OSHA 29 CFR Part 1926OSHA 29 CFR Part 1926Cranes & Derricks In ConstructionCranes & Derricks In Construction
Session Outline• 1926.1419 Signals –
General• 1926.1420 Signals – Radio,
etc.• 1926.1421 Signals – Voice• 1926.1422 Signals – Hand
Signals• 1926.1427 Operator
Certification & Qualification• 1926.1428 Signal Person
Qualifications• 1926.1429 Training
• Presented By:• Ted L. Blanton
President NACB, Inc.
(800) 654-5640
OSH
A 1
926.
1400
OSH
A 1
926.
1400
OSHA 29 CFR Part 1926OSHA 29 CFR Part 1926Cranes & Derricks In ConstructionCranes & Derricks In Construction
Effective Date: November 8, 2010• Employers Must Provide
• Qualified Riggers– Assembly/Disassembly
– 1926.1404 (r)(1)– Rigging Materials in the “Fall
Zone”– 1926.1425 (c)(3)
• Qualified Signal Persons– 1926.1428
OSH
A 1
926.
1400
OSH
A 1
926.
1400
OSHA §29 CFR Part 1926OSHA §29 CFR Part 1926Cranes & Derricks In ConstructionCranes & Derricks In Construction
Effective Date: November 8, 2010• Signal Persons are discussed
throughout the 1400 standard.• 1419 Signals – General• 1420 Signals – Radio, etc.• 1421 Signals – Voice• 1422 Signals – Hand Signals• 1428 Signal Person
Qualifications
OSH
A 1
926.
1400
OSH
A 1
926.
1400
OSHA §29 CFR Part 1926OSHA §29 CFR Part 1926Cranes & Derricks In ConstructionCranes & Derricks In Construction
Effective Date: November 8, 2010• Definitions
• Qualified Rigger– a “Qualified Rigger” is a rigger
who meets the criteria for a “Qualified Person”
• Qualified Person– means a person who, by
possession of a recognized degree, certificate, or professional standing, or who by extensive knowledge, training and experience, successfully demonstrated the ability to solve/resolve problems relating to the subject matter, the work, or the project.
OSH
A 1
926.
1401
OSH
A 1
926.
1401
OSHA §29 CFR Part 1926OSHA §29 CFR Part 1926Cranes & Derricks In ConstructionCranes & Derricks In Construction
Effective Date: November 8, 2010• How To Document a Qualified
Persons ability to solve/resolve work related problems (i.e. rigging, etc.)
• Academic– Degree (engineering, etc.)– Journey Level Certification (DOE
Approved Apprentice Program)– National Certification (NCCER,
NCCCO, CIC, etc.)– Certificate of Training from a
National Training Organization (NACB, CICB, CIA, etc.)
– Proof of Professional Standing
OSH
A 1
926.
1401
OSH
A 1
926.
1401
OSHA §29 CFR Part 1926OSHA §29 CFR Part 1926Cranes & Derricks In ConstructionCranes & Derricks In Construction
Effective Date: November 8, 2010• How To Document a Qualified
Persons ability to solve/resolve work related problems (i.e. rigging, etc.)
• Experience– Proof of Training
– Certificate of Training– Training Records– Successful Completion of a
Written Examination– Proof of Experience
– Work Records– Resume– Successful Completion of a
Practical Examination
OSH
A 1
926.
1401
OSH
A 1
926.
1401
OSHA §29 CFR Part 1926OSHA §29 CFR Part 1926Cranes & Derricks In ConstructionCranes & Derricks In Construction
Effective Date: November 8, 2010• 1419 States that a signal person
must be provided in each of the following situations:
• The point of operation, meaning the load travel or the area near or at load placement, is not in full view of the operator.
• When the equipment is traveling, the view in the direction of travel is obstructed.
• Due to site specific safety concerns, either the operator or the person handling the load determines that it is necessary.
OSH
A 1
926.
1419
OSH
A 1
926.
