CRONOGRAMA DE AVANCE FISICO DE OBRA EN PORCENTAJE
PROYECTO:ETAPA : TODO EL PROYECTOREGION: PROVINCIA: DISTRITO:
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1 MES 2 MES 3 MES 4
% % % %
01 OBRAS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZ. DE MAQUINARIAS Y EQUIPOS glb 1.00 56,080.0056,080.00 30.0% 70.0%
01.02 CARTEL DE OBRA .60!5."0 #$% .00 2,100.""6,301.32 33.3% 33.3% 33.3%
01.0 TOPO&RA'IA Y &EORE'ERENCIACION () 10.1" 1,16.*111,526.24 9.9% 11.2% 9.9% 9.9%
01.0" TOPO&RA'IA Y &EORE'ERENCIACION DURANTE EL PROCESO DE E+ECUCION () 10.1" **1.*57,825.55 9.9% 11.2% 9.9% 9.9%
01.05 CAMPAMENTO TRANSPORTABLE PARA OBRA glb 1.00 1",000.0014,000.00 72.0%
01.06 MANTENIMIENTO DE TRANSITO TEMPORAL Y SE&URIDAD VIAL )- .00 "0,*68.6122,306.88 33.3%
01.0* () .50 ",*50."16,626.19 28.6% 42.9%
01.08 MONTA+E Y DESMONTA+E DE PLANTA DE AS'ALTO glb 1.00 121,0**.61121,077.61 50.0%
01.0 MONTA+E Y DESMONTA+E DE PLANTA C/ANCADORA glb 1.00 58,0*.8658,079.86 50.0%
02 EXPLANACIONES
02.01 ECAVACION EN MATERIAL SUELTO ) 6,00.00 10.5266,276.00 33.3% 33.3% 33.3%
02.02 ECAVACION EN ROCA SUELTA ) ,10.00 16.2851,933.20 31.3% 35.4% 33.2%
02.0 ECAVACION EN ROCA 'I+A ) 12,280.00 2.8*366,803.60 24.4% 25.6%
02.0" RELLENO CON MATERIAL PROPIO ) 21,665.00 8.""182,852.60
02.05 CON'ORMACION DE TERRAPLEN CON MATERIAL DE CANTERA ) 85,000.00 28.882,454,800.00 9.4% 9.4% 9.4%
0 CARPETA ASFALTICA
ACCESO A CANTERAS, BOTADEROS, PLANTAS DE PROCESO Y 'UENTES DEA&UA
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
2/42
CRONOGRAMA DE AVANCE FISICO DE OBRA EN PORCENTAJE
PROYECTO:ETAPA : TODO EL PROYECTOREGION: PROVINCIA: DISTRITO:
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1 MES 2 MES 3 MES 4
% % % %
0.01 SUBBASE &RANULAR E320 CM4 )2 0,5*.00 15.081,366,202.76 9.9% 10.6% 9.9% 9.9%
0.02 BASE &RANULAR E320 CM4 )2 0,5*.00 16.8*1,528,371.39 9.9% 10.6% 9.9%
0.0 IMPRIMACION AS'ALTICA )2 0,5*.00 1.65149,485.05 9.9% 10.6%
0.0" CARPETA AS'ALTICA EN CALIENTE ) 5,5"5.00 21.81,619,029.10
0.05 CEMENTO AS'ALTICO PEN 85100 gl 1*0,250.00 *.001,191,750.00
0.06 AS'ALTO LIQUIDO MC0 gl ,2*0.00 8.50282,795.00
0.0* ADITIVO ME+ORADOR DE AD/ERENCIA (g 5,5"5.00 28.00155,260.00
0.08 'ILLER CAL /IDRATADA4 (g 21,80.00 1.50320,835.00
0" OBRAS DE ARTE Y DRENAJE
0".01 CUNETAS TRIANGULAR TIPO I
0".01.01 ECAVACION EN MATERIAL SUELTO A MANO ) 1,"1.00 6.2051,802.20 24.5% 26.6% 24.5%
0".01.02 CONCRETO 7931*5 (g9)2 PARA CUNETAS ) 681.00 "25.8290,031.09 29.4% 29.4%
0".01.0 CONCRETO 793210 (g9)2 PARA CUNETAS ) 500.00 "5.5226,765.00 25.0% 25.0%
0".01.0" ENCO'RADO Y DESENCO'RADO DE CUNETAS REVESTIDA )2 ,660.00 *.1"358,772.40 25.0% 25.0%
0".01.05 ACERO DE RE'UERZO 7:3",200 (g9)2 (g 12,500.00 5.173,875.00 25.0% 25.0%
0".01.06 +UNTA AS'ALTICA ) 2,00.00 5.2210,596.60 26.1% 24.6%
0".02 CUNETAS CUADRADAS TIPO II EN ZONA URBANA
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
3/42
CRONOGRAMA DE AVANCE FISICO DE OBRA EN PORCENTAJ
PROYECTO:ETAPA : TODO EL PROYECTOREGION: PROVINCIA: DISTRITO:
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1 MES 2 MES 3 MES
% % % %
0".02.01 ECAVACION EN MATERIAL SUELTO A MANO ) ,15.00 6.20141,723.00 25.3% 24.9
0".02.02 CONCRETO 7931*5 (g9)2 PARA CUNETAS ) 1,60.00 "25.8834,744.40 25.0
0".02.0 CONCRETO 793280 (g9)2 PARA TAPA ) 655.00 5"6.8357,878.90 26.3
0".02.0" CONCRETO 793100 (g9)2 PARA SOLADO )2 5,220.00 "0.52211,514.40 25.0
0".02.05 ENCO'RADO Y DESENCO'RADO DE CUNETAS REVESTIDA )2 11,*"5.00 *.1"436,209.30 20.0% 20.0
0".02.06 ACERO DE RE'UERZO 7:3",200 (g9)2 (g *5,000.00 5.1443,250.00 20.0% 20.0
0".02.0* +UNTA AS'ALTICA ) ",56*.00 5.2223,839.74 25.1
0".0 ALCANTARILLA DE MARCO DE CONCRETO MCA
0".0.01 DEMOLICION DE ESTRUCTURAS EISTENTES ) 6".51 1".29,243.64 100.0%
0".0.02 ECAVACION NO CLASI'ICADA PARA ESTRUCTURAS ) 1,15.00 15.*21,000.55 100.0%
0".0.0 RELLENO COMPACTADO PARA ESTRUCTURAS ) 1,510.00 ".051,385.30 50.0% 50.0%
0".0.0" CONCRETO 793210 (g9)2 ) 680.00 "5.5308,400.40 50.0% 50.0%
0".0.05 CONCRETO 793100 (g9)2 PARA SOLADO )2 "2.60 "0.5217,164.27 52.8% 47.2%
0".0.06 ENCO'RADO Y DESENCO'RADO DE ESTRUCTURAS NORMAL )2 2,*65.00 ".0135,733.85 36.2% 36.2% 27.7%
0".0.0* LIMPIEZA DE CAUCE DE ALCANTARILLAS ) 2,666.00 5.*695,336.16 50.0% 50.0%
0".0.08 ACERO DE RE'UERZO 7:3",200 (g9)2 (g 18,000.00 5.1106,380.00 50.0% 50.0%
0".0.0 EMBOQUILLADO DE PIEDRA E30.20M )2 610.00 18.11
84,247.10 100.0%
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
