 2.50% 2.50%

TOTAL INVERSION PRESUPUESTARIA 79,530,821.46 0.01 0.01 0.03 0.03 0.05 0.05 0.05 0.05 0.10 0.10 0.10 0.10 0.08 0.08 0.08 0.08 0.01 0.01 1.00

Costo de la Inversión