S10 Pgina 1
Presupuesto"MEJORAMIENTO INTEGRAL DE LOS SERVICIOS DE LA SEDE CENTRAL DE PERUPETRO - SAN BORJA - LIMA - LIMA"0103001Presupuesto
ESTRUCTURAS001SubpresupuestoPERUPETRO S.A 04/04/2015Costo alCliente
Lugar LIMA - LIMA - SAN BORJA
Precio S/. Parcial S/.Mano de Obra Material Equipo SubcontratoItem Descripcin Und. Metrado
2,809,509.4601 OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD 248,766.11 617,991.38 982,139.10 960,612.81
382,072.2601.01 OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, 73,151.47 112,064.40 196,466.99 389.40
73,132.00 1.00 73,132.00glb 73,132.0001.01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS, HERRAMIENTAS Y MATERIALES
111,600.00 279.00 400.00m01.01.02 111,600.00CERCO PERIMETRICO METALICO
464.40 72.00 6.45m201.01.03 464.40OFICINA, ALMACENES Y CASETAS
2,862.17 1.00 2,862.17mes 389.40 2,453.30 19.4701.01.04 SERVICIOS HIGIENICOS PROVISIONAL PARA EL PERSONAL
1,254.33 1.00 1,254.33pza 1,254.3301.01.05 CARTEL DE OBRA
12,500.00 1.00 12,500.00glb 12,500.0001.01.06 INSTALACIONES SANITARIAS PROVISIONALES
180,259.36 1.00 180,259.36glb 180,259.3601.01.07 INSTALACION DE ENEREGIA ELECTRICA PROVISIONAL
375,971.0801.02 DESMONTAJES Y DEMOLICIONES 350,540.19 25,430.89
25,430.89 1.00 25,430.89glb 25,430.8901.02.01 DESMONTAJE DE INSTALACIONES Y MOBILIARIO
350,540.19 1.00 350,540.19glb01.02.02 350,540.19DEMOLICION DEL BLOQUE NORTE, CENTRAL Y SUR
207,551.0101.03 TRANSPORTE EN OBRA 102,564.22 104,986.79
59,874.23 1.00 59,874.23glb01.03.01 59,874.23MONTAJE Y FIJACION DE GRUA
22,569.33 1.00 22,569.33glb01.03.02 22,569.33DESMONTAJE DE GRUA
22,543.23 1.00 22,543.23mes01.03.03 22,543.23TRANSPORTE VERTICAL CON GRUA
102,564.22 1.00 102,564.22glb 102,564.2201.03.04 TRANSPORTE HORIZONTAL PARA LA OBRA
1,164,391.2001.04 SERVICIOS DURANTE LA OBRA 73,050.42 50,400.00 284,400.00 756,540.72
337,714.56 18.00 18,761.92mes 264,664.08 73,050.4201.04.01 TRAZO NIVELES Y REPLANTEO DURANTE LA OBRA
212,400.00 18.00 11,800.00mes 212,400.0001.04.02 SERVICIOS PARA LA OBRA ( LUZ, AGUA E INTERNET)
357,300.00 18.00 19,850.00mes 357,300.0001.04.03 VIGILANCIA INTERNA Y EXTERNA DE LA OBRA
212,117.76 18.00 11,784.32mes 89,717.76 72,000.0001.04.04 50,400.00LIMPIEZA PERMANENTE DE OBRA
44,858.88 18.00 2,492.16mes 44,858.8801.04.05 LIMPIEZA DE AREAS EXTERIORES DE OBRA
679,523.9101.05 SEGURIDAD Y SALUD 475,841.22 203,682.69
85,415.00 1.00 85,415.00glb 85,415.0001.05.01 ELABORACION E IMPLEMENTACIN DE PLAN DE SALUD EN EL TRABAJO
215,100.00 1.00 215,100.00glb 215,100.0001.05.02 EQUIPOS DE PROTECCIN INDIVIDUAL
155,478.00 1.00 155,478.00glb 155,478.0001.05.03 EQUIPOS DE PROTECCIN COLECTIVA
105,263.22 1.00 105,263.22glb 105,263.2201.05.04 SEALIZACION TEMPORAL DE SEGURIDAD
55,478.36 1.00 55,478.36glb 55,478.3601.05.05 CAPACITACIN Y SEGURIDAD Y SALUD
2,789.33 1.00 2,789.33glb 2,789.3301.05.06 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TRABAJO
