DIAGRAMA DE GANTTPROGRAMAR Y
PLANIFICAR
FLAVIO URIEL ROSARIO FLORESMENDIOLA VAZQUEZ GUSTAVO
CONTROL DE PROYECTOS CON GRÁFICA DE GANTT
PROYECTO CASA UNIFAMILIAR: TRABAJOS PRELIMINARES
TAREA DURACION INICIO FIN DESCRIPCION
TAREA A 1 11-11-15 12-11-15 A= LIMPIEZA DEL TERRENO
TAREA B 2 13-11-15 15-11-15 B= TRAZO Y NIVELACION
TAREA C 5 15-11-15 20-11-15 C= EXCAVACION
TAREA D 7 20-11-15 27-11-15 D= PLANTILLA
TAREA E 3 21-11-15 24-11-15E= CIMBRA EN CIMENTACION
TAREA F 6 21-11-15 27-11-15F= ACERO DE REFUERZO EN LA CIMENTACION
TAREA G 14 27-11-15 11-12-15G= COLADO DE LA CIMENTACION
TAREA H 7 27-11-15 04-12-15H= ACERO EN CADENA DE DESPLANTE
TAREA A
TAREA B
TAREA C
TAREA D
TAREA E
TAREA F
TAREA G
TAREA H
11/11/2015 11/14/2015 11/17/2015 11/20/2015 11/23/2015 11/26/2015 11/29/2015 12/2/2015 12/5/2015 12/8/2015 12/11/2015
PLANNING