Villegas Mines 0052E 10549

download Villegas Mines 0052E 10549

of 186

Transcript of Villegas Mines 0052E 10549

  • 8/17/2019 Villegas Mines 0052E 10549

    1/186

     

    GEOMECHANICAL EVALUATION OF A MECHANICAL UNDERCUTTING SYSTEM IN

    BLOCK CAVING

     by

    Fernando Villegas

  • 8/17/2019 Villegas Mines 0052E 10549

    2/186

     

    ii

    A thesis submitted to the Faculty and the Board of Trustees of the Colorado School of

    Mines in partial fulfillment of the requirements for the degree of Doctor of Philosophy (Mining

    and Earth Systems Engineering).

    Golden, Colorado

    Date: ______________________

    Signed: ______________________________Fernando Villegas

    Signed: ______________________________Dr. Mark Kuchta

    Thesis Advisor

    Golden, Colorado

    Date: ________________________

    Signed: ______________________________Dr. Pricilla P. Nelson

    Professor and HeadDepartment of Mining Engineering

  • 8/17/2019 Villegas Mines 0052E 10549

    3/186

     

    iii

    ABSTRACT

     Nowadays, Block Caving is the underground mining method with the highest productivity in

    the world. Many of the components of block caving have changed in the last few years, as new

    techniques and equipment have become available, increasing the efficiency of the method. Such

    components include automatic LHD (load, haul and dump) trucks and trains, electronic

    detonators and mechanical equipment for the development of drifts and shafts.

     Nevertheless, the first link of the chain of value in Block Caving is the undercutting process,

    which continues, in essence, being performed in the same way it was when the method was

    invented, utilizing drill and blast. This thesis proposes to use a mechanical system to perform the

    undercutting, similar to the longwall method used in coal mines. In order to evaluate the

    technical feasibility of this option, a geomechanical evaluation about the feasibility of theimplementation of this alternative system in block caving was developed.

    Starting with the geomechanical study, the first step was exploring the possible

    geomechanical hazards that could arise if this alternative method is implemented in block caving,

    taking into consideration that the undercutting work should be performed from inside of caving

    volume. An undercutting mine design was proposed and interest zones were defined, also a risk

    analysis was carried out. The result of the risk analysis was the identification of three possible

    hazards, losses of confinement in the cutting front, wedges in the roof of the work area, and

    collapse of the pillar between panels.

    In order to assess the geomechanical hazards, numerical models and kinematic analyses were

    conducted. For these, numerical models were built in FLAC3D  to study the geomechanical

     behavior of the cutting front, work area, and the pillar between panels. The models further

    studied the relation between each of these elements and the undercutting advance and caving

     propagation. A mine design and sequence has been proposed for these analyses. The mine design

    was made based on the macro block method and the sequence of undercutting advance was made

     based on the longwall method.

    The undercutting front advance was modeled in two stages, pre-caving and continuous

    caving, in order to take into consideration the undercut advance and the caving progress. The

    results of the analyses showed that the stress quickly raised with the increase of the undercut area

    until it reached the hydraulic radius of caving. In order to estimate the initiation and depth of

  • 8/17/2019 Villegas Mines 0052E 10549

    4/186

     

    iv

    fracturing in the cutting front and to evaluate the risk of losses of confinement in the center of the

    cutting front, two methodologies were used: UCSlab and critical strain εc. These methodologies

    showed that on the cutting front fracturing started when the undercut area reached 20 to 30% of

    the panel area. Thus, the conditions where the equipment will work change constantly with the

    advance of the undercutting front. Therefore, the machine should cut and remove the rock in the

    cutting front. In addition, three different cutting front widths were analyzed: 120, 150, and 180

    meters. For this range of widths, the difference in stress behavior is low. On the other hand,

    estimates of vertical displacements in the work area increase with the advance of the

    undercutting front, but near the cutting front the vertical displacements will be low; therefore,

    stability in the work area could probably be controlled structurally by wedges formed in the roof.

     Numerical models show that during continuous caving, the length of the beam does not have

    greater influence on variations in the stress condition. Regarding the pillar between panels, it

    should accomplish the function of giving continuity to the method and helping it to provide

    stability of the work area. The pillar design is robust, with a width-to-height ratio of five;

    therefore, it has a high strength. The numerical models confirm this approach by showing that

    although there is damage in the sides of the pillar, the damage never reaches the center of the

     pillar.

    Estimation of the possible undercutting advance rate using a mechanical undercutting system

    in block caving shows that it is similar to or higher than the traditional drill and blast rate.The research developed in this thesis presents an opportunity to improve the quality of

    undercutting, ensuring the cut of the block and eliminating the risk of a remnant pillar that would

    affect the production level. In addition, it delivers the option of a possible increase in the

     performance of the undercutting, and an exploration of a possible automation of the process, both

    of which would contribute to the modernization of block caving exploitation. The main

    conclusion of this work is that from a geomechanical point of view, it is feasible to use a

    mechanical undercutting system in block caving.

  • 8/17/2019 Villegas Mines 0052E 10549

    5/186

     

    v

    TABLE OF CONTENTS

    ABSTRACT ........................................................................................................................ iii 

    LIST OF FIGURES ..................................................................................................................... ix 

    LIST OF TABLES .......................................................................................................................xv 

    ACKNOWLEDGEMENTS ...................................................................................................... xvi 

    INTRODUCTION ..........................................................................................1 CHAPTER 1

    1.1 

    Background ......................................................................................................1 

    1.2  Justification for the research conducted ...........................................................2 

    1.3 

    Objective of the research undertaken ...............................................................2 

    1.4  Research conducted and methodology .............................................................3 

    1.5  Scope of the research ........................................................................................4 

    1.6 

    Original contribution ........................................................................................4 

    1.7  Thesis organization ...........................................................................................5 

    LITERATURE REVIEW ..............................................................................7 CHAPTER 2

    2.1  Block caving method ........................................................................................7 

    2.1.1  Conceptual model of caving .........................................................7 

    2.2  Undercut methods .............................................................................................9 

    2.2.1  Post undercut .................................................................................9 

    2.2.2  Pre undercut ................................................................................10 

    2.2.3 

    Advance undercut .......................................................................11 

    2.2.4 

    “Crinkle cut” layout and blasting design in advanceundercutting ................................................................................12

    2.2.5  Cavability ....................................................................................13 

  • 8/17/2019 Villegas Mines 0052E 10549

    6/186

     

    vi

    2.2.6  Undercutting rate ........................................................................14 

    2.2.7  Geometry of undercutting front ..................................................15 

    2.2.8  Undercutting method in high stress ............................................16 

    2.2.9 

    Generation of dynamic stress ......................................................18 

    2.2.10  Seismicity associated to undercutting process ............................20 

    2.2.11   Numerical models of undercutting in block caving ....................20 

    2.3  Longwall mining method ...............................................................................21 

    2.3.1  Mine design .................................................................................22 

    2.3.2 

    Production system .......................................................................23 

    2.3.3   Numerical model of longwall .....................................................25 

    2.4 

    Chuquicamata underground project ...............................................................27 

    2.4.1  Chuquicamata mine ....................................................................27 

    2.4.2  Geology .......................................................................................29 

    2.4.3  Mining method ............................................................................30 

    UNDERCUTTING WITH A MECHANICAL SYSTEM ........................33 

    CHAPTER 3

    3.1 

    Block caving mine designs with mechanical undercutting ............................33 

    3.1.1  Undercutting mine design ...........................................................34 

    3.1.2 

    Relation between undercut design and production leveldesign ..........................................................................................38

    3.2 

    Undercutting sequence ...................................................................................38 

    3.3  Performance of mechanical undercutting system. ..........................................39  

    3.3.1  Productivity in advance undercut with drilling and blasting ........................................................................................39

    3.3.2 

    Advance undercut with a mechanical undercutting system ........40 

  • 8/17/2019 Villegas Mines 0052E 10549

    7/186

     

    vii

    3.4  Possible differences between the use of a mechanical undercuttingsystem in block caving and longwall ............................................................44

    GEOMECHANICAL HAZARDS IN THE USE OF A MECHANICALCHAPTER 4

    UNDERCUTTING SYSTEM ......................................................................45

    4.1  Methodology used for risk analysis ................................................................45 

    4.2 

    Description of hazard .....................................................................................46 