60,000.00 1.00 60,000.00glb 60,000.0001.05.07 EXMENES MEDICOS PARA EL PERSONAL OBRERO
6,827,291.5902 ESTRUCTURAS 209,225.54 1,664,251.10 3,193,774.69 1,759,924.20
1,001,442.7502.01 MOVIMIENTO DE TIERRAS 7,249.53 924,408.24 8,393.28 61,332.35
25,069.34 4,421.40 5.67m2 20,158.04 4,850.7102.01.01 NIVELACIN DE TERRENO
911,276.24 32,545.58 28.00m302.01.02 911,276.24EXCAVACION MASIVA CON ELIMINACION
16/03/2015 03:23:04p.m.Fecha :
-
S10 Pgina 2
Presupuesto"MEJORAMIENTO INTEGRAL DE LOS SERVICIOS DE LA SEDE CENTRAL DE PERUPETRO - SAN BORJA - LIMA - LIMA"0103001Presupuesto
ESTRUCTURAS001SubpresupuestoPERUPETRO S.A 04/04/2015Costo alCliente
Lugar LIMA - LIMA - SAN BORJA
Precio S/. Parcial S/.Mano de Obra Material Equipo SubcontratoItem Descripcin Und. Metrado
31,882.63 1,018.94 31.29m3 30,955.39 928.6602.01.03 EXCAVACION LOCALIZADA
6,779.19 371.87 18.23m3 6,455.98 322.7802.01.04 RELLENO COMPACTADO CON MATERIAL PROPIO
13,303.35 199.84 66.57m3 3,762.94 8,393.28 1,147.3802.01.05 RELLENO LOCALIZADO CON MATERIAL DE PRSTAMO
13,132.00 469.00 28.00m302.01.06 13,132.00ELIMINACION DE DEMOLICIONES CON EQUIPO
15,770.8502.02 CONCRETO SIMPLE 192.28 11,734.40 3,844.06
6,349.00 350.00 18.14m2 1,988.28 4,263.00 99.4002.02.01 SOLADO
7,058.15 205.00 34.43m2 1,511.26 5,469.40 75.6502.02.02 FALSO PISO
2,363.70 10.00 236.37m3 344.52 2,002.00 17.2302.02.03 CONCRETO 1:10 + 30% P.G. PARA FALSO CIMIENTO
5,810,077.9902.03 CONCRETO ARMADO 201,783.73 739,842.86 3,173,647.01 1,694,747.79
147,290.1202.03.01 ZAPATAS 3,991.68 123,675.86 19,607.49
93,694.14 306.18 306.01m3 4,489.13 88,827.41 379.4502.03.01.01 CONCRETO fc = 280 kg/cm2 ZAPATAS
7,332.28 180.11 40.71m2 3,229.18 3,700.92 401.6502.03.01.02 ENCOFRADO Y DESENCOFRADO ZAPATA
46,045.77 11,425.75 4.03kg 11,769.44 31,057.47 3,202.6402.03.01.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60
217.93 180.11 1.21m2 119.74 90.06 7.9402.03.01.04 CURADO
160,873.4702.03.02 VIGA DE CIMENTACION 8,788.74 107,806.60 44,238.49
36,180.76 107.39 336.91m3 2,152.12 33,748.92 279.4502.03.02.01 CONCRETO fc = 315 kg/cm2 VIGAS DE CIMENTACION
36,370.77 715.96 50.80m2 19,256.47 14,711.63 2,394.8902.03.02.02 ENCOFRADO Y DESENCOFRADO DE VIGAS DE CIMENTACION
87,455.63 21,701.15 4.03kg 22,353.93 58,988.07 6,082.8302.03.02.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60
866.31 715.96 1.21m2 475.97 357.98 31.5702.03.02.04 CURADO
1,026,268.2902.03.03 MURO ANCLADO 23,013.94 311,574.12 308,000.88 383,670.81
3,269.65 152.36 21.46m3 343.36 2,925.3102.03.03.01 EXCAVACION DE TALUDES CON EQUIPO
346,410.36 22,149.00 15.64m2 279,831.88 58,229.72 8,392.2602.03.03.02 PERFILADO Y PAETEO DE TALUDES
260,077.08 1.00 260,077.08glb02.03.03.03 260,077.08ANCLAJE DE MURO ANCLADO
166,983.00 388.45 429.87m3 6,783.90 159,301.80 898.4902.03.03.04 CONCRETO fc = 315 kg/cm2 MURO ANCLADO
120,107.97 2,219.70 54.11m2 62,842.33 3,878.26 1,885.1902.03.03.05 51,497.04ENCOFRADO Y DESENCOFRADO MURO ANCLADO