1419
OSHA §29 CFR Part 1926OSHA §29 CFR Part 1926Cranes & Derricks In ConstructionCranes & Derricks In Construction
Effective Date: November 8, 2010
• Effective 11/8/2010 Employers Must;• Ensure Operators Are
Competent And Safe (1926.1427 (k))
– Trained & Evaluated– Certification
Requirements Effective Nov.10, 2014
OSH
A 1
926.
1427
OSH
A 1
926.
1427
OSHA §29 CFR Part 1926OSHA §29 CFR Part 1926Cranes & Derricks In ConstructionCranes & Derricks In Construction
Effective Date: November 10, 2014• Effective 11/10/2014
Employers Must;• Ensure Operators Are Qualified
& Certified (1926.1427(a))• 1926.1427 (b) Option 1)
Certified by an Accredited Crane Operator Testing Organization
– NCCER– NCCCO (CCO)– CIC– Other
• Must be Portable• Must be Valid For 5 Years
OSH
A 1
926.
1427
OSH
A 1
926.
1427
OSHA §29 CFR Part 1926OSHA §29 CFR Part 1926Cranes & Derricks In ConstructionCranes & Derricks In Construction
Effective Date: November 10, 2014• Effective 11/10/2014
Employers Must;• Ensure Operators Are Qualified
& Certified• 1926.1427 (c) Option 2)
Qualification by an Audited Employer Program
– Written & Practical Testing– Audited By an Option 1
Organization• May Not be Portable• Must be Valid For 5 YearsO
SHA
192
6.14
27O
SHA
192
6.14
27
OSHA §29 CFR Part 1926OSHA §29 CFR Part 1926Cranes & Derricks In ConstructionCranes & Derricks In Construction
Effective Date: November 10, 2014• Effective 11/10/2014 The
following applies;• Pre-Qualification/Certification
Training Period (1926.1427 (f))– All Operators Not Certified May Only
Operate As An Operator-in-training (OIT).
– Must Be Provided Sufficient Training– Tasks Performed During Training
Within Trainees Capability– Trainer
– Employee or Agent– Certified Operator, or– Passed Written– Familiar with Controls– No Distractions
OSH
A 1
926.
1427
OSH
A 1
926.
1427
OSHA §29 CFR Part 1926OSHA §29 CFR Part 1926Cranes & Derricks In ConstructionCranes & Derricks In Construction
Effective Date: November 8, 2010• 1428 Signals –Signal Person
Qualification:• Ensure Signal Persons Are
Qualified (2 Options)– Option1) 3rd Party, or– Option 2) In-House
Qualified Evaluator
OSH
A 1
926.
1428
OSH
A 1
926.
1428
OSHA §29 CFR Part 1926OSHA §29 CFR Part 1926Cranes & Derricks In ConstructionCranes & Derricks In Construction
Effective Date: November 8, 2010• 1428 Signals –Signal Person
Qualification:• Qualification Requirements
– Know & Understand Types of Signals to be Used
– Be Competent in there Application
– Have a Basic Understanding Of Equipment;
– Operation & Limitations– Load Dynamics
» Swinging &» Stopping of Load
– Boom Deflection from Hoisting
OSH
A 1
926.
1428
OSH
A 1
926.
1428
OSHA §29 CFR Part 1926OSHA §29 CFR Part 1926Cranes & Derricks In ConstructionCranes & Derricks In Construction
Effective Date: November 8, 2010• 1428 Signals –Signal Person
Qualification:• Qualification Requirements
– Know & Understand– 1926.1419– 1926.1420– 1926.1421– 1926.1422 &– 1926.1428
– Demonstrate Requirements Through both;
– Written (or Oral) Testing– Practical Testing.O
SHA
192
6.14
28O
SHA
192
6.14
28
OSHA §29 CFR Part 1926OSHA §29 CFR Part 1926Cranes & Derricks In ConstructionCranes & Derricks In Construction
Effective Date: November 8, 2010
• Effective 11/8/2010 Employers Must;• Have Provided Training
as Follows:– On Overhead Power Lines– To Signal Persons– To Operators– To Competent & Qualified
Persons– On Crush/Pinch Points– On Tag-Out
• Training AdministrationOSH
A 1
926.
1430
OSH
A 1
926.
1430