    4.2.1  Cutting front ................................................................................46 

    4.2.2 

    Work area ....................................................................................48 

    4.2.3  Drifts access to panel ..................................................................50 

    4.2.4 

    Pillars of separation between panels ...........................................51 

    4.2.5  Caving volume ............................................................................52 

    4.3  Evaluation of risks ..........................................................................................58 

    NUMERICAL MODELS .............................................................................61 CHAPTER 5

    5.1  Framework of numerical models ....................................................................61 

    5.1.1 

     Numerical models objectives ......................................................61 

    5.1.2   Numerical model software ..........................................................62 

    5.1.3  Caving condition .........................................................................62 

    5.2  Modeling with FLAC3D ..................................................................................63 

    5.3  Modeling construction ....................................................................................66 

    5.3.1   Numerical model geometry .........................................................67 

    5.3.2 

    Boundary conditions ...................................................................72 

    5.3.3 

    Stress condition ...........................................................................72 

    5.3.4  Constitutive model ......................................................................74 

    5.3.5  Rock mass properties ..................................................................74 

  • 8/17/2019 Villegas Mines 0052E 10549

    8/186

     

    viii

    5.3.6  Meshing and element size ...........................................................76 

    5.4  Excavation sequence ......................................................................................77 

    5.4.1  One Panel ....................................................................................77 

    5.4.2 

    Two Panels ..................................................................................79 

    5.5  Criteria to estimate the initiation and depth of fracturing in the cuttingfront ...............................................................................................................82

    5.5.1 

    Estimation of initiation and depth of fracturing in thecutting front based on the uniaxial compression strengthof intact rock (UCSlab) ................................................................82

    5.5.2 

    Estimation of depth fracturing in base of critical strain ..............84 

    GEOMECHANICAL ANALYSES.............................................................86  CHAPTER 6

    6.1 

    Framework of geomechanical analyses ..........................................................86 

    6.2  Geomechanical behavior of cutting front and work areas during pre-caving ............................................................................................................86

    6.3 

    Geomechanical behavior of cutting front and work areas incontinuous caving .........................................................................................91

    6.4  Effect of the width of the panel in the cutting front .......................................94 

    6.5  Stability of the pillar between panels .............................................................95 

    6.6  Kinematic analyses of the work area ............................................................101 

    6.7   Numerical model validation .........................................................................106 

    CONCLUSION AND FUTURE WORK  ..................................................110 CHAPTER 7

    7.1 

    Conclusions ..................................................................................................110 

    7.2 

    Future work ..................................................................................................112 

    REFERENCES CITED .............................................................................................................113 

    APPENDIX A  CODES FLAC3D OF NUMERICAL MODELS ......................................121 

  • 8/17/2019 Villegas Mines 0052E 10549

    9/186

     

    ix

    LIST OF FIGURES

    Figure 2.1 Typical scheme of block caving with LHD (Arce, 2002) ..............................................7

    Figure 2.2 Conceptual model of caving (Brown, 2007) ..................................................................8

    Figure 2.3 Post-undercut (Brown, 2007) .......................................................................................10

    Figure 2.4 Pre-undercut (Brown, 2007) .........................................................................................11

    Figure 2.5 Advanced undercut (Brannon, 2011) ...........................................................................12

    Figure 2.6 Illustration of crinkle cut in Palabora mine (Brown, 2007)..........................................14

    Figure 2.7 Crinkle cut undercut potential problem areas (Butcher, 2000) ....................................14

    Figure 2.8 Relative frequency of different undercut rates in caving mines (Flores, 2002) ...........15

    Figure 2.9 Confinement and traction in the undercutting front (modified from Laubscher,2000) ............................................................................................................................16

    Figure 2.10 Geometries of the undercutting front (Butcher, 1999) ...............................................16

    Figure 2.11 Variation of in-situ stress with depth (Karzulovic, 2004) ..........................................17

    Figure 2.12 Stress conditions in the roof of production drift by effect of the undercuttingfront advance (Trueman, 2002) ................................................................................17

    Figure 2.13 Example of advanced undercutting front with small pillars (Workshop

    undercutting, 2008) ...................................................................................................18

  • 8/17/2019 Villegas Mines 0052E 10549

    10/186

     

    x

    Figure 2.14 Remnant pillar in undercut level (Karzulovic, 2005) .................................................19

    Figure 2.15 Damage caused by collapse in production level (Karzulovic, 2003) .........................19

    Figure 2.16 Cumulative undercut area blasted (green dots) compared to the cumulativenumber of significant events (red line) showing a very strong correlation(Potvin, 2010) ...........................................................................................................20

    Figure 2.17 Classic schematic of longwall, in a coal mine (Energy InformationAdministration, 1994) ...............................................................................................22

    Figure 2.18 A typical longwall coal mine layout showing the panels, entries, and chain pillars, (Source: Ch13.8, SME Handbook, 2011). ....................................................24

    Figure 2.19 Overview of longwall system, main equipment (University of Wollongongwebsite, 2014) ...........................................................................................................25

    Figure 2.20 Three dimensional model (Wei, 2011) .......................................................................26

    Figure 2.21 Chuquicamata Underground Mine, location (Fuentes, 2009) ....................................28

    Figure 2.22 Chuquicamata mine (Fuentes, 2009) ..........................................................................28

    Figure 2.23 Macro blocks and geology, first level, Chuquicamata Underground Project(Villegas, 2008) ........................................................................................................29

    Figure 2.24 Ore deposit characterization (Fuentes, 2009) .............................................................30

    Figure 2.25 Position of production levels in Chuquicamata Underground Project(Fuentes, 2009) .........................................................................................................31

    Figure 2.26 Macro block method (Fuentes, 2009) .........................................................................31

    Figure 2.27 Macro block configuration in first and second levels of ChuquicamataUnderground Project (Allende, 2009) ......................................................................32

  • 8/17/2019 Villegas Mines 0052E 10549

    11/186

     

    xi

    Figure 3.1 Differences in location of the work area in classical undercutting andmechanical undercutting system ..................................................................................33

    Figure 3.2 Scheme of mechanical undercutting system in block caving (modified fromBrown, 2007) ...............................................................................................................34

    Figure 3.3 Layout undercut level for a mechanical undercutting system ......................................36

    Figure 3.4 Section layout undercut and production level in a mechanical undercuttingsystem ..........................................................................................................................36

    Figure 3.5 Plan view of undercut mine design for mechanical undercutting system in block caving .................................................................................................................37

    Figure 3.6 Illustration of mechanical undercutting system ............................................................37

    Figure 3.7 Mine design for mechanical undercutting system in block caving ..............................38

    Figure 3.8 Concept of drum miner (Frenzel, 2011) .......................................................................43

    Figure 5.1 Laubscher’s caving chart (Brown, 2007) .....................................................................63

    Figure 5.2 The basic calculation cycle of FLAC 3D (Itasca, 2012) ..............................................64

    Figure 5.3 Numerical model process (Itasca, 2012) ......................................................................68

    Figure 5.4 Process map of numerical model in block caving undercutting (Modify fromItasca 2012). .................................................................................................................69

    Figure 5.5 Plan view of numerical model mesh for one panel ......................................................70

    Figure 5.6 Configuration of model for one-panel FLAC3D ..........................................................70

    Figure 5.7 Geometry of numerical models two panels ..................................................................71

  • 8/17/2019 Villegas Mines 0052E 10549

    12/186

     

    xii

    Figure 5.8 Configuration of model for two-panel FLAC3D ..........................................................71

    Figure 5.9 Numerical model mesh for two panels .........................................................................72

    Figure 5.10 Border conditions in the numerical models ................................................................73

    Figure 5.11 Theoretical model of strain-softening (Cai, 2007) .....................................................75

    Figure 5.12 Increase in the mesh size. ...........................................................................................77

    Figure 5.13 Model of undercutting sequence for one panel ..........................................................78

    Figure 5.14 Isosurface of vertical displacement to find the steps of undercut for thenumerical model. ........................................................................................................78

    Figure 5.15 Sketch sequences of numerical models for continuous caving ..................................79

    Figure 5.16 Sequence of modelling of the pillar between panels ..................................................80

    Figure 5.17 Plot of laboratory tests in PEK (Board, 2006) ............................................................82