4/42
CRONOGRAMA DE AVANCE FISICO DE OBRA EN PORCENTAJ
PROYECTO:ETAPA : TODO EL PROYECTOREGION: PROVINCIA: DISTRITO:
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1 MES 2 MES 3 MES
% % % %
0".0" ALCANTARILLA CON TUBERIA DE ACERO TMC
0".0".01 ECAVACION NO CLASI'ICADA PARA ESTRUCTURAS ) "15.00 15.*6,627.55 27.7% 24.1% 24.1%
0".0".02 RELLENO COMPACTADO PARA ESTRUCTURAS ) 5.00 ".011,400.05 40.3% 29.9%
0".0".0 CONCRETO 7931*5 (g9)2 ) 51.00 "25.821,720.39 51.0%
0".0".0" ENCO'RADO Y DESENCO'RADO DE ESTRUCTURAS NORMAL )2 28.00 ".011,683.42 41.2% 29.4%
0".0".05 LIMPIEZA DE CAUCE DE ALCANTARILLAS ) 165.00 5.*65,900.40 51.5% 48.5%
0".0".06 ACERO DE RE'UERZO 7:3",200 (g9)2 (g 2,"00.00 5.114,184.00 33.3% 33.3% 33.3%
0".0".0* ALCANTARILLA METALICA CIRCULAR TMC ;36< )ll 115.00 51.*59,078.95 52.2%
0".0".08 EMBOQUILLADO DE PIEDRA E30.20M )2 8*.00 18.1112,015.57
0".05 SUB DRENES
0".05.01 ECAVACION DE SUELO PSUB DRENES CEQUIPO ) 110.00 5.""3,898.40
0".05.02 MATERIAL SELECCIONADO PARA 'ILTRADO ) 1*5.00 *".213,111.00
0".05.0 CAMA DE ARENA E30.10M )2 120.00 1.623,794.40
0".05.0" RELLENO CON MATERIAL ARCILLOSO E30.10M )2 120.00 1.1*1,580.40
0".05.05 MALLA &EOTETIL )2 "50.00 15.5*7,006.50
0".05.06 CONCRETO 7931*5 (g9)2 PARA SUB DRENES ) 5.00 "25.82,129.45
0".05.0* ENCO'RADO Y DESENCO'RADO DE ESTRUCTURAS NORMAL )2 "0.00 ".0
1,963.60
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
5/42
CRONOGRAMA DE AVANCE FISICO DE OBRA EN PORCENTAJE
PROYECTO:ETAPA : TODO EL PROYECTOREGION: PROVINCIA: DISTRITO:
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1 MES 2 MES 3 MES 4
% % % %
0".05.08 ACERO DE RE'UERZO 7:3",200 (g9)2 (g 250.00 5.11,477.50
0".05.0 TUBERIA PVC SAP PER'ORADA DE 6< ) 1*0.00 "6.2"7,860.80
0".05.10 TUBO 'IERRO &ALV. DE 2< ) 12.00 "8.00576.00
0".06 VEREDAS
0".06.01 OBRAS PRELIMINARES
0".06.01.01 TRAZO Y REPLANTEO )2 ,200.00 2.09,280.00
0".06.02 MOVIMIENTO DE TIERRAS
0".06.02.01 CORTE DE TERRENO MANUAL PARA VEREDAS )2 ,200.00 6.20,256.00
0".06.02.02 NIVELACION Y COMPACTACION DE TERRENO )2 ,200.00 .510,720.00
0".06.02.0 A'IRMADO PARA VEREDAS E3 6
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
6/42
CRONOGRAMA DE AVANCE FISICO DE OBRA EN PORCENTAJE
PROYECTO:ETAPA : TODO EL PROYECTOREGION: PROVINCIA: DISTRITO:
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1 MES 2 MES 3 MES 4
% % % %
0".0*.01 OBRAS PRELIMINARES
0".0*.01.01 TRAZO Y REPLANTEO )2 250.00 2.0725.00
0".0*.02 MOVIMIENTO DE TIERRAS
0".0*.02.01 ECAVACION ZAN+AS PARA ZAPATAS ) 100.00 "*.84,738.00
0".0*.02.02 COMPACTACION MANUAL )2 250.00 15.263,815.00
0".0*.0 OBRAS DE CONCRETO SIMPLE
0".0*.0.01 CONCRETO 793210 (g9)2 ) 20.00 "50.29,006.40
0".0*.0" ARQUITECTURA
0".0*.0".01 ESTRUCTURA DE PARADERO URBANO glb 28.00 ",800.00134,400.00
0".0*.0".02 ESTRUCTURA DE PARADERO RURAL glb 28.00 ,800.00106,400.00
0".0*.0".0 INSTALACION DE PARADERO URBANO glb 28.00 1,500.0042,000.00
0".0*.0".0" INSTALACION DE PARADERO RURAL glb 28.00 50.0026,600.00
05 TRANSPORTE PAGADO
05.01 TRANSPORTE DE MEZCLA AS'ALTICA PARA D=3 1 >M )( ,80.00 10.240,954.20
05.02 TRANSPORTE DE MEZCLA AS'ALTICA PARA D? 1 >M )( 20,60.00 .5572,278.00
05.0 TRANSPORTE DE MATERIAL &RANULAR PARA D = 3 1 >M )( 2,0*5.00 10.2*329,410.25 50.1% 49.9%
05.0" TRANSPORTE DE MATERIAL &RANULAR PARA D ? 1 >M )( 101,05.00 5.56561,754.60 35.7% 34.6% 29.7%
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
7/42
CRONOGRAMA DE AVANCE FISICO DE OBRA EN PORCENTAJE
PROYECTO:ETAPA : TODO EL PROYECTO
REGION: PROVINCIA: DISTRITO:
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1 MES 2 MES 3 MES 4
% % % %
05.05 TRANSPORTE DE MATERIAL PROVENIENTE DE CANTERA PARA D = 3 1 >M )( "5,000.00 .5"429,300.00 100.0%
05.06 TRANSPORTE DE MATERIAL PROVENIENTE DE CANTERA PARA D ? 1 >M )( 10*,*1.00 ".1"446,254.74 30.4% 23.2% 23.2%
05.0* ELIMINACION DE MATERIAL PROVENIENTE DE DERRUMBES PARA D = 3 1 >M )( 1,200.00 1.0*15,684.00
05.08 ELIMINACION DE MATERIAL PROVENIENTE DE DERRUMBES PARA D ? 1 >M )( 6,000.00 5."35,640.00
06 SEALIZACION Y SEGURIDAD VIAL
06.01 SE@ALIZACION Y SE&URIDAD VIAL glb 1.00 102,602.10102,602.10 100.0%
0* PROTECCION AMBIENTAL
0*.01 ACONDICIONAMIENTO DE ECEDENTES EN ZONAS DE BOTADEROS ) 500.00 .561,780.00 20.0% 20.0% 20.0%
0*.02 )2 10,500.00 1.6116,905.00
RECUPERACION AMB DE AREAS A'ECTADAS LIMP Y RESTAURACDCANTERAS
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
8/42
MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12
