8/11/2019 Mavis Presentation 2.pptx
1/23
AN INDUSTRIAL TRAININGEXPERIENCE PRESENTATION
BY
ALIEMEKE MARVIS EMEKEU2009/3010262
DONE AT
MINISTRY OF NIGER DELTA AFFAIRS(MNDA)
8/11/2019 Mavis Presentation 2.pptx
2/23
OUTLINE
Introduction
Activities of different sections on site
Problems encountered
Relevance of the SIWES Programme
8/11/2019 Mavis Presentation 2.pptx
3/23
Contd.
Ways of improving the programme
Advice for future participants
Advice for SIWES managers
Conclusion
8/11/2019 Mavis Presentation 2.pptx
4/23
INTRODUCTION
Location of project/activities carried out in thecourse of the project
History of ministry of Niger Delta Affairs (MNDA)
Scope of works
Organizational chart
8/11/2019 Mavis Presentation 2.pptx
5/23
Ministers Office
Minister of States Office
Permanent Secretarys Office
Director Highway
Deputy Director Highway
Engineers Representative
Assistant Engrs Representative
Administrator Maintenance Chief Resident Engr
ReceptionistSecretary
Clerk/typistLaboratory Superintendent Resident Engr (1)
Resident Engr (II) Technology Assistant
Me (industrial trainee)
Maintenance
8/11/2019 Mavis Presentation 2.pptx
6/23
ACTIVITIES OF DIFFERENT SECTIONSON SITE
Earthmoving
Bush clearing carried out by anexcavator.
A bulldozer carrying a leveling processon the excavated subgrade.
8/11/2019 Mavis Presentation 2.pptx
7/23
Excavation of unsuitable material. A sheep-foot roller compacting theexcavated subgrade.
Contd.
8/11/2019 Mavis Presentation 2.pptx
8/23
Cement stabilization
Spraying of cement by a wheel loaderready for stabilization process.
A pulverizer carrying out sand-cementmixing (sand-cement stabilization).
8/11/2019 Mavis Presentation 2.pptx
9/23
Bridge/Pile construction
Pile work process A casen used for pile casting.
A reinforcement cage used for pilecasting.
8/11/2019 Mavis Presentation 2.pptx
10/23
Contd.
Insertion of pile casen by the crane withthe use of a vibro-machine into theground.
A drilling rig carrying out a drilling processin the pile casen.
8/11/2019 Mavis Presentation 2.pptx
11/23
Contd.
A concrete pump ready for pile casting through the triming pipe inserted intothe drilled pile.
8/11/2019 Mavis Presentation 2.pptx
12/23
Reinforcement detail used for the pilling work
Size/thickness
of reinforcement
Length
(m)
Lap
length(m)
No of
reinforcementused
26 T 20 2.8 120 1
26 T 20 11.7 120 2
26 T 25 12 150 1
24 T 32 12 190 1
Contd.
8/11/2019 Mavis Presentation 2.pptx
13/23
Number of casen used/length of each casenNo of casen used Length of casen(m)
1 7.5
1 12.5
2 5
Contd.
8/11/2019 Mavis Presentation 2.pptx
14/23
8/11/2019 Mavis Presentation 2.pptx
15/23
Contd.
Casting of the drainage wall after the drainage form work.
8/11/2019 Mavis Presentation 2.pptx
16/23
PROBLEMS ENCOUNTERED
Industrial training placement
Poor pay pack
No insurance cover
8/11/2019 Mavis Presentation 2.pptx
17/23
RELEVANCE OF SIWES PROGRAMM
Acquisition of industrial skills and experiences in
their course of study.
The program prepares students for work
situations/conditions they are likely to meet after
graduation.
8/11/2019 Mavis Presentation 2.pptx
18/23
WAYS OF IMPROVING THE PROGRAM
Industrial training students should be exposed to
all companies facilities and jobs, since they are
the future of industrialization.
Establishments should be forced to offer
attachment to industrial training students.
8/11/2019 Mavis Presentation 2.pptx
19/23
ADVICE FOR FUTURE PARTICIPANTS
They should put in their best regardless of the
pay pack.
They should obey safety measure.
8/11/2019 Mavis Presentation 2.pptx
20/23
ADVICE FOR SIWES MANAGERS
SIWES officials, should carry out a routine check
at their students place of work.
8/11/2019 Mavis Presentation 2.pptx
21/23
8/11/2019 Mavis Presentation 2.pptx
22/23
ACKNOWLEDGEMENT
Ministry of Niger Delta Affairs (MNDA)
Engr. Igwe
Engr. Odia
Engr. LeoEngr. Henry
Engr. Steve
All Lecturers of Civil Engineering Department /
The School Authority
Surv. K. A. Raheem
8/11/2019 Mavis Presentation 2.pptx