    Figure 5.18 Empirical thresholds for in-situ damage in moderately jointed hard rock mass(Diederichs, 2003) ......................................................................................................83

    Figure 5.19 Concept of initiation of fracture and slabbing (Stacey, 1981) ....................................85

    Figure 6.1 Scheme of analysis of stress in the cutting front ..........................................................87

    Figure 6.2 Behaviour of vertical stress with advance of the undercutting front ............................88

    Figure 6.3 Behaviour of normal stress with the advance of the undercutting front .......................88

  • 8/17/2019 Villegas Mines 0052E 10549

    13/186

     

    xiii

    Figure 6.4 Behaviour of horizontal stress with the advance of the undercutting front ..................89

    Figure 6.5 Increase of displacements with the advance of the undercutting front ........................90

    Figure 6.6 Variation of depth of fracture in the cutting front with the advance of theundercutting front.........................................................................................................91

    Figure 6.7 Prediction of fracturing in the cutting front with 120 meters of undercuttingfront advance with UCSlab and critical strain criteria .................................................92

    Figure 6.8 Distributions of tress in the cutting front of different undercutting advanceoperations in continuous caving with a 40 meters beam .............................................93

    Figure 6.9 Distributions of vertical stress in the cutting front for different lengths of beams with an undercutting advance of 180 meters ....................................................93

    Figure 6.10 High vertical displacement in the work area with a 20 meters beam .........................94

    Figure 6.11 Vertical displacements in the cutting work area with different sizes of beams .........95

    Figure 6.12 Variation of principal stress with the undercutting front advance and changeof the cutting front condition ....................................................................................96

    Figure 6.13 Variation of stress in the undercutting front for different widths of theundercutting front .......................................................................................................96

    Figure 6.14 Sequence for modelling of Panel B and pillar ............................................................97

    Figure 6.15 Mining steps in the life of the pillar between panels ..................................................98

    Figure 6.16 Monitoring of vertical stress in the middle of the pillar .............................................98

    Figure 6.17 Profile of vertical stress in the pillar to 100 meters of undercutting advance ..........101

  • 8/17/2019 Villegas Mines 0052E 10549

    14/186

     

    xiv

    Figure 6.18 Profile of vertical stress in the edge of the pillar to the position of theundercutting front .....................................................................................................102

    Figure 6.19 Fracturing zones in the pillar using UCSlab criterion ..............................................103

    Figure 6.20 Estimated fragmentation of macro blocks for Chuquicamata UndergroundProject, using BCF (Board, 2006) ............................................................................104

    Figure 6.21 Three-dimensional view of maximum wedge in work area, and oneillustrative example (Brown, 2007) ..........................................................................104

    Figure 6.22 Plan of view of maximum wedge and hydraulic roof support .................................105

    Figure 6.23 Possible wedges in the border of the beam and the caving volume .........................105

    Figure 6.24 Brittle failure in longwall face (Qing- Sheng, 2013) ................................................106

    Figure 6.25 Estimation depth fracture in the cutting face from Thesis work ..............................107

    Figure 6.26 Stress redistribution around a coal mining face (Qing-Sheng, 2013) ......................107

    Figure 6.27 Result of numerical models stress distribution (Figure 6.2).....................................107

    Figure 6.28 Collapse of the hanging wall of the working for a sub-critical support pressure (Gonzalez, 2008) ........................................................................................108

    Figure 6.29 Plasticity zones for 20 and 40 meters undercutting advances, showing theinstability zones in the roof ......................................................................................109

    Figure 6.30 Numerical model fracturing initiation and exploration tunnel condition. ................109

  • 8/17/2019 Villegas Mines 0052E 10549

    15/186

     

    xv

    LIST OF TABLES

    Table 3.1 Productivity estimation for an advance undercut with drill and blast. ..................... 40 

    Table 3.2 Muck to be removed in advance undercut. ............................................................... 40 

    Table 3.3  Parameters for estimating the productivity of a mechanical system withdifferent widths of the undercutting front. ................................................................42 

    Table 3.4  Estimate of productivities for different widths of undercut fronts. .......................... 43 

    Table 4.1 

    Matrix of evaluation of probability of occurrence (likelihood) ................................ 45 

    Table 4.2  Matrix of evaluation of impact (consequence) ......................................................... 45 

    Table 4.3 

    Matrix to identify the significant risks of the project ............................................... 46 

    Table 4.4 Identification of geomechanical hazards during the undercutting processusing a mechanical undercutting system ...................................................................54

    Table 4.5 Matrix of risk assessment ......................................................................................... 58 

    Table 5.1 Stress condition of macro block N-42 (see Chapter 2) level 1841 ........................... 73 

    Table 5.2 Properties of intact rock (Laboratory tests, Russo 2010) ......................................... 75 

    Table 5.3 Properties of rock mass (Russo, 2010) ..................................................................... 76 

    Table 5.4  Consideration of numerical models .......................................................................... 81 

    Table 5.5 Detail of numerical models built .............................................................................. 81 

    Table 6.1  Structural sets in macro block N 42 (Zaro, 2009). ................................................. 103 

  • 8/17/2019 Villegas Mines 0052E 10549

    16/186

     

    xvi

    ACKNOWLEDGEMENTS

    I would first like to express my gratitude to my first and second advisers in the mining

    department of Colorado School of Mines, Dr. Christian Frenzel and Dr. Mark Kuchta. To

    committee member Dr. Gideon Chitombo, who accepted a place on this committee and

    supported me from Australia, I offer my thanks for his friendship and advice. I also thank Dr.

    Gubb, Dr. Nakagawa, and Dr. Cohen for their help on my research.

    I would like to acknowledge God and my family for their support, motivation, prayers, and

    love: my wife Fresia and my children Fernando, Francisca, and Pía. Also, I would like to thank

    my mother and brother for their constant concern and support.

    I am very grateful to my company, Codelco-Chile, which was my sponsor during this time — 

    especially the person that encouraged me to study and supported me throughout, Mr. SergioFuentes. Thanks also to my colleagues Samuel Peñaloza and Andrea Russo.

    I thank Itasca Consulting group in Minnesota for helping me to use FLAC 3D, with special

    thanks to Dr. Loren Lorig, Thierry Lavoie, Math Pierce, David DeGagne, and my friend Mark

    Board and his wife Cathy.

    I am very grateful to my friends Matias, Beatriz, Andres, and Adalberto. Thank you for your

    friendship. And thanks to my English teacher, Joyce, for her help and sympathy.

  • 8/17/2019 Villegas Mines 0052E 10549

    17/186

     

    1

    CHAPTER 1

    INTRODUCTION

    1.1  Background

    The largest mining companies in the world have begun the construction phase of their biggest

     projects in block caving mining history. In the coming decades we will see that underground

     production rates increase more dramatically than ever before (Brown, 2007 b, Chitombo, 2010).

    Block caving is an efficient method of underground mining with a high production rate; it is the

    method currently used in the biggest underground mines around the world. It has evolved

    through time from a manual to a mechanized production operation, adapting to different rock

    qualities and stress conditions. During the application of block caving, the first activity in the

     process to generate the caving is the undercut, which uses drilling and blasting to cut the base ofthe blocks (Hustrulid, 2001).

    Modern block caving operations such as Palabora, DOZ, and El Teniente have incorporated

    changes in the sequences of mining construction. Most of these changes have been related to the

    undercutting advance, because this process causes an important increase in the abutment stress,

    which in turn damages the infrastructure near the undercutting front (Chitombo, 2010). In order

    to mitigate this effect, new undercutting variants have been incorporated which are pre-

    undercutting and advanced undercutting (Bartlett, 2000). These changes have led to an increase

    in the available area for the production and a decrease in the repair rates for the production levels

    (Araneda, 2007). However, along with these positives come negative effects in the undercut

    level, because these variants need around twice as much development in the undercut level,

    compared with the post undercut method, to compensate for the swelling factor and achieve an

    adequate undercutting blasting. This causes a decrease in the width of the pillars in the undercut

    level, which leads to reduction in strength of the pillars, causing collapses in undercut and

     production levels (Villegas, 2008).