% % % % % % % %
9.9% 9.9% 9.9% 9.9% 9.9% 9.9%
9.9% 9.9% 9.9% 9.9% 9.9% 9.9%
28.0%
33.3% 33.3%
28.6%
50.0%
50.0%
25.6% 24.4%
18.5% 18.5% 18.5% 18.5% 18.5% 7.7%
9.4% 9.4% 9.4% 9.4% 9.4% 9.4% 9.4% 5.9%
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
9/42
MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12
% % % % % % % %
9.9% 9.9% 9.9% 9.9% 9.9% 9.9%
9.9% 9.9% 9.9% 9.9% 9.9% 9.9% 9.9%
9.9% 9.9% 9.9% 9.9% 9.9% 9.9% 9.9% 9.9%
18.0% 27.9% 18.0% 18.0% 18.0%
20.0% 20.0% 20.0% 20.0% 20.0%
20.0% 20.0% 20.0% 20.0% 20.0%
18.0% 27.9% 18.0% 18.0% 18.0%
20.0% 20.0% 20.0% 20.0% 20.0%
24.5%
29.4% 11.9%
25.0% 25.0%
25.0% 25.0%
25.0% 25.0%
24.6% 24.6%
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
10/42
MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12
% % % % % % % %
24.9% 24.9%
25.0% 25.0% 25.0%
24.6% 24.6% 24.6%
25.0% 25.0% 25.0%
20.0% 20.0% 20.0%
20.0% 20.0% 20.0%
25.0% 25.0% 25.0%
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
11/42
MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12
% % % % % % % %
24.1%
29.9%
49.0%
29.4%
47.8%
54.0% 46.0%
31.8% 22.7% 22.7% 22.7%
32.6% 32.6% 34.9%
50.0% 50.0%
50.0% 50.0%
33.3% 33.3% 33.3%
100.0%
50.0% 50.0%
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
12/42
MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12
% % % % % % % %
50.0% 50.0%
50.0% 50.0%
100.0%
37.5% 31.3% 31.3%
37.5% 31.3% 31.3%
37.5% 31.3% 31.3%
37.5% 31.3% 31.3%
37.5% 31.3% 31.3%
100.0%
37.5% 31.3% 31.3%
33.3% 33.3% 33.3%
50.0% 50.0%
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
13/42
MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12
% % % % % % % %
36.0% 32.0% 32.0%
50.0% 50.0%
50.0% 50.0%
50.0% 50.0%
50.0% 50.0%
50.0% 50.0%
50.0% 50.0%
50.0% 50.0%
49.7% 25.1% 25.1%
26.3% 24.6% 24.6% 24.6%
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
14/42
MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12
% % % % % % % %
23.2%
20.0% 20.0%
19.0% 19.0% 19.0% 19.0% 19.0% 4.8%
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
15/42
CRONOGRAMA DE AVANCE FISICO DE
PROYECTO:
REGION: PROVINCIA: DIST
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1 MES 2 M
CANT CANT C
01 OBRAS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZ. DE MAQUINARIAS Y EQUIPOS glb 1.00 56,080.0056,080.00 0.30 0.70
01.02 CARTEL DE OBRA .60!5."0 #$% .00 2,100.""6,301.32 1.00 1.00
01.0 TOPO&RA'IA Y &EORE'ERENCIACION () 10.1" 1,16.*111,526.24 1.00 1.14
01.0" TOPO&RA'IA Y &EORE'ERENCIACION DURANTE EL PROCESO DE E+ECUCION () 10.1" **1.*57,825.55 1.00 1.14
01.05 CAMPAMENTO TRANSPORTABLE PARA OBRA glb 1.00 1",000.0014,000.00 0.72
01.06 MANTENIMIENTO DE TRANSITO TEMPORAL Y SE&URIDAD VIAL )- .00 "0,*68.6122,306.88 1.00
01.0* ACCESO A CANTERAS, BOTADEROS, PLANTAS DE PROCESO Y 'UENTES DE A&UA () .50 ",*50." 16,626.19 1.00
01.08 MONTA+E Y DESMONTA+E DE PLANTA DE AS'ALTO glb 1.00 121,0**.61121,077.61 0.50
01.0 MONTA+E Y DESMONTA+E DE PLANTA C/ANCADORA glb 1.00 58,0*.8658,079.86 0.50
02 EXPLANACIONES
02.01 ECAVACION EN MATERIAL SUELTO ) 6,00.00 10.5266,276.00 2,100.00 2,100.00 2
02.02 ECAVACION EN ROCA SUELTA ) ,10.00 16.2851,933.20 1,000.00 1
02.0 ECAVACION EN ROCA 'I+A ) 12,280.00 2.8*366,803.60 3
02.0" RELLENO CON MATERIAL PROPIO ) 21,665.00 8.""182,852.60
02.05 CON'ORMACION DE TERRAPLEN CON MATERIAL DE CANTERA ) 85,000.00 28.882,454,800.00 8,000.00
0 CARPETA ASFALTICA
0.01 SUBBASE &RANULAR E320 CM4 )2 0,5*.00 15.081,366,202.76 9,000.00 9,597.00 9
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
16/42
CRONOGRAMA DE AVANCE FISICO DE
PROYECTO:
REGION: PROVINCIA: DIST
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1 MES 2 M
CANT CANT C
0.02 BASE &RANULAR E320 CM4 )2 0,5*.00 16.8*1,528,371.39 9,000.00
0.0 IMPRIMACION AS'ALTICA )2 0,5*.00 1.65149,485.05 9
0.0" CARPETA AS'ALTICA EN CALIENTE ) 5,5"5.00 21.81,619,029.10
0.05 CEMENTO AS'ALTICO PEN 85100 gl 1*0,250.00 *.001,191,750.00
0.06 AS'ALTO LIQUIDO MC0 gl ,2*0.00 8.50282,795.00
0.0* ADITIVO ME+ORADOR DE AD/ERENCIA (g 5,5"5.00 28.00155,260.00
0.08 'ILLER CAL /IDRATADA4 (g 21,80.00 1.50320,835.00
0" OBRAS DE ARTE Y DRENAJE
0".01 CUNETAS TRIANGULAR TIPO I
0".01.01 ECAVACION EN MATERIAL SUELTO A MANO ) 1,"1.00 6.2051,802.20 350.00
0".01.02 CONCRETO 7931*5 (g9)2 PARA CUNETAS ) 681.00 "25.8290,031.09 2
0".01.0 CONCRETO 793210 (g9)2 PARA CUNETAS ) 500.00 "5.5226,765.00