126,734.39 31,447.74 4.03kg 32,393.68 85,481.25 8,814.8002.03.03.06 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60
2,685.84 2,219.70 1.21m2 1,475.66 1,109.85 97.8902.03.03.07 CURADO
1,003,513.9902.03.04 PLACAS 39,494.78 79,074.49 643,782.81 241,065.16
265,444.85 757.44 350.45m3 23,831.97 238,607.24 3,009.5402.03.04.01 CONCRETO fc = 315 kg/cm2 PLACAS
162,515.08 472.95 343.62m3 14,880.82 145,759.88 1,879.1702.03.04.02 CONCRETO fc = 280 kg/cm2 PLACAS
233,394.59 8,323.63 28.04m2 111,936.17 31,263.48 11,141.1802.03.04.03 79,074.49ENCOFRADO Y DESENCOFRADO PLACAS
332,087.88 82,403.94 4.03kg 84,882.65 223,990.39 23,097.8202.03.04.04 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60
10,071.59 8,323.63 1.21m2 5,533.55 4,161.82 367.0702.03.04.05 CURADO
387,648.9402.03.05 COLUMNAS 19,471.34 17,451.50 245,759.24 104,868.38
69,392.28 192.10 361.23m3 7,883.77 60,514.96 995.4002.03.05.01 CONCRETO fc = 315 kg/cm2 COLUMNAS
20,626.08 58.20 354.40m3 2,388.52 17,936.83 301.5802.03.05.02 CONCRETO fc = 280 kg/cm2 COLUMNAS
16/03/2015 03:23:04p.m.Fecha :
-
S10 Pgina 3
Presupuesto"MEJORAMIENTO INTEGRAL DE LOS SERVICIOS DE LA SEDE CENTRAL DE PERUPETRO - SAN BORJA - LIMA - LIMA"0103001Presupuesto
ESTRUCTURAS001SubpresupuestoPERUPETRO S.A 04/04/2015Costo alCliente
Lugar LIMA - LIMA - SAN BORJA
Precio S/. Parcial S/.Mano de Obra Material Equipo SubcontratoItem Descripcin Und. Metrado
58,949.33 1,837.00 32.09m2 32,935.36 6,899.76 1,646.8702.03.05.03 17,451.50ENCOFRADO Y DESENCOFRADO COLUMNAS
236,458.48 58,674.56 4.03kg 60,439.49 159,489.19 16,446.4802.03.05.04 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60
2,222.77 1,837.00 1.21m2 1,221.24 918.50 81.0102.03.05.05 CURADO
1,283,866.9202.03.06 VIGAS 58,332.87 170,960.00 654,497.35 399,933.11
259,990.40 742.13 350.33m3 20,635.09 236,745.40 2,614.9702.03.06.01 CONCRETO fc = 315 kg/cm2 VIGAS
102,579.55 302.14 339.51m3 8,401.07 93,117.44 1,064.6202.03.06.02 CONCRETO fc = 280 kg/cm2 VIGAS
507,751.20 6,838.40 74.25m2 262,762.23 47,863.33 26,163.7202.03.06.03 170,960.00ENCOFRADO Y DESENCOFRADO VIGAS
405,271.31 100,563.60 4.03kg 103,588.56 273,351.98 28,187.9902.03.06.04 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60
8,274.46 6,838.40 1.21m2 4,546.16 3,419.20 301.5702.03.06.05 CURADO
1,364,276.5202.03.07 LOSAS ALIGERADAS 31,945.67 145,872.60 785,850.90 400,981.02
161,736.85 461.67 350.33m3 12,836.84 147,276.42 1,626.7402.03.07.01 CONCRETO fc = 315 kg/cm2 LOSAS ALIGERADAS
145,306.88 427.99 339.51m3 11,900.36 131,903.52 1,508.0702.03.07.02 CONCRETO fc = 280 kg/cm2 LOSAS ALIGERADAS
419,918.59 9,724.84 43.18m2 174,355.52 82,291.60 17,353.9802.03.07.03 145,872.60ENCOFRADO Y DESENCOFRADO LOSAS ALIGERADAS
83,411.45 20,697.63 4.03kg 21,320.22 56,260.30 5,801.5502.03.07.04 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60
186,514.95 61,965.10 3.01und 49,627.85 135,889.46 1,487.1602.03.07.05 LADRILLO DE BOVEDILLA 0.15mX0.30mX0.30m.