     Nowadays, considering the deepening of mining (and high stresses due to the height of the

    rock column), the pre-undercutting and advanced undercutting variants would be the most

    adequate for a high stress condition. Nevertheless, the stability problem in the undercut level

    (specifically the pillar collapses due to the thinness of the rock pillars) has not yet been solved,

  • 8/17/2019 Villegas Mines 0052E 10549

    18/186

     

    2

    and it is necessary to make mitigation efforts. Such efforts may include pre-charge of explosives

    or use of extra support in the undercut level (Bartlett, 2000). 

    Due to a shortage of new mineral deposits close to the surface, the trend of the mining

    industry is toward underground exploitations, and block caving is the method most used and

    which provides the highest production (Brown, 2007).

    One of the main concerns during mining by block caving is to avoid leaving areas with a

    deficient undercut, which could provoke intense damage in the levels below and generate

    collapses that result in loss of productive areas. In contrast, the longwall caving method that is

    used in underground coal mining has overcome this problem. The longwall method uses a

    machine to cut the rock, a series of hydraulic shields to maintain ground stability in the work

    area, advancing and cutting the base of the rock column. The method provides absolute certainty

    that the cut of the panel is total, without the possibility of a remnant pillar (Peng, 2006).

    1.2  Justification for the research conducted

    Codelco is in the first phase of construction of the two biggest underground projects in the

    world: the Chuquicamata Underground Project and the New Mine Level, name given to the new

     production sector in El Teniente mine. They will be exploited by using the block caving method,

    with a production of 140,000 ton per day. The topic developed in this thesis is part of the aim of

    modernization of future operations through changes in the process. In this case, changes to the

    undercutting process are examined in order to ensure the cut quality and research of possible

    management opportunities from changing a discontinuous undercutting process such as drill and

     blast to a continuous process such as mechanical undercutting, eliminating or mitigating the

    negative geomechanical effects. Based on the aforesaid, this thesis proposes the possibility to use

    longwall method as a mechanical undercutting system. This is based on the experience of the

    longwall method in coal mining

    1.3 

    Objective of the research undertaken

    The main objective of this thesis is to evaluate, based on a geomechanical point of view, the

    technical feasibility of using a mechanical excavation system for undercutting in underground

     block caving.

  • 8/17/2019 Villegas Mines 0052E 10549

    19/186

     

    3

    This thesis presents a geomechanical evaluation of a proposed alternative method for the

    classical undercutting system. Advantages of the proposed undercutting system include ensuring

    the undercutting and decreasing the quantity of development in the undercut level. This in turn

    would improve excavation stability and reduce long-term costs. The use of a mechanical system

    would also offer the ability to increase the undercutting rate and offer the possibility to automate

    the system.

    In the first part of this work the possible geomechanical aspects of the use of a mechanical

    undercutting system in block caving are identified and evaluated. The objective of this new

    approach may be applied in future block caving operations. During this first part, it was

    necessary to explore all possible stability problems in different stages of the caving, and identify

    the places more susceptible to damage. Every condition is explained and illustrated for a better

    understanding. With this information, a risk evaluation was made in order to identify the mostcritical problems for the geomechanical analyses. This work should also be useful for possible

    industrial testing.

    The geomechanical evaluations of the main risks were made through analytical and

    numerical models, to identify parameters and conditions that control the stability problems and

    the alternative solutions. The numerical tool used for the geomechanical analyses was FLAC3D.

    To develop this thesis, the data of the Chuquicamata Underground Project was used.

    The numerical models were used in order to estimate the stress behavior in the undercutting

    front when the undercut front advance and the caving propagation grow, all within a scheme of

    advance undercutting similar to the longwall method.

    A resulting consideration is the evaluation of the technical feasibility of controlling possible

    stability problems in the area of the operation of the cutting system, and in the pillar between

    undercut panels, in order to permit a safe operation for equipment and people.

    Another objective is to present a rough estimation of possible productivity of a mechanical

    undercutting system compared to the classical drill and blast.

    1.4  Research conducted and methodology

    The research was conducted based on a geomechanical point of view, an evaluation of the

     possible application of a mechanical undercutting system in block caving. The bibliographic

    review was focused on geomechanical issues occurred during the undercutting process with

  • 8/17/2019 Villegas Mines 0052E 10549

    20/186

     

    4

    different undercutting methods, this due to that there are not experiences in applying mechanical

    undercutting in block caving. Because of this, it was necessary to propose a type of undercutting

    method with a mine design for mechanical undercutting. Based on the review and the Codelco

    Chile experience in block caving operations, an identification and evaluation of the possible risks

    in the implementation of a mechanical undercutting system were undertaken to recognize and

     prevent the most relevant hazards. Mining design and the rock mass properties used are derived

    from the Chuquicamata Underground Project.

    With the information previously mentioned, numerical models were completed by using

    different caving stages and different widths of the undercutting front. The results of the

    numerical models showed the stress and deformation, and the analyses resulted in obtaining a

     behavior hypothesis, which has made possible an estimation of the potential performance of the

    system’s productivity and the exercise of a comparison with the drill and blast classical system.

    1.5  Scope of the research

    This work evaluates the technical feasibility of incorporating the mechanical undercutting in

    the block caving process, from a geomechanical approach, without considering the mechanical

    design of the equipment. Currently, the equipment — such as the shearer and hydraulic support — 

    are developed for soft rock, but the technology associated with cutting tools and roof support

    capacities have grown significantly in recent years. This study is offered as a starting point

    toward the adaptation and development of this technology in block caving. Furthermore, the

    mechanical design of the equipment is beyond the scope of this work.

    The information used in the analyses and numerical models is from the Chuquicamata

    Underground Project. This project’s  characteristics, in terms of rock properties and stress

    conditions, correspond to average block caving operations elsewhere in the world. Also, this

     project sponsored the author of this thesis during the time of this research.

    1.6 

    Original contribution

     Nowadays, there is little research about undercutting system in block caving, and the latest

    innovations associated with the undercutting, such as pre and advance undercut, have increased

    the complexity of the system. In addition, the use of drill and blast system to initiate the caving

    has never been questioned.

  • 8/17/2019 Villegas Mines 0052E 10549

    21/186

     

    5

    This thesis is the first work to consider and evaluate, from a geomechanical point of view, the

    application of a mechanical undercutting system in block caving.

    In this work, there is a mine design and an undercutting sequence which would allow the

     possible implementation of a project for industrial testing. In addition, this thesis presents an idea

    about of the stress behavior with the undercut, which could be used by mining equipment

    manufacturers to design or adjust the technology necessary for this application in block caving.

    Another original contribution is a description of the possible geomechanical risk in the

    eventual uses of a mechanical system in block caving. This alternative, use a mechanical system

    to undercutting, opens the door for automation of the undercut system in block caving.

    This work is an innovation work, never before in the metallic mining industry has been

    evaluate the option of use a mechanical system to do the undercutting in block caving, therefore

    an objective of this thesis will be an original contribution to the mining engineering.

    1.7  Thesis organization

    This thesis is divided into seven chapters.

    Chapter 1 is an introduction that explains the motivation of the study and the problem

    statement, current geomechanical challenges in block caving, the objectives of the study and the

    scope of the thesis and how it is organized. Also, original contributions of this study are

    discussed and suggestions for further research are provided.

    Chapter 2 provides a literature review, which present the different block caving undercut

    alternatives, the longwall method in coal mines and an overview of the study sector which was

    used as the basis for the studies and analyses developed in this work.

    Chapter 3 in this chapter there is a description of mining method proposed for the analyses

    developed in this study, the mine design and performance for both methodologies are discussed,

    drill and blast method and mechanical undercutting, from the perspective of the implementation,

    and also gives a practical breakdown of the differences between a mechanical system and the

    classical system of drilling and blasting.

    Chapter 4 identifies and evaluates the possible geomechanical aspects in the use of a

    mechanical undercutting system in block caving, and reveals the places most susceptible to

    suffer damage. Based on this a risk analysis was done.

  • 8/17/2019 Villegas Mines 0052E 10549

    22/186

     

    6

    Chapter 5 describes the organization of numerical models used for the studies and analyses of

    the mechanical undercutting system, and also the criteria for the evaluations used.

    Chapter 6 discusses and analyzes the results of the numerical models for the different steps of

    the caving process in order to understand the behavior of the rock mass with regard to the results

    of the undercutting process.

    Chapter 7 provides a summary of the work undertaken and the conclusions drawn from this

    study.

    .