0".01.0" ENCO'RADO Y DESENCO'RADO DE CUNETAS REVESTIDA )2 ,660.00 *.1"358,772.40 2
0".01.05 ACERO DE RE'UERZO 7:3",200 (g9)2 (g 12,500.00 5.173,875.00 3
0".01.06 +UNTA AS'ALTICA ) 2,00.00 5.2210,596.60 5
0".02 CUNETAS CUADRADAS TIPO II EN ZONA URBANA
0".02.01 ECAVACION EN MATERIAL SUELTO A MANO ) ,15.00 6.20141,723.00 9
0".02.02 CONCRETO 7931*5 (g9)2 PARA CUNETAS ) 1,60.00 "25.8834,744.40
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
17/42
CRONOGRAMA DE AVANCE FISICO D
PROYECTO:
REGION: PROVINCIA: DIS
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1 MES 2
CANT CANT
0".02.0 CONCRETO 793280 (g9)2 PARA TAPA ) 655.00 5"6.8357,878.90
0".02.0" CONCRETO 793100 (g9)2 PARA SOLADO )2 5,220.00 "0.52211,514.40
0".02.05 ENCO'RADO Y DESENCO'RADO DE CUNETAS REVESTIDA )2 11,*"5.00 *.1" 436,209.30
0".02.06 ACERO DE RE'UERZO 7:3",200 (g9)2 (g *5,000.00 5.1443,250.00 1
0".02.0* +UNTA AS'ALTICA ) ",56*.00 5.2223,839.74
0".0 ALCANTARILLA DE MARCO DE CONCRETO MCA
0".0.01 DEMOLICION DE ESTRUCTURAS EISTENTES ) 6".51 1".29,243.64 64.51
0".0.02 ECAVACION NO CLASI'ICADA PARA ESTRUCTURAS ) 1,15.00 15.* 21,000.55 1,315.00
0".0.0 RELLENO COMPACTADO PARA ESTRUCTURAS ) 1,510.00 ".051,385.30 755.00 755.00
0".0.0" CONCRETO 793210 (g9)2 ) 680.00 "5.5308,400.40 340.00
0".0.05 CONCRETO 793100 (g9)2 PARA SOLADO )2 "2.60 "0.5217,164.27 223.60 200.00
0".0.06 ENCO'RADO Y DESENCO'RADO DE ESTRUCTURAS NORMAL )2 2,*65.00 ".0135,733.85 1,000.00 1,000.00
0".0.0* LIMPIEZA DE CAUCE DE ALCANTARILLAS ) 2,666.00 5.*695,336.16 1,333.00 1,333.00
0".0.08 ACERO DE RE'UERZO 7:3",200 (g9)2 (g 18,000.00 5.1106,380.00 9,000.00 9,000.00
0".0.0 EMBOQUILLADO DE PIEDRA E30.20M )2 610.00 18.1184,247.10
0".0" ALCANTARILLA CON TUBERIA DE ACERO TMC
0".0".01 ECAVACION NO CLASI'ICADA PARA ESTRUCTURAS ) "15.00 15.*6,627.55 115.00
0".0".02 RELLENO COMPACTADO PARA ESTRUCTURAS ) 5.00 ".011,400.05
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
18/42
CRONOGRAMA DE AVANCE FISICO DE
PROYECTO:
REGION: PROVINCIA: DIS
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1 MES 2
CANT CANT
0".0".0 CONCRETO 7931*5 (g9)2 ) 51.00 "25.821,720.39
0".0".0" ENCO'RADO Y DESENCO'RADO DE ESTRUCTURAS NORMAL )2 28.00 ".011,683.42
0".0".05 LIMPIEZA DE CAUCE DE ALCANTARILLAS ) 165.00 5.*6 5,900.40 85.00
0".0".06 ACERO DE RE'UERZO 7:3",200 (g9)2 (g 2,"00.00 5.114,184.00 800.00
0".0".0* ALCANTARILLA METALICA CIRCULAR TMC ;36< )ll 115.00 51.*59,078.95
0".0".08 EMBOQUILLADO DE PIEDRA E30.20M )2 8*.00 18.1112,015.57
0".05 SUB DRENES
0".05.01 ECAVACION DE SUELO PSUB DRENES CEQUIPO ) 110.00 5."" 3,898.40
0".05.02 MATERIAL SELECCIONADO PARA 'ILTRADO ) 1*5.00 *".213,111.00
0".05.0 CAMA DE ARENA E30.10M )2 120.00 1.623,794.40
0".05.0" RELLENO CON MATERIAL ARCILLOSO E30.10M )2 120.00 1.1*1,580.40
0".05.05 MALLA &EOTETIL )2 "50.00 15.5*7,006.50
0".05.06 CONCRETO 7931*5 (g9)2 PARA SUB DRENES ) 5.00 "25.82,129.45
0".05.0* ENCO'RADO Y DESENCO'RADO DE ESTRUCTURAS NORMAL )2 "0.00 ".01,963.60
0".05.08 ACERO DE RE'UERZO 7:3",200 (g9)2 (g 250.00 5.11,477.50
0".05.0 TUBERIA PVC SAP PER'ORADA DE 6< ) 1*0.00 "6.2"7,860.80
0".05.10 TUBO 'IERRO &ALV. DE 2< ) 12.00 "8.00576.00
0".06 VEREDAS
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
19/42
CRONOGRAMA DE AVANCE FISICO DE
PROYECTO:
REGION: PROVINCIA: DIS
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1 MES 2
CANT CANT
0".06.01 OBRAS PRELIMINARES
0".06.01.01 TRAZO Y REPLANTEO )2 ,200.00 2.09,280.00
0".06.02 MOVIMIENTO DE TIERRAS
0".06.02.01 CORTE DE TERRENO MANUAL PARA VEREDAS )2 ,200.00 6.20,256.00
0".06.02.02 NIVELACION Y COMPACTACION DE TERRENO )2 ,200.00 .510,720.00
0".06.02.0 A'IRMADO PARA VEREDAS E3 6
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
20/42
CRONOGRAMA DE AVANCE FISICO D
PROYECTO:
REGION: PROVINCIA: DIS
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1 MES 2
CANT CANT
0".0*.0 OBRAS DE CONCRETO SIMPLE
0".0*.0.01 CONCRETO 793210 (g9)2 ) 20.00 "50.29,006.40
0".0*.0" ARQUITECTURA
0".0*.0".01 ESTRUCTURA DE PARADERO URBANO glb 28.00 ",800.00134,400.00
0".0*.0".02 ESTRUCTURA DE PARADERO RURAL glb 28.00 ,800.00106,400.00
0".0*.0".0 INSTALACION DE PARADERO URBANO glb 28.00 1,500.0042,000.00
0".0*.0".0" INSTALACION DE PARADERO RURAL glb 28.00 50.0026,600.00
05 TRANSPORTE PAGADO
05.01 TRANSPORTE DE MEZCLA AS'ALTICA PARA D=3 1 >M )( ,80.00 10.240,954.20
05.02 TRANSPORTE DE MEZCLA AS'ALTICA PARA D? 1 >M )( 20,60.00 .5572,278.00
