NUEVAS TECNICAS DE PROGRAMACION DE OBRAS
UNIVERSIDAD : UNIVERSIDAD ALAS PERUANAS
CICLO : X
DOCENTE : Ing. CARLOS LARA CARPIOFECHA : AGOSTO 2015
Item DESCRIPCION UND METRADOCUADRILLA
OP OF PEMOVIMIENTO DE TIERRA
EXCAVACION MANUAL / ZAPATAS profund. = 1.30 m m3 12 0 0 1
1.00 EXCAVACION DE CIMIENTO m3 7 0 0 1
OBRAS DE CONCRETO SIMPLE
CONCRETO EN SOLADO e=10cm m2 9 2 1 6
CONCRETO EN CIMIENTO m3 11 1 2 8
CONCRETO EN SOBRECIMIENTO m3 1 1 2 8
CONCRETO ARMADO
CONCRETO EN ZAPATAS m2 6 2 1 6
![Page 2: Programacion de Obras1](https://reader036.fdocuments.co/reader036/viewer/2022082819/563dbaf2550346aa9aa8f504/html5/thumbnails/2.jpg)
NUEVAS TECNICAS DE PROGRAMACION DE OBRAS
RENDIMIENTO
# DIAS# personas x cuadrilla / DIA NUEVO # DIAS x Cuadrilla
Und. medida/dia OP OF PE OP OF PE
6 2.05 5.00 0.00 0.00 2.00 0.0 0.0 1.0
4 1.76 4.00 0.00 0.00 2.00 0.0 0.0 0.9
60 0.16 5.00 2.00 1.00 6.00 0.1 0.2 0.0
25 0.44 5.00 1.00 2.00 8.00 0.4 0.2 0.1
10 0.11 4.00 1.00 2.00 8.00 0.1 0.1 0.0
60 0.09 5.00 2.00 1.00 6.00 0.0 0.1 0.0
# VECES DE CUADRILLA x
DIA
![Page 3: Programacion de Obras1](https://reader036.fdocuments.co/reader036/viewer/2022082819/563dbaf2550346aa9aa8f504/html5/thumbnails/3.jpg)
NUEVAS TECNICAS DE PROGRAMACION DE OBRAS
1.0
0.9
0.2
0.4
0.1
0.1
0.0
Dias x Partida