  • 8/17/2019 Villegas Mines 0052E 10549

    23/186

     

    7

    CHAPTER 2

    LITERATURE REVIEW

    2.1  Block caving method

    Block caving is a method of mining normally used in massive orebodies, in which a block of

    rock mass is defined, this block is fully undercut to initiate the caving. The undercutting process

    is performed through drill and blasting, the broken material is drawn to create a void to initiate

    the caving. The broken material is removed through the production level from the drawbells.

    Block caving is a low cost production method with high productivity, but requires

    considerable investment in mine preparation. Today, there are large mining operations that use

    mechanized block caving and some other operations have trials for automated mode Figure 2.1. 

    Figure 2.1 Typical scheme of block caving with LHD (Arce, 2002)

    2.1.1 Conceptual model of caving

    Duplancic and Brady developed a conceptual caving model (Brown, 2007) Figure 2.2. The

    model includes four zones each has different rock mass properties due to their different degrees

    of fracturing. As caving progresses, the zones change sequentially in a process of rock mass

    degradation associated with the propagation of the caving. The zones are defined as follows.

  • 8/17/2019 Villegas Mines 0052E 10549

    24/186

     

    8

    o   Pseudo-continuous domain: The virgin rock mass around the caving, without the caving

    effect. The behavior of the rock mass in general is elastic.

    o  Seismogenic zone: In this zone, the geological discontinuities start to open and new

    fractures are created. This generates seismic activity associated with damage to the rock

    mass.

    o   Zone of loosening : The rock mass in this zone has lost its cohesive strength. The rock

    mass is intensely fractured, and only has residual strength.

    o  Caving zone: This is fractured material that is to be removed through the production

    draw. It does not have cohesion properties.

    o   Air gap: The air gap is a zone that does not contain any material, which allows the caving

    to progress.

    Figure 2.2 Conceptual model of caving (Brown, 2007)

    Based on this conceptual model of caving, the behavior of stress and strain in the rock around

    the undercutting area is affected by the caving process. Therefore, the mine design is affected by

    the caving geometry (which changes with the caving propagation and the undercutting advance).

    Also, the size and the properties of the different zones defined in Figure 2.2 change, through a

    degradation process caused by continuous redistribution of stress. To estimate the behavior of the

  • 8/17/2019 Villegas Mines 0052E 10549

    25/186

     

    9

    stress/strain for any alternative or sequence of block caving using numerical models, it is

    necessary to consider the conceptual model of caving.

    2.2  Undercut methods

    Caving is initiated with the undercutting process in which the base of the block or panel is

    cut until the hydraulic radius of caving is reached (hydraulic radius is calculated dividing the

    area by the perimeter of undercut zone). The material inside the caving zone is removed through

    the drawpoints on the production level and the rock above this area collapses and the breaking

     process progresses until reaching the surface.

    The undercutting activity is critical for the success of block caving (Laubscher, 2000), so it is

    necessary to have a plan and a design for the undercut. If the cut is of low quality, it is possible

    to lose production area, due to the damage or collapse of the production level, so it may benecessary to re-install ground support or rehabilitate some zones, which delays the production

    schedule.

    The traditional undercut system is post-undercutting. Recently developed undercutting

    systems are the pre-undercut, advanced undercut, and macro block methods.

    2.2.1 Post undercut

    Post-undercutting is the classical undercut method, (Figure 2.3), all levels (undercut,

     production ventilation, transference, hammer, transport, and other) are developed before the

    undercut process begins (drilling and blasting). Therefore, in this methodology it is necessary to

    make investments in advance in order to build the necessary infrastructure. The advantage is that

    when the undercut is done the sector is incorporated immediately into the production area. In this

    method the pillars in the undercut level have more strength than that achieved with the pre-

    undercut and advance undercut methods. The drifts in the undercut level have the same distance

     between them as the drifts in the production level, which gives greater pillar strength in the

    undercut level. In addition, the undercut level is used only for undercut drilling and blasting, and

    it is not necessary to handle muck on this level.

    With post- undercuting, between one and three “drawbell lines” are blasted before the

    undercutting front passes above the draw points on the production level, to absorb part of the

    rock volume from the undercut blasting. Another advantage of post-undercutting is the relative

  • 8/17/2019 Villegas Mines 0052E 10549

    26/186

  • 8/17/2019 Villegas Mines 0052E 10549

    27/186

     

    11

     blasting. This has an important effect on the stability of the undercut level, which requires more

    support than other methods such as pre-undercut and advance undercut. However, from an

    economic point of view, this alternative has the advantage that investment in production level

    infrastructure is made shortly before the area is incorporated into production.

    Figure 2.4 Pre-undercut (Brown, 2007)

    2.2.3 Advance undercut

    In the advance undercut method, the undercut front advances ahead the blasting of drawbells

    and part of the development and construction of the production level is done before the

    undercutting front passes, Figure 2.5. This method has the advantage that it decreases the time

    necessary to complete the development and construction of the production level. Also, like the

     pre-undercut method, it requires less support on the production level. Nonetheless, the

    infrastructure developed before the undercut level needs strong support, and after the undercutfront has passed it is sometimes necessary to perform some reparation. This method increases the

    effective life of the drawpoint, compared with post-undercutting. The disadvantage of this

    method is the complexity of coordinating development, construction, and the advance of the

    undercut front simultaneously. As with pre-undercutting, the advance undercut method requires

  • 8/17/2019 Villegas Mines 0052E 10549

    28/186

     

    12

    twice the amount of development in the undercut level, to absorb the rock from the undercut

     blasting.

    Figure 2.5 Advanced undercut (Brannon, 2011)

    2.2.4 

    “Crinkle cut” layout and blasting design in advance undercutting  

    The narrow inclined undercut, or crinkle cut, corresponds to the advance undercutting most

    used in block caving (Workshop undercutting 2008). It considers two concepts: the stability of

    the undercut level and production level, and the clearance of muck generated from the blast

    (clearance of muck creates the void necessary to contain the material for the next undercutting

     blast). To improve the stability of the production level, the height of the apex of the pillar

     between the drawbells is increased, and the drawbell is formed by the inclined blasting in the

    undercut level (Butcher, 2000). In addition, the inclination helps to remove the muck because thematerial flows by gravity due to its own weight. Figure 2.6 illustrates the inclined blasting and is

     possible to see the drawbell, drilling design, blasting design and also the caving and production

    levels all in 3D.

    This design presents some problems inherent to the method (Casten, 2002). For example, it

    creates the perfect condition to generate a coarse fragmentation in the caving initiation, due to

  • 8/17/2019 Villegas Mines 0052E 10549

    29/186

     

    13

    the effect of the chevron geometry in the undercut roof. Butcher (2000) pointed out several other

     potential problem areas that must be taken into consideration when this method in used (Figure

    2.7). These include: the possibility of leaving a remnant pillar in the apex of the crown pillar due

    to poor drilling and blasting, muckpile stacking that affects the next blasting, and the requirement

    of re-drilling in some blasting holes. Another difficult part of this method is the need for strict

    control of the process: the crinkle cut requires strong discipline in the operation (Bartlett, 2000).

    Moreover, the geometry of the undercutting advance (plan view) is irregular, with high stress

    concentrations in the sharp parts, and the risk of losses of drills or abandonment of areas. Some

    solutions for this problem have been the use of pre-charges of explosives and remote control

    equipment to clear the area, in order to avoid the presence of people (Casten, 2002).

    The undercutting method is highly demanding in the quantity of meters of the drift

    development.In this method, the criterion is to open the drawbells behind the undercutting front, in a

    distress zone with a distance that normally depends on the capacity to complete the infrastructure

    of the production level (Araneda, 2007) (e.g., draw points construction, drilling of pilot shafts,

    and drilling of drawbells). The minimum horizontal distance between the undercutting front and

    the development and constructions, in the production level, is frequently the vertical distance

     between the undercut level and the production level. This is called “the 45 degree rule” (Brown,

    2007). For example, in the case of the Esmeralda sector of El Teniente Mine — despite the fact

    that the distance between levels is 18 meters — the minimum distance used was 22.5 meters

    (Jofre, 2000).

    2.2.5 Cavability

    Brown (2007) defined cavability as “a measure (often non-quantitative) of the ability of an

    orebody to cave under particular circumstances” Cavability is associated with a minimum  area

    (area of caving) and a minimum span, which is the minimum width of the undercutting front.