05.0 TRANSPORTE DE MATERIAL &RANULAR PARA D = 3 1 >M )( 2,0*5.00 10.2*329,410.25 16,075.00 16,000.00
05.0" TRANSPORTE DE MATERIAL &RANULAR PARA D ? 1 >M )( 101,05.00 5.56561,754.60 36,035.00 35,000.00
05.05 TRANSPORTE DE MATERIAL PROVENIENTE DE CANTERA PARA D = 3 1 >M )( "5,000.00 .5"429,300.00 45,000.00
05.06 TRANSPORTE DE MATERIAL PROVENIENTE DE CANTERA PARA D ? 1 >M )( 10*,*1.00 ".1"446,254.74 32,791.00
05.0* ELIMINACION DE MATERIAL PROVENIENTE DE DERRUMBES PARA D = 3 1 >M )( 1,200.00 1.0*15,684.00
05.08 ELIMINACION DE MATERIAL PROVENIENTE DE DERRUMBES PARA D ? 1 >M )( 6,000.00 5."35,640.00
06 SEALIZACION Y SEGURIDAD VIAL
06.01 SE@ALIZACION Y SE&URIDAD VIAL glb 1.00 102,602.10102,602.10 1.00
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
21/42
Pg.: 21
CRONOGRAMA DE AVANCE FISICO DE OBRA
PROYECTO:
REGION: PROVINCIA: DISTRITO:
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1 MES 2 MES 3
CANT CANT CANT
0* PROTECCION AMBIENTAL
0*.01 ACONDICIONAMIENTO DE ECEDENTES EN ZONAS DE BOTADEROS ) 500.00 .561,780.00 100.00 100.00
0*.02 RECUPERACION AMB DE AREAS A'ECTADAS LIMP Y RESTAURAC DCANTERAS )2 10,500.00 1.6116,905.00
P 22
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
22/42
Pg.: 22
N METRADOS
MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12
CANT CANT CANT CANT CANT CANT CANT CANT CANT
1.00 1.00 1.00 1.00 1.00 1.00 1.00
1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.28
1.00 1.00
1.00
0.50
0.50
1,060.00
3,140.00 3,140.00 3,000.00
4,000.00 4,000.00 4,000.00 4,000.00 4,000.00 1,665.00
8,000.00 8,000.00 8,000.00 8,000.00 8,000.00 8,000.00 8,000.00 8,000.00 5,000.00
9,000.00 9,000.00 9,000.00 9,000.00 9,000.00 9,000.00 9,000.00
P 23
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
23/42
Pg.: 23
N METRADOS
MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12
CANT CANT CANT CANT CANT CANT CANT CANT CANT
9,000.00 9,000.00 9,000.00 9,000.00 9,000.00 9,000.00 9,000.00 9,000.00
9,597.00 9,000.00 9,000.00 9,000.00 9,000.00 9,000.00 9,000.00 9,000.00 9,000.00
1,000.00 1,545.00 1,000.00 1,000.00 1,000.00
34,050.00 34,050.00 34,050.00 34,050.00 34,050.00
6,654.00 6,654.00 6,654.00 6,654.00 6,654.00
1,000.00 1,545.00 1,000.00 1,000.00 1,000.00
42,778.00 42,778.00 42,778.00 42,778.00 42,778.00
350.00 350.00
200.00 200.00 81.00
125.00 125.00 125.00
2,415.00 2,415.00 2,415.00
3,125.00 3,125.00 3,125.00
500.00 500.00 500.00
975.00 975.00 975.00
490.00 490.00 490.00 490.00
Pg : 24
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
24/42
Pg.: 24
N METRADOS
MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12
CANT CANT CANT CANT CANT CANT CANT CANT CANT
172.00 161.00 161.00 161.00
1,305.00 1,305.00 1,305.00 1,305.00
2,349.00 2,349.00 2,349.00 2,349.00
15,000.00 15,000.00 15,000.00 15,000.00
1,147.00 1,140.00 1,140.00 1,140.00
100.00 100.00
100.00 100.00
Pg.: 25
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
25/42
g
N METRADOS
MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12
CANT CANT CANT CANT CANT CANT CANT CANT CANT
26.00 25.00
70.00 70.00
800.00
60.00 55.00
47.00 40.00
35.00 25.00 25.00 25.00
57.00 57.00 61.00
60.00 60.00
60.00 60.00
150.00 150.00 150.00
5.00
20.00 20.00
125.00 125.00
85.00 85.00
12.00
Pg.: 26
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
26/42
g
N METRADOS
MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12
CANT CANT CANT CANT CANT CANT CANT CANT CANT
1,200.00 1,000.00 1,000.00
1,200.00 1,000.00 1,000.00
1,200.00 1,000.00 1,000.00
1,200.00 1,000.00 1,000.00
1,200.00 1,000.00 1,000.00
20.00
60.00 50.00 50.00
400.00 400.00 400.00
80.00 80.00
90.00 80.00 80.00
50.00 50.00
125.00 125.00
Pg.: 27
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
27/42
N METRADOS
MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12
CANT CANT CANT CANT CANT CANT CANT CANT CANT
10.00 10.00
14.00 14.00
14.00 14.00
14.00 14.00
14.00 14.00
1,980.00 1,000.00 1,000.00
5,360.00 5,000.00 5,000.00 5,000.00
25,000.00 25,000.00
600.00 600.00
2,000.00 2,000.00 2,000.00
Pg.: 28
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
28/42
N METRADOS
MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12CANT CANT CANT CANT CANT CANT CANT CANT CANT
100.00 100.00 100.00
2,000.00 2,000.00 2,000.00 2,000.00 2,000.00 500.00
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
29/42
CRONOGRAMA VALORIZAD
PROYECTO
REGION: PROVINCIA:
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1
S/.
