S10Empresa no registrada
Obra CONST. DE PAVIMENTO Y VEREDAS EN LA 1°, 2° Y 3° CUADRA DEL JR. SAN AGUSTIN Y EL PERIMETRO DE LA PLAZA DE ARMAS DEL DIST. DE SAISA, PROV. DE LUCANAS-AYACUCHO
Fórmula PAVIMENTO RIGIDOCliente MUNICIPALIDAD DISTRITAL DE SAISADepartament AYACUCHO
Item Descripción Total01.01.00 OBRAS PROVISIONALES 300001.02.00 OBRAS PRELIMINARES 1554.0801.03.00 MOVIMIENTO DE TIERRAS 26851.1701.04.00 PAVIMENTO DE CONCRETO 91827.0901.05.00 CANALETA PLUVIAL 24227.2901.06.00 VEREDAS 59781.6403.00.00 ENSAYOS04.00.00 FLETE 10825.95
218067.22COSTO DIRECTO 219,864.58GASTOS GENERALES ( 8% ) 17,589.17UTILIDAD ( 6% ) 13191.87SUB TOTAL 250645.62IGV 45116.21TOTAL GENERAL 295761.83
SON : DOSCIENTOS NOVENTINUEVE MIL OCHOCIENTOS SETENTITRES Y 30/100 NUEVOS SOLES
CONST. DE PAVIMENTO Y VEREDAS EN LA 1°, 2° Y 3° CUADRA DEL JR. SAN AGUSTIN Y EL PERIMETRO DE LA PLAZA DE ARMAS DEL DIST. DE SAISA, PROV. DE LUCANAS-AYACUCHO
CRONOGRAMA DE EJECUCION VALORIZADO
OBRA: CONST. DE PAVTO. Y VEREDAS EN LA 1°, 2° Y3° CUDR. DEL JR. SAN AGUSTIN Y EL PERMT. DE LA PLAZA DE ARMAS DEL DIST. DE SAISA
UBICACIÓN: DEPT. : AYACUCHO DISTRITO : SAISA
PROV. : LUCANAS LUGAR : SAISA
EPOCA DE EJECUCION : ABRIL A DICIEMBRE
Nº DESCRIPCION DE PARTIDAS PRESTO. PRIMER MES SEGUNDO MES TERCER MES
1 PAVIMENTACION DE CALLES
1.1 OBRAS PROVISIONALES 3000 3,000.00
2 OBRAS PRELIMINARES 1554.08 777.04 777.04
3 MOVIMIENTO DE TIERRAS 26851.17 5,370.23 5,370.23 5,370.23 5,370.23 5,370.23
4 PAVIMENTO DE CONCRETO 91827.09 11,478.39 11,478.39 11,478.39 11,478.39 11,478.39 11,478.39 11,478.39 11,478.39
5 CANALETA PLUVIAL 24227.29 4,845.46 4,845.46 4,845.46 4,845.46 4,845.46
6 VEREDAS 59781.64 9,963.61 9,963.61 9,963.61 9,963.61 9,963.61
7 FLETE 10825.95 5,412.98 5,412.98
8 LIMPIEZA Y ENTREGA DE OBRA
COSTO DIRECTO TOTAL 218,067.22 8,412.98 777.04 6,147.27 16,848.62 22,261.60 21,694.08 31,657.68 26,287.45 26,287.45 26,287.45 21,441.99
GASTOS GENERALES 15,264.71 588.91 54.39 430.31 1,179.40 1,558.31 1,518.59 2,216.04 1,840.12 1,840.12 1,840.12 1,500.94
UTILIDAD 10,903.36 420.65 38.85 307.36 842.43 1,113.08 1,084.70 1,582.88 1,314.37 1,314.37 1,314.37 1,072.10
IGV (18%) 43,962.35 1,696.06 156.65 1,239.29 3,396.68 4,487.94 4,373.53 6,382.19 5,299.55 5,299.55 5,299.55 4,322.71
TOTAL GENERAL 288,197.64 11,118.59 1,026.94 8,124.24 22,267.14 29,420.92 28,670.89 41,838.80 34,741.50 34,741.50 34,741.50 28,337.74
PORCENTAJE SEMANAL 100.00% 3.86% 0.36% 2.82% 7.73% 10.21% 9.95% 14.52% 12.05% 12.05% 12.05% 9.83%