    This area of caving (hydraulic radius of caving, hydraulic radius is calculated dividing the area

     by the perimeter of undercut zone) has significant importance in the stability of in the

    undercutting front, because when the undercutting area achieves this value, the caving process

    starts and the roof of the cavity collapses —  which changes the abutment stress around the caving

    area.

  • 8/17/2019 Villegas Mines 0052E 10549

    30/186

     

    14

    Figure 2.6 Illustration of crinkle cut in Palabora mine (Brown, 2007)

    Figure 2.7 Crinkle cut undercut potential problem areas (Butcher, 2000)

    2.2.6 Undercutting rate

    There is not an optimal value for the undercutting rate, as it depends on the characteristics of

    the rock mass, the capacity of the development, the construction, and the production

    requirements (Flores, 2002). From the geomechanical point of view, the undercutting rate has

    influence on the stability of the abutment stress zone (Karzulovic, 2001). If the rate is very low

    or the undercutting front stops, the magnitude of the stress begins to open structures and create

  • 8/17/2019 Villegas Mines 0052E 10549

    31/186

     

    15

    new fractures (Butcher, 1999). This decreases the strength of the rock mass, provoking damage

    in the mining infrastructure. On the other hand, if the undercutting rate is too fast, it can originate

    high seismicity with the possibility of rock burst (Karzulovic, 2006). An average rate of

    undercutting is around 2,250 m2/month (Figure 2.8) (Flores, 2002).

    Figure 2.8 Relative frequency of different undercut rates in caving mines (Flores, 2002)

    2.2.7 Geometry of undercutting front

    The geometry of the undercutting front has an effect on the extent of damage ahead of the

    undercut front, basically because it can generate the stress of confinement, in the case of concave

    geometry, or traction, in the case of convex geometry. A convex geometry should be avoided

     because it generates more extensive damage (Figure 2.9) (Laubscher, 2000).

    Based on Laubscher’s work (1994), Butcher (1999) developed five rules to avoid damage in

     block caving operations. One of the most important is the geometry of the undercutting front.

    Butcher points out that the problems associated with the geometry of the undercut are the large

    irregularities in the horizontal geometry of the undercut front (cave line), which cause an

    increase in stress concentration that may result in serious damage, (Figure 2.10). Therefore, the

    horizontal irregularity in the undercut front panel should be avoided (Brown, 2007).

  • 8/17/2019 Villegas Mines 0052E 10549

    32/186

     

    16

    Figure 2.9 Confinement and traction in the undercutting front (modified from Laubscher,2000)

    Figure 2.10 Geometries of the undercutting front (Butcher, 1999)

    2.2.8 Undercutting method in high stress

    Mining in later years has demonstrated that caving methods can be applied successfully in

    strong rock mass conditions at greater depths, which increases geotechnical challenges (Flores,

    2008). Together with the deepening of mining operations, there has been an increase in stress

    conditions, (Figure 2.11). The use of post-undercutting in a condition of high in-situ stress

  • 8/17/2019 Villegas Mines 0052E 10549

    33/186

     

    17

    (Flores, 2002) causes significant redistributions of stress (abutment stress) in the caving front,

    which causes damage in the production levels that in turn affects the available production area

    and increases the number of repairs. Figure 2.12 shows the increase in stress caused by the

    undercutting advance effect in the roof of a production drift (Bartlett, 1992).

    Figure 2.11 Variation of in-situ stress with depth (Karzulovic, 2004)

    Figure 2.12 Stress conditions in the roof of production drift by effect of the undercuttingfront advance (Trueman, 2002)

  • 8/17/2019 Villegas Mines 0052E 10549

    34/186

     

    18

    Some changes in the sequence of development and construction of mining infrastructure have

     been applied to solve these problems in order to manage the stress. In high-stress conditions,

     postponing all or part of the development and construction in the production levels until the

    undercut front has passed can prevent premature damage. This causes a decrease in the width of

    the pillars in the undercut level, which leads to a reduction in strength of the pillars, difficulty the

    undercutting blasting due to the damage in the blast hole, thus causing partial blasting and

    therefore the formation of remnant pillars (Villegas, 2008) (Figure 2.13, Figure 2.14 and Figure

    2.15)  or even collapses in undercut and production levels. For these reasons, some mines are

    considering returning to the post-undercut method and will assume the costs of reparation, but

    will gain flexibility and stability for the undercut level (Araneda, 2007).

    Figure 2.13 Example of advanced undercutting front with small pillars (Workshopundercutting, 2008)

    2.2.9 Generation of dynamic stress

    In all undercutting methods used in block caving, the undercut is performed by drilling and

     blasting to cut the base of the block. This is a discontinue process that increases stress due to the

    explosive detonation and the instantaneous redistribution of stress caused by the volume

    removed from the base of the block by the undercutting blast (Aguirre, 1994).

  • 8/17/2019 Villegas Mines 0052E 10549

    35/186

     

    19

    In order to control these effects, every mine carefully plans its undercutting program and

    avoids blasting large areas or using significant amounts of explosives (Flores, 2002). Mine

     project staff normally monitors the vibrations and seismic activity to adjust the blasting design.

    The effect of dynamic stress increases if the in-situ stress condition of high stress, because it

    causes a major transfer of energy around the blasting area (Dunlop, 1999). For this reason, the

     blasting of drawbells can cause minor damage in a pre- or advance undercut method where the

    stress condition is relaxed after the passage of the undercut front (Potvin, 2010).

    Figure 2.14 Remnant pillar in undercut level (Karzulovic, 2005)

    Figure 2.15 Damage caused by collapse in production level (Karzulovic, 2003)

  • 8/17/2019 Villegas Mines 0052E 10549

    36/186

     

    20

    2.2.10 Seismicity associated to undercutting process

    The relationship between the undercutting advance with drill and blast and seismicity has

     been studied in El Teniente mine (Potvin, 2010). The conclusion reached was that there is a

    direct cause/effect relationship between the two. To illustrate this concept,  Figure 2.16 presents

    the relationship between the undercut area and the seismic events in the sector RENO of El

    Teniente Mine (historically known for the rockburst). The red line represents the cumulative

    number of significant seismic events (seismic events that the people in the El Teniente mine

    could feel) in the timeframe measured. The green line shows the cumulative undercutting area by

    drill and blast. Clearly, there is a direct relationship between the frequency of the undercutting

     blasts and the increase in seismicity.

    In addition, it is interesting to note that one of the strategies used to control the rockburst in

     block caving is to decrease the area of undercut in each blast along with the frequency betweenthe blasts, to decrease the number and magnitude of the seismic events.

    Figure 2.16 Cumulative undercut area blasted (green dots) compared to the cumulativenumber of significant events (red line) showing a very strong correlation(Potvin, 2010)

    2.2.11 Numerical models of undercutting in block caving

    The most common use of numerical models in block caving is associated to the caving

     propagation relationship with the extraction rate, namely beyond hydraulic radius, and parameter

    studies such as:

  • 8/17/2019 Villegas Mines 0052E 10549

    37/186

     

    21

    -  Geometry of the cutting front during the font advance, in order to study the stability of

    undercut and production levels. Also, these analyses allow selecting the suitable,

    undercutting method (Brown, 2007).

    - The caving rate, in this case the focus is on trying to predict when and how the fracturing

    arises in the surface. This is important information in the transition from open pit to

    underground method (Brown, 2007).

    - The dilution prediction, this is a key economical factor, because it is related to the

    mineral recover and it is an input for planning the needs of reposition of the production

    area (Board, 2009).

    - Subsidence estimation, this prediction is important for the location of infrastructure,

    shaft, crushers, and other that can be affected by the caving process. In addition, this

     parameter may be related to with the dilution entry (Board, 2006).

    Usually, the numerical models in block caving are three dimensional, because the caving

     process affects the whole rock mass around the caving volume.

    There is a significant uncertainty on the transition from intact rock to caving material

    (Sainsbury, 2010), the propagation rate of caving and the relation between the rock mass quality

    and the stress condition. In general, the numerical model of caving uses strain softening as

    constitutive property, which through the evaluation of “critical plastic strain” adjusts the rock

     properties and simulates the rock mass degradation around caving volume.

