RBM-MERG Malaria Indicator Training Workshop, 9th-12th September 2008, Lusaka, Zambia 1 Budgeting for a Malaria Indicator Survey Dr Ayub Manya & Laurent Bergeron

Transcript of 9 mis budget

Page 1: 9 mis budget

RBM-MERG Malaria Indicator Training Workshop, 9th-12th September 2008, Lusaka, Zambia 1

Budgeting for a Malaria Indicator Survey

Dr Ayub Manya & Laurent Bergeron

Page 2: 9 mis budget

RBM-MERG Malaria Indicator Training Workshop, 9th-12th September 2008, Lusaka, Zambia 2

Outline of presentation

• Pre Survey Budgeting to secure funding• Actual allocation of funds during planning and

implementation

Page 3: 9 mis budget

RBM-MERG Malaria Indicator Training Workshop, 9th-12th September 2008, Lusaka, Zambia 3

Pre-Survey budgeting

Two-fold: • Get a quick estimate - using key information- of what financial

resources are needed to conduct an MIS• Identify potential financial needs ahead of time to secure

funding

Page 4: 9 mis budget

RBM-MERG Malaria Indicator Training Workshop, 9th-12th September 2008, Lusaka, Zambia 4

Cost of an MIS

• What determines the cost of an MIS?Mainly:

– Sample size– In-country costs

Page 5: 9 mis budget

RBM-MERG Malaria Indicator Training Workshop, 9th-12th September 2008, Lusaka, Zambia 5

Rationale

Budgeting an MIS consists in: • Spanning key activities & stages from MIS-planning through

MIS report-writing and dissemination• Budgeting associated cost categories and budget line items

using country-specific and MIS-specific data (sample size, clusters, per diems, etc.)

Page 6: 9 mis budget

RBM-MERG Malaria Indicator Training Workshop, 9th-12th September 2008, Lusaka, Zambia 6

Securing funding to conduct your MIS

• A preliminary budget can be useful to involve your partners, by distributing specific activities among them

• Include request for MIS funding in your Global Fund proposal – need to have a pretty good idea of the cost.

Page 7: 9 mis budget

RBM-MERG Malaria Indicator Training Workshop, 9th-12th September 2008, Lusaka, Zambia 7

Budgeting for implementation

Page 8: 9 mis budget

RBM-MERG Malaria Indicator Training Workshop, 9th-12th September 2008, Lusaka, Zambia 8

Step 1: MIS coordination

MIS Coordinator: From planning to the end of field work,

right through to the dissemination meeting

Can consider hiring an assistant too…

Page 9: 9 mis budget

RBM-MERG Malaria Indicator Training Workshop, 9th-12th September 2008, Lusaka, Zambia 9

Step 2: Protocol development

• Protocol development and submission to ethical committees is a collaborative process that requires mainly TA time (usually staff time and travel costs) among stakeholders and donors

Page 10: 9 mis budget

RBM-MERG Malaria Indicator Training Workshop, 9th-12th September 2008, Lusaka, Zambia 10

Step 3: CSO engagement sample selection

CSO engagement in the following:• Sample design preparation / protocol development• Map preparation and printing (clusters and pre-testing site)• Depending on countries specificities, translation cost of

questionnaires and consent forms into local languages

Page 11: 9 mis budget

RBM-MERG Malaria Indicator Training Workshop, 9th-12th September 2008, Lusaka, Zambia 11

Step 4: Communication strategy

In advance or/during the MIS, the following need to be considered:

Production of radio spots Airing of radio spots (national/regional

radio) District sensitization meeting Enumeration area advocacy meetings Calendars, leaflets, etc.

Page 12: 9 mis budget

RBM-MERG Malaria Indicator Training Workshop, 9th-12th September 2008, Lusaka, Zambia 12

Communication budget Kenya

Item Description Unit cost No Cost

Radio Advert 30000 20 600,000

District sensitisation meeting Meeting 200000 24 4,800,000

Print Advert 350,000 8 2,800,000

Total 8,200,000

Page 13: 9 mis budget

RBM-MERG Malaria Indicator Training Workshop, 9th-12th September 2008, Lusaka, Zambia 13

Step 5: Commodities

Main cost categories:• PDAs or paper• RDTs• Drugs (depending on your national guidelines)• Hemocues for anemia testing

Page 14: 9 mis budget

RBM-MERG Malaria Indicator Training Workshop, 9th-12th September 2008, Lusaka, Zambia 14

Step 6: MIS training

• Per diem and transport costs for data collectors• Venue• Supplies for field testing activities

Page 15: 9 mis budget

RBM-MERG Malaria Indicator Training Workshop, 9th-12th September 2008, Lusaka, Zambia 15

Example of training budget, KenyaItem No Unit cost No of days Total

Accommodation for trainees 144 4,000 6 3,456,000

Allowances for trainees 144 500 6 432,000

Per diem for facilitators 24 4,500 6 648,000

Drivers allowances 8 2,000 6 96,000

Secretaries 2 2,500 6 30,000

Facilitators allowances 16 2,600 6 240.000

Transport operations 192,000

Production of supervisor and training manuals, SOPs, etc.

1,036,800

Stationery 48,000

Total 6,174,000

Page 16: 9 mis budget

RBM-MERG Malaria Indicator Training Workshop, 9th-12th September 2008, Lusaka, Zambia 16

Step 7: Data collection/field work

• Per diems• Vehicles • Communication (phone calls)

Page 17: 9 mis budget

RBM-MERG Malaria Indicator Training Workshop, 9th-12th September 2008, Lusaka, Zambia 17

Step 8: Slide transport and reading

• Slide readers• Transport cost back to central level

Page 18: 9 mis budget

RBM-MERG Malaria Indicator Training Workshop, 9th-12th September 2008, Lusaka, Zambia 18

Step 9: Report preparation and dissemination

• Printing of final report• Dissemination meetings: central and regional

levels

Page 19: 9 mis budget

RBM-MERG Malaria Indicator Training Workshop, 9th-12th September 2008, Lusaka, Zambia 19

Thank you!