589.94 204.13 2.89und 171.69 409.38 8.5702.03.07.06 LADRILLO ARCILLA PARA TECHO DE 15X30X30cm
355,030.80 19,400.59 18.30m 124,303.46 226,957.80 3,730.7302.03.07.07 VIGUETA FIRTH
11,767.06 9,724.84 1.21m2 6,465.08 4,862.42 428.8702.03.07.08 CURADO
197,030.6102.03.08 LOSAS MACIZAS 7,056.42 14,910.15 132,540.31 42,517.87
57,517.18 164.18 350.33m3 4,565.06 52,374.74 578.5002.03.08.01 CONCRETO fc = 315 kg/cm2 LOSAS MACIZAS
34,082.15 103.59 329.01m3 2,880.34 30,838.02 365.0102.03.08.02 CONCRETO fc = 280 kg/cm2 LOSAS MACIZAS
44,303.03 994.01 44.57m2 19,094.51 8,411.31 1,901.0402.03.08.03 14,910.15ENCOFRADO Y DESENCOFRADO LOSAS MACIZAS
59,925.50 14,869.85 4.03kg 15,317.14 40,419.23 4,168.0302.03.08.04 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60
1,202.75 994.01 1.21m2 660.82 497.01 43.8402.03.08.05 CURADO
98,916.8002.03.09 ESCALERAS 3,640.21 72,823.76 22,445.80
61,489.73 185.91 330.75m3 5,173.96 55,344.11 972.5802.03.09.01 CONCRETO fc = 280 kg/cm2 ESCALERAS
22,940.47 325.12 70.56m2 13,453.44 7,811.34 1,673.0602.03.09.02 ENCOFRADO Y DESENCOFRADO NORMAL ESCALERAS
14,093.19 3,497.07 4.03kg 3,602.26 9,505.74 980.2302.03.09.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60
393.41 325.13 1.21m2 216.14 162.57 14.3402.03.09.04 CURADO
140,392.3302.03.10 CISTERNA 6,048.08 98,909.30 35,419.66
56,693.92 162.82 348.20m3 4,897.77 51,291.23 505.4202.03.10.01 CONCRETO fc = 315 kg/cm2 CISTERNA
35,792.77 736.78 48.58m2 18,015.12 15,539.05 2,240.1802.03.10.02 ENCOFRADO Y DESENCOFRADO EN CISTERNA
47,014.14 11,666.04 4.03kg 12,016.96 31,710.63 3,269.9902.03.10.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60
891.50 736.78 1.21m2 489.81 368.39 32.4902.03.10.04 CURADO
Costo Directo 9,636,801.05
Gastos Generales 963,680.11
16/03/2015 03:23:04p.m.Fecha :
-
S10 Pgina 4
Presupuesto"MEJORAMIENTO INTEGRAL DE LOS SERVICIOS DE LA SEDE CENTRAL DE PERUPETRO - SAN BORJA - LIMA - LIMA"0103001Presupuesto
ESTRUCTURAS001SubpresupuestoPERUPETRO S.A 04/04/2015Costo alCliente
Lugar LIMA - LIMA - SAN BORJA
Precio S/. Parcial S/.Mano de Obra Material Equipo SubcontratoItem Descripcin Und. Metrado
Utilidad 770,944.08
=============
Subtotal 11,371,425.24
IGV 2,046,856.54
===================
Total_Presupuesto 13,418,281.78
SON : TRECE MILLONES CUATROCIENTOS DIECIOCHO MIL DOSCIENTOS OCHENTIUNO Y 78/100 NUEVOS SOLES