01 OBRAS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZ. DE MAQUINARIAS Y EQUIPOS glb 1.00 56,080.0056,080.00 16,824.00
01.02 CARTEL DE OBRA .60!5."0 #$% .00 2,100.""6,301.32 2,100.44
01.0 TOPO&RA'IA Y &EORE'ERENCIACION () 10.1" 1,16.*1 11,526.24 1,136.71
01.0" TOPO&RA'IA Y &EORE'ERENCIACION DURANTE EL PROCESO DE E+ECUCION () 10.1" **1.*57,825.55 771.75
01.05 CAMPAMENTO TRANSPORTABLE PARA OBRA glb 1.00 1",000.0014,000.00 10,080.00
01.06 MANTENIMIENTO DE TRANSITO TEMPORAL Y SE&URIDAD VIAL )- .00 "0,*68.6122,306.88 40,768.96
01.0* ACCESO A CANTERAS, BOTADEROS, PLANTAS DE PROCESO Y 'UENTES DE A&UA () .50 ",*50."16,626.19 4,750.34
01.08 MONTA+E Y DESMONTA+E DE PLANTA DE AS'ALTO glb 1.00 121,0**.61121,077.61
01.0 MONTA+E Y DESMONTA+E DE PLANTA C/ANCADORA glb 1.00 58,0*.8658,079.86 29,039.93
02 EXPLANACIONES
02.01 ECAVACION EN MATERIAL SUELTO ) 6,00.00 10.5266,276.00 22,092.00
02.02 ECAVACION EN ROCA SUELTA ) ,10.00 16.2851,933.20
02.0 ECAVACION EN ROCA 'I+A ) 12,280.00 2.8*366,803.60
02.0" RELLENO CON MATERIAL PROPIO ) 21,665.00 8.""182,852.60
02.05 CON'ORMACION DE TERRAPLEN CON MATERIAL DE CANTERA ) 85,000.00 28.882,454,800.00
0 CARPETA ASFALTICA
0.01 SUBBASE &RANULAR E320 CM4 )2 0,5*.00 15.08
1,366,202.76 135,720.00
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
30/42
CRONOGRAMA VALORIZAD
PROYECTO
REGION: PROVINCIA:
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1
S/.
0.02 BASE &RANULAR E320 CM4 )2 0,5*.00 16.8*1,528,371.39
0.0 IMPRIMACION AS'ALTICA )2 0,5*.00 1.65149,485.05
0.0" CARPETA AS'ALTICA EN CALIENTE ) 5,5"5.00 21.81,619,029.10
0.05 CEMENTO AS'ALTICO PEN 85100 gl 1*0,250.00 *.00 1,191,750.00
0.06 AS'ALTO LIQUIDO MC0 gl ,2*0.00 8.50282,795.00
0.0* ADITIVO ME+ORADOR DE AD/ERENCIA (g 5,5"5.00 28.00155,260.00
0.08 'ILLER CAL /IDRATADA4 (g 21,80.00 1.50320,835.00
0" OBRAS DE ARTE Y DRENAJE
0".01 CUNETAS TRIANGULAR TIPO I
0".01.01 ECAVACION EN MATERIAL SUELTO A MANO ) 1,"1.00 6.2051,802.20
0".01.02 CONCRETO 7931*5 (g9)2 PARA CUNETAS ) 681.00 "25.8290,031.09
0".01.0 CONCRETO 793210 (g9)2 PARA CUNETAS ) 500.00 "5.5226,765.00
0".01.0" ENCO'RADO Y DESENCO'RADO DE CUNETAS REVESTIDA )2 ,660.00 *.1"358,772.40
0".01.05 ACERO DE RE'UERZO 7:3",200 (g9)2 (g 12,500.00 5.173,875.00
0".01.06 +UNTA AS'ALTICA ) 2,00.00 5.2210,596.60
0".02 CUNETAS CUADRADAS TIPO II EN ZONA URBANA
0".02.01 ECAVACION EN MATERIAL SUELTO A MANO ) ,15.00 6.20141,723.00
0".02.02 CONCRETO 7931*5 (g9)2 PARA CUNETAS ) 1,60.00 "25.8
834,744.40
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
31/42
CRONOGRAMA VALORIZA
PROYECT
REGION: PROVINCIA:
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1
S/.
0".02.0 CONCRETO 793280 (g9)2 PARA TAPA ) 655.00 5"6.8357,878.90
0".02.0" CONCRETO 793100 (g9)2 PARA SOLADO )2 5,220.00 "0.52211,514.40
0".02.05 ENCO'RADO Y DESENCO'RADO DE CUNETAS REVESTIDA )2 11,*"5.00 *.1"436,209.30
0".02.06 ACERO DE RE'UERZO 7:3",200 (g9)2 (g *5,000.00 5.1 443,250.00
0".02.0* +UNTA AS'ALTICA ) ",56*.00 5.2223,839.74
0".0 ALCANTARILLA DE MARCO DE CONCRETO MCA
0".0.01 DEMOLICION DE ESTRUCTURAS EISTENTES ) 6".51 1".29,243.64 9,243.64
0".0.02 ECAVACION NO CLASI'ICADA PARA ESTRUCTURAS ) 1,15.00 15.*21,000.55 21,000.55
0".0.0 RELLENO COMPACTADO PARA ESTRUCTURAS ) 1,510.00 ".051,385.30 25,692.65
0".0.0" CONCRETO 793210 (g9)2 ) 680.00 "5.5308,400.40
0".0.05 CONCRETO 793100 (g9)2 PARA SOLADO )2 "2.60 "0.5217,164.27 9,060.27
0".0.06 ENCO'RADO Y DESENCO'RADO DE ESTRUCTURAS NORMAL )2 2,*65.00 ".0135,733.85 49,090.00
0".0.0* LIMPIEZA DE CAUCE DE ALCANTARILLAS ) 2,666.00 5.*695,336.16 47,668.08
0".0.08 ACERO DE RE'UERZO 7:3",200 (g9)2 (g 18,000.00 5.1106,380.00 53,190.00
0".0.0 EMBOQUILLADO DE PIEDRA E30.20M )2 610.00 18.1184,247.10
0".0" ALCANTARILLA CON TUBERIA DE ACERO TMC
0".0".01 ECAVACION NO CLASI'ICADA PARA ESTRUCTURAS ) "15.00 15.*6,627.55
0".0".02 RELLENO COMPACTADO PARA ESTRUCTURAS ) 5.00 ".0
11,400.05
CRONOGRAMA VALORIZAD
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
32/42
CRONOGRAMA VALORIZAD
PROYECT
REGION: PROVINCIA:
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1
S/.