    2.3  Longwall mining method

    Longwall mining is a highly mechanized underground cave mining technique that is usually

    used to extract a seam from a bedded sedimentary deposit such as coal or trona. Seam heights

    are in the range of 2 to 5 m, which is relatively thin compared to block caving column heights

    Within non-metallic underground methods, longwall method has the highest productivity

    (Haycocks, 1997). The drawback is the high capital cost of equipment and installation (Energy

    Information Administration, 1994). The main components in longwall are hydraulic roof support,

    a cutting machine, and an armored face conveyor (Figure 2.17) (Mitchell, 2012).

    The longwall system advances along a full face wall of rock with a cutting machine, and

    loads the coal mineral into a conveyor system parallel to the cutting face. A shield of hydraulic

  • 8/17/2019 Villegas Mines 0052E 10549

    38/186

     

    22

    support that advances together with the undercutting front advance protects the whole equipment

    system. Behind the shield support, the roof collapses, filling the cavity (Mitchell, 2012).

    This method is used mainly in soft rock such as coal or potash. A disadvantage of longwall

    mining is the high level of skill and training required for personnel operating the system (Energy

    Information Administration, 1994). Moreover, if some of the components have problems, it stops

    the entire production.

    Figure 2.17 Classic schematic of longwall, in a coal mine (Energy InformationAdministration, 1994)

    2.3.1 Mine design

    A typical layout for a longwall coal mine is given in Figure 2.18. A series of roadways called

    main entries service a section of the mine. The roadways are developed using continuous mining

    machines (Peng, 2006). These entries are used for the main mine ventilation system, and provideaccess for people, machinery, electrical supply, communication systems, water pump out lines,

    compressed air lines and gas drainage lines.

    The longwall design is related to the geometry of the coal seam such as height, dip, depth etc.

    and the production requirement (Peng, 2006). The geological and geotechnical investigations are

    very important to design suitable longwall application and choose the equipment properly.

  • 8/17/2019 Villegas Mines 0052E 10549

    39/186

     

    23

    Parameters such as water table, aquifers, faults and lithology of the rock columns, may define the

    success or failure of the method implementation. During the longwall designs is necessary to

    estimate the longwall production and define the width and length of the panel (Energy

    Information Administration, 1995), the number of entries, size of pillars, advance rate, advance

    direction, ventilation requirements and others.

    A panel of coal to be extracted is blocked out using entries along the sides of the panel and

    connected together across the end of the panel. The pillars formed between adjacent entries are

    called chain pillars. In a developed longwall panel, the headgate is the entry where the belt

    conveyor system, the stage loader and crushing system used to transport the extracted coal are

    located. The tailgate entries are on the opposite side of the panel and are used to complete the

    ventilation circuit to remove methane and dust from the longwall cutting face. A barrier pillar is

    often left at the end of the panel to protect the main entries. Panel dimensions range from 150 to300 meters wide, and 1000 to 3500 meters long.

    Other typical longwall drift are bleeder entries (allow the ventilation to eliminate the methane

    concentration) and the main entries that allow the connection with other panel and access to the

    surface (Energy Information Administration, 1994). Longwall could be advancing or retreat type.

    In the advancing type the gate roads are formed as the coal face advances (Wikipedia, 2014). In

    retreat longwall the panel is formed by driving the headgate, tailgate and development before the

    cutting face advances. Figure 2.18 shows a classical longwall retreat design.

    2.3.2 Production system

    Currently in longwall all the production systems are mechanized. The roadways are

    developed using continuous mining machines (Peng, 2006). The production is obtained cutting

    the coal seam or other mineral to full face using a cutting machine called  shearer , which consists

    in a drum with cutting picks (between 40 to 60) which cuts the rock in a continuous way. The

    rock falls over a conveyor system (AFC armored face conveyor ) and is extracted by means of a

     belt system to the surface. The production operation is in the face, to protect the people and

    equipment a shield  is used, which consists in hydraulic jacks that support the roof and advances

    coordinately; Figure 2.19 shows the production system (University of Wollongong, 2014).

    The shearer haulage system is attached to the AFC, through a mechanical interface, the

    system pushes the drum to the face and this rotates cutting the coal, also the AFC is connected

  • 8/17/2019 Villegas Mines 0052E 10549

    40/186

     

    24

    with the hydraulic shield and everything is an interconnected system (University of Wollongong,

    2014).

    Figure 2.18 A typical longwall coal mine layout showing the panels, entries, and chain pillars, (Source: Ch13.8, SME Handbook, 2011).

    Hydraulic shield is the system used to support the roof, this allows the work of the cutting

    machine and protects the people and production equipment (Barczak, 1992) (Peng, 2006):

    The relationship between the support load, generated by a shield support and the stiffness of

    the support in terms of roof convergence, prior to generating the yield load is critical to control

    the roof above the work area (Mitchell, 2012). The purpose of hydraulic shield support is to

     prevent or delay the failure of the roof during the mining operation (Barczak, 1992).

  • 8/17/2019 Villegas Mines 0052E 10549

    41/186

     

    25

    The AFC, is formed for short sections, called pans, which allows to move the material from

    the cutting face. The section is 1.5 meters long average, the transport velocity is around 1

    meter/second. The AFC is installed in front of the hydraulic support and behind shear system.

    All the system advances together.

    In longwall, a crusher is used to reduce the coal fragment to the appropriate size for the belt

    design and then it is loaded onto the first conveyor belt by the BSL (Beam Stage Loader) (Peng,

    2006).

    The components of the longwall machine are highly integrated and controlled by a

    computerized control system. When the shearer passes, individual shields are advanced forward,

    and the entire longhwall system advances thereby together in a systematic fashion.

    Figure 2.19 Overview of longwall system, main equipment (University of Wollongongwebsite, 2014)

    2.3.3 Numerical model of longwall

    The numerical models are widely used in the longwall studies. The main analyses are related

    to the stability of gates (Shabanimashcool, 2012), in order to ensure the safety of the workers and

    infrastructure stability, also the numerical models are used to evaluate the mine design, panelorientation and effect of undercut advance (Chen, 1998) (Qing- Sheng, 2013). Regarding design

    of pillars, chain pillars and yielding pillar, numerical model are used to estimate the strength of

     pillars (Badr, 2002).

  • 8/17/2019 Villegas Mines 0052E 10549

    42/186

     

    26

    The hydraulic support and shield support, are inherent aspects to the longwall method, in

    which is necessary to estimate the load variation during the undercut front advance (Barczak,

    1992), namely the stress and deformations, for these analyses numerical model helps to predict

     possible behavior in different rock mass conditions. In order to study the behavior of these

     parameters, the numerical model must incorporate the strength of rock mass beyond the peak

    strength, incorporating the residual strength parameters. With these concepts most of the

    numerical models have used strain softening as constitutive property (Ozbay, 2003).

    On the other hand, the longwall method is a caving method, the mineral is extracted and the

    cavity is filled by surrounding material, fracturing advances in vertical direction (Peng, 2006).

    Velocity and magnitude of vertical movement depend on the depth of exploitation and the rock

    mass properties, causing subsidence as a consequence (Keilich, 2006). In cases when there is

    infrastructure in the surface models are used to study the possible effects (Zhang, 2013).Figure 2.20, shows an example of numerical model in longwall to study the abutment stress

    around a panel (Wei, 2011).

    Figure 2.20 Three dimensional model (Wei, 2011)

    The numerical models in longwall method and block caving method during the modeling of

    undercut process are similar, only with the difference in the damage caused by the blasting used

  • 8/17/2019 Villegas Mines 0052E 10549

    43/186

     

    27

    in the undercutting process in block caving, which is normally confined, this changes the rock

     properties estimation around of the undercutting area, Hoek 1998 presents a correction factor

    “D” to re present this effect in the rock mass properties (Cai, 2007). Another important difference

    is that in the block caving the mineral column is extracted and the draw process must be

    modeled.

    2.4  Chuquicamata underground project

    This work considers using the stress condition and the rock properties of a real case, where

    the mechanical undercutting could be applied.

    In this case the Chuquicamata underground project information is considered to be

    appropriate, because this project is in the construction phase and is possible to evaluate the

    option of using a mechanical system to do the undercut.