0".0".0 CONCRETO 7931*5 (g9)2 ) 51.00 "25.821,720.39
0".0".0" ENCO'RADO Y DESENCO'RADO DE ESTRUCTURAS NORMAL )2 28.00 ".011,683.42
0".0".05 LIMPIEZA DE CAUCE DE ALCANTARILLAS ) 165.00 5.*65,900.40
0".0".06 ACERO DE RE'UERZO 7:3",200 (g9)2 (g 2,"00.00 5.1 14,184.00
0".0".0* ALCANTARILLA METALICA CIRCULAR TMC ;36< )ll 115.00 51.*59,078.95
0".0".08 EMBOQUILLADO DE PIEDRA E30.20M )2 8*.00 18.1112,015.57
0".05 SUB DRENES
0".05.01 ECAVACION DE SUELO PSUB DRENES CEQUIPO ) 110.00 5.""3,898.40
0".05.02 MATERIAL SELECCIONADO PARA 'ILTRADO ) 1*5.00 *".213,111.00
0".05.0 CAMA DE ARENA E30.10M )2 120.00 1.623,794.40
0".05.0" RELLENO CON MATERIAL ARCILLOSO E30.10M )2 120.00 1.1*1,580.40
0".05.05 MALLA &EOTETIL )2 "50.00 15.5*7,006.50
0".05.06 CONCRETO 7931*5 (g9)2 PARA SUB DRENES ) 5.00 "25.82,129.45
0".05.0* ENCO'RADO Y DESENCO'RADO DE ESTRUCTURAS NORMAL )2 "0.00 ".01,963.60
0".05.08 ACERO DE RE'UERZO 7:3",200 (g9)2 (g 250.00 5.11,477.50
0".05.0 TUBERIA PVC SAP PER'ORADA DE 6< ) 1*0.00 "6.2"7,860.80
0".05.10 TUBO 'IERRO &ALV. DE 2< ) 12.00 "8.00576.00
0".06 VEREDAS
CRONOGRAMA VALORIZAD
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
33/42
CRONOGRAMA VALORIZAD
PROYECT
REGION: PROVINCIA:
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1
S/.
0".06.01 OBRAS PRELIMINARES
0".06.01.01 TRAZO Y REPLANTEO )2 ,200.00 2.09,280.00
0".06.02 MOVIMIENTO DE TIERRAS
0".06.02.01 CORTE DE TERRENO MANUAL PARA VEREDAS )2 ,200.00 6. 20,256.00
0".06.02.02 NIVELACION Y COMPACTACION DE TERRENO )2 ,200.00 .510,720.00
0".06.02.0 A'IRMADO PARA VEREDAS E3 6
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
34/42
CRONOGRAMA VALORIZA
PROYECT
REGION: PROVINCIA:
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1
S/.
0".0*.0 OBRAS DE CONCRETO SIMPLE
0".0*.0.01 CONCRETO 793210 (g9)2 ) 20.00 "50.29,006.40
0".0*.0" ARQUITECTURA
0".0*.0".01 ESTRUCTURA DE PARADERO URBANO glb 28.00 ",800.00 134,400.00
0".0*.0".02 ESTRUCTURA DE PARADERO RURAL glb 28.00 ,800.00106,400.00
0".0*.0".0 INSTALACION DE PARADERO URBANO glb 28.00 1,500.0042,000.00
0".0*.0".0" INSTALACION DE PARADERO RURAL glb 28.00 50.0026,600.00
05 TRANSPORTE PAGADO
05.01 TRANSPORTE DE MEZCLA AS'ALTICA PARA D=3 1 >M )( ,80.00 10.240,954.20
05.02 TRANSPORTE DE MEZCLA AS'ALTICA PARA D? 1 >M )( 20,60.00 .5572,278.00
05.0 TRANSPORTE DE MATERIAL &RANULAR PARA D = 3 1 >M )( 2,0*5.00 10.2*329,410.25 165,090.25
05.0" TRANSPORTE DE MATERIAL &RANULAR PARA D ? 1 >M )( 101,05.00 5.56561,754.60 200,354.60
05.05 TRANSPORTE DE MATERIAL PROVENIENTE DE CANTERA PARA D = 3 1 >M )( "5,000.00 .5"429,300.00 429,300.00
05.06 TRANSPORTE DE MATERIAL PROVENIENTE DE CANTERA PARA D ? 1 >M )( 10*,*1.00 ".1"446,254.74
05.0* ELIMINACION DE MATERIAL PROVENIENTE DE DERRUMBES PARA D = 3 1 >M )( 1,200.00 1.0*15,684.00
05.08 ELIMINACION DE MATERIAL PROVENIENTE DE DERRUMBES PARA D ? 1 >M )( 6,000.00 5."35,640.00
06 SEALIZACION Y SEGURIDAD VIAL
06.01 SE@ALIZACION Y SE&URIDAD VIAL glb 1.00 102,602.10102,602.10 102,602.10
CRONOGRAMA VALORIZADO DE AVAN
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
35/42
C O OG O O
PROYECTO:
REGION: PROVINCIA:
TEM DESCRIPCIN PARTIDA UNIDAD METRADO P. UNIT. PARCIAL MES 1 MES 2S/. S/.
0* PROTECCION AMBIENTAL
0*.01 ACONDICIONAMIENTO DE ECEDENTES EN ZONAS DE BOTADEROS ) 500.00 .561,780.00 356.00
0*.02 RECUPERACION AMB DE AREAS A'ECTADAS LIMP Y RESTAURAC DCANTERAS )2 10,500.00 1.6116,905.00
COSTO DIRECTO 17,438,655.12 1,375,576.27 1,525,285.48
GASTOS GENERALES 1,743,865.51 137,557.63 152,528.55
UTILIDAD (10%) 1,743,865.51 137,557.63 152,528.55
SUB TOTAL 20,926,386.14 1,650,691.53 1,830,342.58
IGV (1%) 3,766,749.51 297,124.48 329,461.66
TOTAL 24,693,135.65 1,947,816.01 2,159,804.24
CE FISICO DE OBRA
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
36/42
DISTRITO: Hoja N :
MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12
S/. S/. S/. S/. S/. S/. S/. S/. S/. S/.
2,100.44
1,136.71 1,136.71 1,136.71 1,136.71 1,136.71 1,136.71 1,136.71 1,136.71
771.75 771.75 771.75 771.75 771.75 771.75 771.75 771.75
3,920.00
40,768.96 40,768.96
7,125.51 4,750.34
60,538.80
29,039.93
22,092.00
18,396.40 17,256.80
89,610.00 93,791.80 93,791.80 89,610.00
33,760.00 33,760.00 33,760.00 33,760.00 33,760.00 14,052.60
231,040.00 231,040.00 231,040.00 231,040.00 231,040.00 231,040.00 231,040.00 231,040.00 231,040.00 144,400.00
135,720.00 135,720.00 135,720.00 135,720.00 135,720.00 135,720.00 135,720.00 135,720.00
CE FISICO DE OBRA
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
37/42
DISTRITO: Hoja N :
MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12S/. S/. S/. S/. S/. S/. S/. S/. S/. S/.
161,901.39 151,830.00 151,830.00 151,830.00 151,830.00 151,830.00 151,830.00 151,830.00 151,830.00
14,850.00 15,835.05 14,850.00 14,850.00 14,850.00 14,850.00 14,850.00 14,850.00 14,850.00 14,850.00
291,980.00 451,109.10 291,980.00 291,980.00 291,980.00
238,350.00 238,350.00 238,350.00 238,350.00 238,350.00
56,559.00 56,559.00 56,559.00 56,559.00 56,559.00
28,000.00 43,260.00 28,000.00 28,000.00 28,000.00
64,167.00 64,167.00 64,167.00 64,167.00 64,167.00
13,792.20 12,670.00 12,670.00 0.00
85,178.00 85,178.00 85,178.00 34,497.09
56,691.25 56,691.25 56,691.25 56,691.25
89,693.10 89,693.10 89,693.10 89,693.10
18,468.75 18,468.75 18,468.75 18,468.75
2,766.60 2,610.00 2,610.00 2,610.00
35,838.00 35,295.00 35,295.00 35,295.00
208,686.10 208,686.10 208,686.10 208,686.10
CE FISICO DE OBRA
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
38/42
DISTRITO: Hoja N :
MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12
S/. S/. S/. S/. S/. S/. S/. S/. S/. S/.
93,977.36 87,967.18 87,967.18 87,967.18
52,878.60 52,878.60 52,878.60 52,878.60
87,241.86 87,241.86 87,241.86 87,241.86 87,241.86
88,650.00 88,650.00 88,650.00 88,650.00 88,650.00
5,987.34 5,950.80 5,950.80 5,950.80
154,200.20
37,553.85
84,247.10
1,597.00 1,597.00 1,597.00
4,594.05 3,403.00 3,403.00
CE FISICO DE OBRA
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
39/42
DISTRITO: Hoja N :
MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12
S/. S/. S/. S/. S/. S/. S/. S/. S/. S/.
11,073.14 10,647.25
4,810.82 3,436.30 3,436.30
2,860.80
4,728.00 4,728.00
30,823.80 28,255.15
6,491.17 5,524.40
1,240.40 886.00 886.00 886.00
4,270.44 4,270.44 4,570.12
1,897.20 1,897.20
790.20 790.20 0.00
2,335.50 2,335.50 2,335.50
2,129.45
981.80 981.80
738.75 738.75
3,930.40 3,930.40
576.00
CE FISICO DE OBRA
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
40/42
DISTRITO: Hoja N :
MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12
S/. S/. S/. S/. S/. S/. S/. S/. S/. S/.
3,480.00 2,900.00 2,900.00
7,596.00 6,330.00 6,330.00
4,020.00 3,350.00 3,350.00
23,700.00 19,750.00 19,750.00
70,512.00 58,760.00 58,760.00
0.00 0.00 9,006.40
27,019.20 22,516.00 22,516.00
19,636.00 19,636.00 19,636.00
417.60 417.60
261.00 232.00 232.00
2,369.00 2,369.00
1,907.50 1,907.50
CE FISICO DE OBRA
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
41/42
DISTRITO: Hoja N :
MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12
S/. S/. S/. S/. S/. S/. S/. S/. S/. S/.
4,503.20 4,503.20
67,200.00 67,200.00
53,200.00 53,200.00
21,000.00 21,000.00
13,300.00 13,300.00
20,374.20 10,290.00 10,290.00
19,028.00 17,750.00 17,750.00 17,750.00
166,800.00
103,500.00 103,500.00 103,500.00
7,842.00 7,842.00
11,880.00 11,880.00 11,880.00
CE FISICO DE OBRA
-
7/25/2019 CRONOGRAMA PROYECTO DIVERSOS
42/42
DISTRITO: Hoja N :
MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12S/. S/. S/. S/. S/. S/. S/. S/. S/. S/.
356.00 356.00 356.00 356.00
3,220.00 3,220.00 3,220.00 3,220.00 3,220.00 805.00
1,728,311.78 1,664,048.71 1,767,431.31 1,491,108.33 1,152,196.27 1,334,567.66 1,612,884.69 1,489,140.26 1,275,424.56 1,022,679.80
172,831.18 166,404.87 176,743.13 149,110.83 115,219.63 133,456.77 161,288.47 148,914.03 127,542.46 102,267.98172,831.18 166,404.87 176,743.13 149,110.83 115,219.63 133,456.77 161,288.47 148,914.03 127,542.46 102,267.98
2,073,974.14 1,996,858.45 2,120,917.57 1,789,329.99 1,382,635.53 1,601,481.20 1,935,461.63 1,786,968.32 1,530,509.48 1,227,215.76
373,315.35 359,434.52 381,765.16 322,079.40 248,874.40 288,266.62 348,383.09 321,654.30 275,491.71 220,898.84
2,447,289.49 2,356,292.97 2,502,682.73 2,111,409.39 1,631,509.93 1,889,747.82 2,283,844.72 2,108,622.62 1,806,001.19 1,448,114.60