    2.4.1 Chuquicamata mine

    Chuquicamata mine is an open pit mine located near Calama, II Region of Antofagasta,

    1,650 kilometers north of Chile’s capital, Santiago. It is approximately 2,900 meters above sea

    level (masl) (Figure 2.21). Chuquicamata started its operations in 1915, although the high quality

    of the ore has been well known for centuries, dating back to the prehispanic cultures that

    inhabited the region. The production is 443,381 metric tons of fine copper electrorefined,

    electrowon cathodes, and copper concentrates. In 2011 Chuquicamata had 6,527 employees

    (CODELCO, 2011). Today Chuquicamata is a big open pit 4.9 kilometers long, 2.9 kilometers

    wide and 1.0 kilometers deep Figure 2.22 (Allende, 2009).

    Chuquicamata plans to change its mining method from open pit to underground, because the

    open pit is approaching to the end of its economic mine life. The Chuquicamata Underground

    Project considers recovering around 1,700 million tons of ore with an average grade of 0.71%

    Cu, 499 ppm of Mo and 460 ppm of As, over an operational period of approximately 45 years.

    The studies to date suggest that the earliest start of production for the underground mine would

     be towards the end of 2018 at a rate of 4,000 tpd (metric tons per day) of ore from tunnels

    development. The production will increase in 2019 by supplementing with ore from the

     beginning of caving activities, followed by a production ramp-up to achieve the design capacity

    of 140 ktpd (Fuentes, 2009).

  • 8/17/2019 Villegas Mines 0052E 10549

    44/186

     

    28

    Figure 2.21 Chuquicamata Underground Mine, location (Fuentes, 2009)

    Figure 2.22 Chuquicamata mine (Fuentes, 2009)

    The project has considered four exploitation levels, starting in the central area and then

    advancing north and south. Two blocks were planned to test new technologies. These blocks will

     begin together with the regular exploitation blocks. This thesis uses the information from one of

    those blocks, block N 42 (Figure 2.23), for the different studies.

  • 8/17/2019 Villegas Mines 0052E 10549

    45/186

     

    29

    Figure 2.23 Macro blocks and geology, first level, Chuquicamata Underground Project(Villegas, 2008)

    2.4.2 Geology

    The mineralized area of the Chuquicamata deposit is found in a tertiary intrusive body in theimmediate footwall of the West Fault. This intrusive unit corresponds to a porphyric stockwork

    of granodiorite composition, known as the Chuquicamata Porphyry. This unit has various

    textural and hydrothermal alteration differences that allow it to be subdivided into various units,

    including sericitic, potassic, and chloritic domains (Figure 2.24). The mineable portions of the

    ore body are found in the sericite-altered rock mass within the immediate footwall of the West

    Fault. The highest ore grades (>1% Cu) are found directly adjacent to the fault in the highly

    altered and weak RQS, QS) and porphyry (Porphyry East Sericitic, Porphyry East Potassic (K),

    and Porphyryc East Choritic) units. The immediate hanging wall of the West Fault is a heavily

    sheared, poor-quality Fortuna Granodiorite that increases in rock quality with distance away

    from the West Fault (Board, 2006).

  • 8/17/2019 Villegas Mines 0052E 10549

    46/186

     

    30

    Figure 2.24 Ore deposit characterization (Fuentes, 2009)

    2.4.3 Mining method

    The mine exploitation method being used is the block caving method, in four levels (Figure

    2.25). Two levels will be simultaneously in operation during the production (Fuentes, 2009).

    When the underground mine starts, the open pit operation should be stopped. There is not

    consideration of a transition time with both operations working.

    In this project, the block caving method has been modified to the variant called “macro

     block” (Figure 2.26). This mining method offers advantages in cost and production capacity

    (Fuentes, 2009). The characteristic of this method is to separate and group the activities of

    developments and construction in one sector without interferences from other activities.

    The advantages of macro block method with respect to panel caving are:

      It gives more flexibility in production planning, developments of mining infrastructure,

    and other operations.

      It is suitable for the geometry of the Chuquicamata’s ore body (long and thin).

     

    The modular design allows the incorporation of technological changes more easily.

  • 8/17/2019 Villegas Mines 0052E 10549

    47/186

     

    31

      Major collapses in the production areas could be isolated easily.

     

    The activities of development, construction, and undercutting are separated from the

     production operation with the possibility of achieving a better index of productivity.

    Figure 2.25 Position of production levels in Chuquicamata Underground Project(Fuentes, 2009)

    Figure 2.26 Macro block method (Fuentes, 2009)

  • 8/17/2019 Villegas Mines 0052E 10549

    48/186

     

    32

    The macro block method was developed during the Chuquicamata Underground Project as a

    way of managing mining preparation and production administration. It is a variant of block

    caving, but with larger block size and with a pillar to separate the macro blocks. Its configuration

    was developed by the Chuquicamata Underground Project to confront the important need of

     preparing and replacing the depletion area in order to keep production over 140,000 tons/day

    (Fuentes, 2009). With this configuration, it is possible to isolate zones that have stability

     problems such as collapses, air blast risk, and mud rushes without stopping new areas from being

    incorporated into the production. The macro block method is a variant of block caving that offers

    great management opportunities to organize the activities of construction and production. Each

    macro block could be considered an independent unit with its own mine design and organization.

    Figure 2.27 shows the macro block configuration for the Chuquicamata Underground Project

    (Villegas, 2008). The method gives flexibility to incorporate new technologies or adjust designs.Each macro block should have enough area to initiate a new caving. In addition, each new macro

     block should have a special draw system, to control the dilution from neighboring blocks

    (Fuentes, 2009).

    Figure 2.27 Macro block configuration in first and second levels of Chuquicamata UndergroundProject (Allende, 2009)

  • 8/17/2019 Villegas Mines 0052E 10549

    49/186

     

    33

    CHAPTER 3

    UNDERCUTTING WITH A MECHANICAL SYSTEM

    3.1  Block caving mine designs with mechanical undercutting

    This work presents an alternative to the use of the drill and blasting method for the

    undercutting process; in this case, using a mechanical system similar to the one used in a

    longwall panel in underground coal mining. For this idea to be feasible, the undercutting process

    should be compatible with the production process. Therefore, it is necessary to have a mine

    design that incorporates both activities.

    In the longwall panel method, the undercut front advances as the coal is cut and removed

    and behind it, the overlying rockmass collapses and is left behind, this area is called the Gob. In

    the block caving case, the Gob area is above the production level, where the caved rock isremoved through drawpoints.

    One important aspect to consider for the implementation of this mechanical undercutting

    system in block caving is the undercutting process, because when undercutting in block caving is

    developed, in any of its forms, the undercutting activity is located ahead of the cutting front, but

    in a mechanical system such as longwall is located behind the cutting front — namely, inside of

    the caving, Figure 3.1. 

    Figure 3.1 Differences in location of the work area in classical undercutting andmechanical undercutting system

  • 8/17/2019 Villegas Mines 0052E 10549

    50/186

     

    34

    When applying a longwall like mechanical undercutting system in block caving, the

    cutting process is accomplished from the inside of the undercut area. Therefore, when using a

     block caving exploitation system, it is necessary to separate the undercutting zone from the

     production zone or caving volume (where caving grows by the extraction process) Figure 3.2. 

    This is possible using pre or advance undercut. In this configuration, the cutting system advances

    along with the undercut, and the drawbells are opened in the back to incorporate the area into the

    caving. For this reason, it is important to understand what might be the effect of the caving

    advance in the undercutting process, which is studied in Chapter 5.

    Figure 3.2 Scheme of mechanical undercutting system in block caving (modified fromBrown, 2007)

    3.1.1 Undercutting mine design

    The layout of the mine design for a mechanical undercutting system should consider the

    following requirements.

    Access to the cutting front is needed for:

    o  The assembly and disassembly of the undercutting machine,

    o  Access to the work face for operation and maintenance of equipment,

    o  Ventilation of the front face, and

    o  Handling of muck.

  • 8/17/2019 Villegas Mines 0052E 10549

    51/186

     

    35

    Separation of undercut panels is needed for:

    o  Allowing access to the next panel to be undercut

    o  Use of all the potential associated with the block caving method by macro blocks.

    Dividing a panel to reduce the width of the undercutting front provides:  

    o  Control of the stability in the work area, and

    o  The ability to increase the rate of the undercutting front advance.

    The design proposed as shown